FORT PIERCE Strategic Plan 2021 Goals GOAL 7: Means Court Redevelopment Strategy: Development Key Issues School Utilization Lincoln Theater Highwaymen Area Development Overall Vision Preservation of History and Heritage Grocery Store Land Acquisition
1. Develop comprehensive RFP on redevelopment strategy 2. FPRA PRESENTATION: RFP and Direction 3. Issue RFP 4. Evaluate responses and prepare recommendations 5. FPRA DECISION: Award Contract
4/21 4/21 4/21 7/21 8/21
Responsibility: City Manager
June 1, 2021 Update RFP# 2021-027 was advertised April 22 and 29. A Pre-bid Conference was held on May 20, 2021 and was attended by five (5) interested proposers. The original proposal due date, 3:00 p.m., June 7, 2021, has been extended to 3:00 p.m., June 22, 2021 due to needed clarification of bid proceedings.