GOAL 4: Greenway Trail
GOAL 4: Greenway Trail: Development
Key Issues
Link to Sun Trail Goals Options Funding Route through Downtown FEC Land Acquisition (Small Parcel 1. Complete Highwaymen Trail Gap
Design 2. Solidify Historic Downtown route 3. CONFERENCE AGENDA: Presentation and
Direction 6/22
8/22 9/22
4. DECISION: Historic Downtown Route 11/22 Responsibility: City Engineer
March 2022 Update: Highwaymen Trail Segment
• Consultant to provide 60% design plans by second week of April 2022.
Historic Downtown Segment
• Consultant has submitted 30% plans for review. • Alternative routes being explored