FORT PIERCE Strategic Plan 2021 Goals GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions Key Issues Design Construction Funding
1. Prepare report 2. CONFERENCE AGENDA: Report Presentation and Direction 3. DECISION: Design Contract 4. Complete design 5. DECISION: Award construction contract 6. Construction
8/21 10/21 12/21 3/22 5/22 2022
Responsibility: City Engineer
June 1, 2021 Update Revised Agreement of Understanding was submitted to Lawnwood Regional Medical Center for review and approval. This is a necessary item for the approval from FDOT permitting the creation of the Seaplane Base. Anticipate response by July 1,2021.