FORT PIERCE Strategic Plan 2021 Goals GOAL 8: Porpoise Park Design: Funding and Direction Key Issues Parking Lot Connection to Beach Crossing Natural Dunes
1. CONFERENCE AGENDA: Design and Proposed Budget 2. Bid Project 3. DECISION: Award construction contract 4. Open
2/21 8/21 10/21 1/22
Responsibility: City Engineer
June 1, 2021 Update Currently awaiting review by FDOT for approval of the north driveway connection to S.R. A1A. Plans and bid specifications are ready for bidding upon approval by FDOT.