FORT PIERCE Strategic Plan 2022 Goals GOAL 11: King’s Landing Development: Site Plan and Preparation Key Issues Site Plan
1. DECISION: Site Plan Approval 2. DECISION: Land Conveyance 3. Initiate site preparation work
2/22 4/22 2023
Responsibility: City Manager March 2022 Update: The site plan for this project was approved by the City Commission on February 7, 2022. The property conveyance is on target to be completed during the month of April 2022. The removal of additional buried material is slated to begin within the next 30 to 45 days.