HSEFeb2013

Page 1

JGC-Tecnimont Joint Venture

MONTHLY SAFETY MEETING for February 2013

Habshan 5 IGD Project, Abu Dhabi, UAE


PRESENTATION AGENDA                 

Monthly Meeting February 2013

Project Lost Time Injury Frequency Rate & Recordable Frequency Rate; Days and Man-hours without LTI and Days and Man-hours without RI; JV Monthly Medical Consultation for February 2013; Cumulative Up to January 2013, FAC Body Part for February 2013; Manpower & Observation Up to February 2013; Area Violation, Incident Violation for the Month of for February 2013; Noncompliance with safe work Issues for February 2013; Poor Housekeeping Issues for February 2013; Equipment & Tool Issues for February 2013; PPE Issues for February 2013; JV Risk Assessment Graph, High Medium & Low Risk Analysis; NM, UC & UA Observation Report and Trend Analysis for JV; Toolbox Meeting, Safety Moment; Training Man-Hours Up to February 2013; Monthly KPI and Target 2010 – 2013; Safety Achievement for February 2013; Commissioning Activities & Safety Campaign for February 2013.


Lost Time Injury Frequency Rate Lost Time Injury Frequency Rate

Target LTIR = 0.02

LTIR

0.04

0.01 0.02 0.002 0

MONTH

Construction

Period

To Date

Man-Hours

3,139,434

125,553,837

LTI

0

1

LTIR

0.00

Days w/o LTI

591

0.002

0.01

Up to 1/3/2013

Date of Last LTI Case

19-Jul-11

Man-Hours Worked Since Last LTI

90,932,858

Total Recordable Injury Rate

TRIR

Total Recordable Injury Rate 1.20 1.00 0.80 0.60 0.40 0.20 0.00

MONTH

Target TRIR = 0.20

Construction

Period

To Date

Man-Hours

3,139,434

125,553,837

Recorable Case

0

33

0.27

TRIR

0.00

0.05

Days w/o Rec. Case

0.003 0.002 0.002 0.002 2010 2011 2012

2013

0.05

0.27

Up to Up to 1/3/2013

110

Date of Last Rec. Case

11-Nov-12

Man-Hours Worked Since Last RI

14,123,548

LOST TIME INJURY FREQUENCY RATE - PROJECT YEARLY STATISTICS

0.02

0.00

FIRST AID CASE COMPARISON TABLE 3 2 1 0

PTD

RIR, LTI x 1,000,000/man-hours - Company RIR, LTI x 200,000/man-hours - JV

3

3 1

1


JV DAYS & Man-hours Without LTI Up to February 2013

Monthly Meeting February 2013

Date of Last LTI Case : 19th July 2011

90,932,858 100,000,000 80,000,000

up to Mar. 1, 2013

60,000,000 40,000,000

20,000,000 0

January 7, 2010 Starting Project

0


JV DAYS & Man-hours Without Recordable Up to February 2013

Monthly Meeting February 2013

Date of Last RI Case : 11th November 2012

35,000,000 30,000,000 25,000,000 20,000,000 15,000,000 10,000,000 5,000,000 January 7, 2010 0 Starting Project

14,123,548 up to Mar. 1, 2013

0



JV Monthly Medical Consultation

Monthly Meeting February 2013

320

Others, Backache, Muscular Pain, Toothache, Etc. Heat Stress

0 0

Major Accident/Injury

0 0

First Aid Minor Scratches, Bruises, Laceration, Abrassions, Insect Bites, Etc.

0 1 77

Skin Infection / Allergy

357

110

EENT (Eyes, Ear, Nose and Throat)

1,596

432

34 22

Systemic Problem Hypertension Etc.

76

Gastro-Intestinal Disorder (Diarrhea Abdominal Pain) Etc. 8

Genito-Urinary Diseases

394 186

143

Respiratory Problem (Cold,Cough etc.)

0 JGC

914

500 TCM

1000

1500

2000


CUMULATIVE Up to February 2013

Monthly Meeting February 2013

Recordable- 33

Reportable - 483

LTI, 1

RWC, 8

MTC, 24 FAC 483

FAC-First Aid Case | MTC-Medical Treatment | RWC-Restricted Work Case LTI-Lost Injury Incident


FAC by Body Part For the Month of February 2013

Monthly Meeting February 2013

Shoulder



Manpower and Observation Manpower

Monthly Meeting February 2013

Observation

13,301 11,894

2,244

2,235


Monthly Meeting February 2013


184 Observation Issues

Area Violation by Issues for the Month of February 2013

Monthly Meeting February 2013

420 Observation Issues 1 Near Miss 1 Near Miss 1,277 Observation Issues

1

40 Observation Issues 71 Observation Issues

29 Observation Issues

121 Observation Issues

93 Observation Issues


February 20, 2013 (PTW) Confined Space Violation @ Unit 550 People Potential Consequences (1-5)

4

Probability of the potential consequence occurring (A-E)

A

High, Medium , Low

M

Asset

Env

Monthly Meeting February 2013

Reputation

1ST

1st February 12, 2013 Hit by JCB @ A400

Incident Violation Indicator Area Focus for the Month of February 2013

People

Asset

Env

Reputation

Potential Consequences (1-5)

1

1

1

Probability of the potential consequence occurring (A-E)

C

C

C

High, Medium , Low

L

L

L


February 19, 2013 Work started (internal cleaning) with the supervision of PTW PICWS and KN Supervisor.

February 19, 2013 Commissioning PTW was issued for the work

February 20, 2013 PTW Signatories done worksite endorsement.

February 19, 2013 Cleaning completed ,but no internal inspection has carried out by EU and TCM.

14:50

15:00

February 19, 2013 Confined Space Gas Test done by TCM Area Commissioning HSE

06:30

18:00 Date : 20-02-2013

Date : 19-02-2013

14:15

06:45

February 20, 2013 Confined Space Gas Test done by TCM Area Commissioning HSE

TIMELINE INCIDENT @550-H-102


TIMELINE INCIDENT @550-H-102

February 20, 2013 Confined Space Gas Test done by TCM Area Commissioning HSE

February 20, 2013 PICWS Signed the work site endorsement in the PTW

TIME Date : 20-02-2013

06:55

13:30

February 20, 2013 @ IES 506 Punch list closure of interlock started with no request of isolation

14:10

15:30

February 20, 2013 2 EU,1 TCM & 1KN employers went inside vessel 550H-102 for visual inspection.

February 20, 2013 Pilot Igniter sparks / Inspection suspended ,EU operator straight inform to GASCO HSE and TCM Supervisor went to TCM PTW Office to inform HSE.

15:45

16:20

February 20, 2013 EU HSE got the call from EU Shift controller about the situation.


February 20, 2013 EU HSE /Operator and TCM HSE Personals arrived together to the incident scene and EU Suspended all activities in the unit 550.

17:00

07:30- 11:30

18:00

February 20, 2013 EU called for the incident meeting and created a investigation team for next days investigation.

Date : 21-02-2013

Date : 20-02-2013

TIME

February 21, 2013 A detailed investigation made, that lasts for 4 hours and concluded in findings and recommendations from EU.

Timeline Incident @550-H-102


Finding out the route cause of the incident

February 20, 2013 EU HSE /Operator and TCM HSE Personals arrived together to the incident scene and EU Suspended all activities in the unit 550.

TIMELINE INCIDENT @550-H-102


Result of InvestigationMonthly – Part II Meeting November 2012 IMMEDIATE CAUSE Failure to de-isolate the ignition pilot @ 550-H-102 . (As per the finding there was no instrument isolation been in place ,only mechanical isolation done. )

Route Cause : 1. Failure to implement the control of PTW. 2. Issuer did not verify the work site preparation and initial the permit. 3. Lack of knowledge about the commissioning PTW system , both for ISSUER/RECIEVER OR PICWS. 4. JSA is too generic and missing the major controls like LOTO. 5. Poor communication between the PTW Issuer and receiver. 6. Poor work coordination between different work groups. 7. Instrumentation group were working inside the IES 506 without permit. 8. Pilot tested /Not de-energized.


Result of InvestigationMonthly – Part II Meeting November 2012 Recommendations: 1. All PTW which is requires EU sign earlier prior to get a permit , now they need daily counter sign from EU prior to start the job.. 2. Re organization of the Shift controller assignments by assigning one shift controller in each units by TCM Commissioning Dept. 3. Risk assessment and JSA need to be updated to ensure that documents are prepared specific for the job. 4. Safety Alert which is related to the Incident need to be issued/released with immediate effect. 5. Log Entry Register for Energisation/de- energisation of the equipment ,panels and this need to be visible in the each substation access control point. 6. Commissioning PTW requires in sub station /IES buildings ,regardless what activity they are going to perform. 7. All signaturies and those people involved in the incident related activity in IES 506 need to go for refreshment training. 8. Training (Commissioning.PTW) module need to be cross checked , reviewed and comprehensive to ensure that signaturies are well known their roles and other signaturies roles.


LESSON LEARNED

No work is so urgent that could endanger human life

TIMELINE INCIDENT @550-H-102


JV Job Safety Observation

Monthly Meeting February 2013

Noncompliance with safe work

Poor House Keeping

Equipment & Tool

PPE


Noncompliance With Safe Work (A)

Monthly Meeting February 2013


Noncompliance with Safe Work (A) Others

Monthly Meeting February 2013


Poor House Keeping (B)

Monthly Meeting February 2013


PPE (D)

Monthly Meeting February 2013


Equipment & Tool (C)

Monthly Meeting February 2013


JV Risk Assessment Graph Jan 2013 1400

1,300

Monthly Meeting February 2013 January 2013 – 2,244 February 2013 – 2,235

Feb 2013 1,275

1200 1000 800

600 400

431

524

513

436

200 0 Low

Medium

High


Near Miss, Unsafe Act and Unsafe Condition Observation Report and Trend Analysis 1800 1600 1400 1200 1000 800 600 400 200 0

Monthly Meeting February 2013

1,692 1,639

552

596

Jan-2013

Feb-2013

FAC-First Aid Case | MTC-Medical Treatment | RWC-Restricted Work Case | LWC-Lost Work Case | FAT – Fatality LTI-Lost Time Injury

513 524

3

1

0 0

0 0

0 0

0 0

0


Toolbox Meeting & Safety Moment Monthly Meeting February 2013


Total Training Man-Hours 2,480,766

Monthly Meeting February 2013



Monthly KPI and Target 2010 – 2013 Monthly Meeting February 2013 Fatality Rate

1

1

0.03

Lost time Injury Frequency Rate

Target 0.02

0.02 0.01

Target 0

0

0 Actual Fatality

Actual LTIR

Target Fatality

Total Recordable Injuries Rate 1.20 1.00 0.80 0.60 0.40 0.20 0.00

0.002

Target 0.20 0.05

Actual RIR

Target RIR

4000 3500 3000 2500 2000 1500 1000 500 0

Target LTIR

Observation + Near Misses Cases

Target >1000 2,235

Actual (Observation + Near Misses) Target (Observation + Near Misses)


Monthly Meeting October 2012


Commissioning Safety Alert

Monthly Meeting February 2013

18 Safety Alert Issued during February 2013 113 Safety Alert Issued Cumulative as of February 2013


Safety Achievements for February 2013

Monthly Meeting February 2013


Safety Achievements for February 2013

Monthly Meeting February 2013

90 Million Safe Man-hours 80 Million Safe Man-hours 60 Million Safe Man-hours

20 Million Safe Man-hours 10 Million Safe Man-hours


Monthly Meeting October 2012


Safety Campaign

Monthly Meeting February 2013



Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.