FORT PIERCE Strategic Plan 2022 Goals GOAL 15: Seaplanes: Facility and Service Key Issues Design Funding Construction
1. 2. 3. 4.
Obtain permits DECISION: Funding and Design Complete construction Ribbon-cutting and 1st Flight
4/22 4/22 7/22 9/22
Responsibility: City Engineer March 2022 Update: • Final approval for seaplane base from FDOT is currently in the 45-day public comment period. Expect final approval by end of May 2022. • A request has been made to the consultant to provide a proposal for the engineering design and permitting of the seaplane base. Proposal anticipated by May 1, 2022.