1 minute read

GOAL 10: King’s Landing Development: Site Plan

GOAL 10: King’s Landing Development: Site Plan

Key Issues

 Site Plan 1. Developer submits site plan

4/21 2. TRC Review 5/21 3. Historic Preservation Board Review 5/21 4. Planning Board Review 7/21 4. DECISION: Approval 9/21

Responsibility: City Manager

June 1, 2021 Update

Audubon Development submitted a complete Design and Development Review Application package which is currently being routed through various city departments.