APPROVED MINUTES OF FEBRUARY 20, 2021 BOARD MEETING VIA ZOOM The meeting is called to order by POA President Brian Faller at 8:59 am. Present at the meeting are Mark Ossont, Rosemary Kucharski (PP), Ron Triani, Sandra LaPorte, Jim Clark, PP), Bob Russo, Bill Vaccaro and Grace Zoccali. Community Manager Ralph Graf and Administrative Assistant Elisabeth Muller are also present.

Motion by: Grace Zoccali - Second by: Sandra LaPorte To approve the executive session minutes of January 2021, November 2020 and April 2020. The motion passes unanimously. Treasurer’s Report, Ron Triani: Treasurer’s Report, February 20,2021 Board Meeting The bank account balances as of January 29, 2021: Dime Bank

- Money Market - Operating - Special Fund - New Capital - Contractors Total all Dime accounts

$150,791 283,909 40,000 144,539 12,896 $632,135

Cash position 01/29

$716,502

Mortgage loan balance PNC Balance NBT Balance Vanguard

Receipts for 2020:

Homes Lots Docks

Cash Disbursements to date:

$251,748 $28,782 $68,481

$576,712 $363,377 34% 197,746 28% 99,933 89%

$74,174 (pre audit)

Spending for Operations in January included payments for some items & services purchased in 2020. Large expenditures include $21,774 for Insurance, $3,918 Refuse/Recycle, $1,201 Road maintenance, and $1.035 Lake Tanglwood maintenance. Reserve Spending: Loan payments of $3,754 chalet mortgage (Jan & Feb); $1,126 Kubota, $464 Safety car, and $1,457 lake dredging bid specs. New Capital Spending: $0

Motion by: Rosemary Kucharski (PP) - Second by: Jim Clark (PP) To approve the Treasurer’s Report. The motion passes unanimously.

Motion by: Ron Triani - Second by: Jim Clark (PP) To extend a grace period of until April 1, 2021, before charging late fees or interest on late dues payments. The motion passes unanimously. Capital Reserve Spending Reserve Study Predicted Spending 2021 - 2025 2020 Year end Reserve Balance

$619,669

2021 Planned Expenditures: - Paving - Lake sediment removal - Salt spreaders replacement - Loan payments - Miscellaneous Planned Revenue Projected Yr. End Balance

$200,000 150,000 19,000 42,530 27,000 $438,530 $449,997* $631,136

Planned Revenue Projected Yr. End Balance

$449,997* $661,603

Planned Revenue Projected Yr End Balance

$449,997* $611,870

2024 Planned Expenditures: - Paving - Lake sediment removal - Loan Payments - Miscellaneous

$200,000 150,000 28,730 27,000 $405,730

Planned Revenue Projected Yr. End Balance

$449,997* $656,137

Planned Revenue Projected Yr, End Balance

$449,997* $604,904

2025 Planned Expenditures: - Paving - Lake sediment removal - 550 Dump Truck replacement - Loan Payments - Miscellaneous Projected Revenue: Projected Spending

$200,000 150,000 95,500 28,730 27,000 $501,230

$2,249,985 * 2,264,750 $(14,765)*

*Does not include dividends earned nor additions funds deposited. Variance Request

Type of Variance: Equipment & Fees associated with enabling audio and video conferencing via the internet in the community center. Date: 02/20/2021 Submitted by: POA President Brian Faller From Account: Operating Description: Equipment and internet fees. Amount: $

Reason For Request: To enable Board meetings to be viewed via the internet by all members of the community via video conferencing. Costs not budgeted in 2021

Budget & Finance Committee Approved ____ Board Of Directors Approved _____

Denied ______

Denied_______

Date: 02/17/2021 Date: 02/20/2021

Community Manager’s Report, Ralph Graf : Community Manager’s Report to Board of Directors, February 2021

The snow-storm in early February was trying for staff and equipment. We were in a good position with our salt and cinders. The vehicles held up with minor damage, a cracked windshield, to the maintenance Pick Up Truck. The Safety Phone was used as a point of contact as the office was closed for two days due to the storm.

The maintenance staff received many compliments in keeping the roads open and safe for travel.

* I signed the application for the Pike County Conservation District regarding sediment removal. The plan is to have the bids back at Princeton Hydro so the contract can be awarded for the first phase in March. I reached out to the contractor for the docks regarding a contract for the coming season. TJ Edwards will be preparing a new agreement for the 2021 Season.

There is nothing further to report on the issues related to the spillway and the shut off valve on the 18th hole of the Golf Course. I authorized Kiley to survey the area to address the concerns raised by Director Russo as to the ownership of the property. The maintenance staff completed the construction of four additional canoe racks that will increase capacity by 16 canoes at the Indian Drive Storage Facility.

+ I have applied for a variance for the proposed new maintenance garage with Palmyra Township. The lot at the maintenance facility is a pre-existing non- conforming property as it relates to the current maintenance building. The variance request will be reviewed by the 2022 Planned Expenditures: Township Zoning Hearing Board. I prepared a narrative noting the hardship with respect - Paving $200,000 to conforming to the ordinance and have identified the facility on a survey map. It appears - Lake sediment removal 150,000 I may need counsel to draft a new deed to identify the existing roadway as it relates to the - Loans Payments 42,530 placement of the garage. - Miscellaneous 27,000 $419,530 ...CONTINUED NEXT PAGE 2023 Planned Expenditures: - Paving - Lake sediment removal - Compactor replacement - Steps & Railing to docks - Loan payments - Miscellaneous

$200,000 150,000 90,000 4,000 28,730 27,000 $499,730

TANGLWOOD LAKES | JUNE/JULY 2021

PAGE 17


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Tanglwood Lakes June/July 2021 by Niki Jones Agency, Inc. - Issuu