PIGGING & ILI
Successful start to 2022 Pipe Tek has completed the construction of the pipeline at Tingira Street, Pinkenba, Queensland, as part of the Ampol Cross River horizonal directional drilling project with Pipeline Drillers.
A
s a hard-working pipeline testing firm based in Brisbane, Queensland, Pipe Tek has grown its business from its original establishment in 1953 as Tank Calibrators to what it is today. Managing Director Myles Brannelly tells The Australian Pipeliner that the recent project the company completed included welding, nondestructive testing, coating and pre-testing works. âWe hit the ground running with our direct approach to safety, with the HDD drilled by Pipeline Drillers and pulled though in January 2022,â he says. âPipe Tek conducted the post hydrotest, cleaning and drying of the section. âBefore you place a new pipeline into commission, itâs essential to test it thoroughly for leaks or other issues with structural integrity. This process usually involves hydrostatic testing, wherein your pipeline is filled with water and pressurised. âGetting water into the pipeline for
hydrostatic testing without allowing air to pass into the pipes is a key responsibility for all pipeline pigging companies. At Pipe Tek, we are proud to have an average air inclusion rate of 0.08 per cent. For reference, the maximum air allowance is 5 per cent, while the standard recommended rate is 0.2 per cent. By keeping our numbers low, we provide practical pigging services without compromising on safety.â As part of the contract, Pipe Tek was also responsible for cleaning and drying the section of the pipeline. Through the companyâs pipeline pigging services, it uses a mix of foam pigs, refrigerant dryers and desiccant, to eliminate water from the pipeline to dew points of -40°C. This process prevents corrosion and keeps moisture out of the product flow. âIn addition to the drying process, Pipe Tek used pipeline
cleaning pigs to remove debris from the pipeline, maximising flow and efficiency. Depending on the project, we use a variety of brush, bi-directional, and foam pigs to clean pipes effectively and thoroughly,â Brannelly says. Pipe Tek's motto reads, âWhen you need a professional result, we make it happenâ. The biggest challenge of the project was the area where the pipe was welded being in soft sand. Brannelly says this made it difficult for machinery movements. âThe use of Pipe Teks off road Polaris buggy came in handy and helped the project be delivered ahead of schedule,â he says. âThe pipe was also very dirty as it was stored without endcaps which made the cleaning component take longer. âHowever, the way we adapted to changing conditions, our ability to complete our first construction project ahead of schedule and on budget with no near misses or recordable incidents
Machinery lifting the HDD section for the angle required for pull back under the Brisbane River.
44
The Australian Pipeliner | March 2022