GOAL 8: Porpoise Park Design: Funding and Direction
GOAL 8: Porpoise Park Design: Funding and Direction
Key Issues
Parking Lot Connection to Beach Crossing Natural Dunes 1. CONFERENCE AGENDA: Design and
Proposed Budget 2/21
2. Bid Project 8/21 3. DECISION: Award construction contract 10/21 4. Open 1/22
Responsibility: City Engineer
June 1, 2021 Update
Currently awaiting review by FDOT for approval of the north driveway connection to S.R. A1A. Plans and bid specifications are ready for bidding upon approval by FDOT.