Basic headland settings
45
F
46


47
Press the “Soft Key” (Fig.45)
– in order to leave the screen “Init” and to return to the screen “Maintenance”.
Note!
The automatic sequence can only be interrupted by means of the “STOP” key. Initialisation must be started again from the beginning, if it is interrupted.
Press the “Soft Key” (Fig.45).
– The automatic initialization is started. – The display switches to the “Init automatic” (Fig.46)screen. The hydraulic pressure increases audibly. The initialisation procedure runs automatically. The initialization status is shown on the screen. The progress bar(F) shows the progress of the procedure. Complete initialization takes approx.120sec.
After completion of the initialization the display returns to the start screen. • The control unit must be adjusted with the specific requirements again –see Initial settings, page81. (Fig.41,43,44,45,46,47)
11.4.2Basic headland settings
delay period up/down 2.5sec raise front rotors 25% raise rear rotors 42%