City Manager: Joe Neeb WWTP Superintendent: Daniel Mendiola

Waste Water Treatment Plant

The wastewater treatment plant treated 1,163,290,000 gallons of water for the year. Started to discharge to the Rio Hondo on November 25, 2019. Will continue until the farmer requests the water for irrigation. The plant was allocated monies for several projects for the 2020 fiscal year. The PO for refurbishing the drying bed has been issued and awaiting the construction crew to commence the project.

City of Roswell Sewer Crew The “Right of Entry� forms for the 5th and Orchard sewer line projects have been returned and engineering can continue with the data gathering of line to be replaced. This will go out to bid in early spring of 2020.

Manhole rehab for 2019 is complete and 2020 rehab will go out to bid in early spring of 2020. There is a need to repair 3 (three) manholes on private property located on 2400 E 19th. The manholes will arrive 1/3/2020 the cost for this The road project for the repaving of the road repair is slightly over $60,000.00 from gate to gate will begin in the spring of 2020 The 2008 Vactor was sent out for repair, due to the weather. repairs have been made, the cost for repairs is Awaiting bids to reroof the digester roof, facility approximately $80,000.00 maintenance is handling this project. The city council gave the approval to move forward with the loan for the dewatering building project. As of yet have not heard anything back from the state.

Roswell Test Facility An offer was made to purchase the RTF (Roswell Test Facility) located on East Second St. The amount offered was $1.00. This will go back out to bid to see if there are any real potential buyers.

River Discharge and drying bed # 1

City of Roswell Lab The city lab currently has no projects for this fiscal year. The lab is in need of some upgrades. The hood vents are passing inspection but no guarantee on how long they will last. Also the flooring is starting to show a lot of wear in some areas. The square tiles have a lot of cracks in them. A request for a quote of an upgrade will be made in February. This is to get an idea of the potential cost of upgrading the city lab.

Manholes needing repair and Vactor truck

89


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
City of Roswell Annual Report 2019 by City of Roswell - Official - Issuu