GOAL 6: 13th Street Upgrade
GOAL 6: 13th Street Upgrade: Direction and Funding (North and South)
Key Issues
Project Costs: $10 million Funding Source Grant Opportunities Federal Infrastructure North - Design 1. Identify initial funding options – South 6/22 2. Incorporate in CIP Update 7/22 3. Updated Plan Completed 12/22
Responsibility: City Engineer
March 2022 Update:
Continuing to search for alternative funding sources.