FORT PIERCE Strategic Plan 2022 Goals GOAL 3: Fort Pierce Corridor Streetscape and Beautification Projects: Action Plan Key Issues  Economic Development Incentives for Private Sector  Façade Improvement Grants  Streetscape Designs  Projects  Funding Mechanism  Grant Opportunities  Complete Streets Concept  Indian River Drive Moore’s Creek Bridge Condition  Public Input into Designs March 2022 Update

A. Orange Avenue Corridor (FDOT) Project 1. Provide City input into design Ongoing Coordination meeting with FDOT Design Consultant, last week of March 2022. 2. Complete resurfacing design for 7/22 Consultant nearing 60% design plan 33rd to U.S. 1 (FDOT) completion 3. Complete construction (FDOT) 2023 Project funding appropriated for FY 2024 (July 2023) B. Avenue D Corridor (29th to Indian River Drive) Project 1. Complete design 2. Complete construction C. Indian River Drive Corridor Project 1. DECISION: Interlocal Agreement with St. Lucie County 2. Hire consultant 3. Develop streetscape plan

9/22 6/23

Design currently underway. 60% design plans by April 30th. To be determined

7/22

No change

8/22 8/23

No change No change

Responsibility: City Engineer/FPUA FPUA March 2022 Update: FPUA staff reviewed the projects listed above in general. An FPUA utility design will be completed once the final roadway project designs have been completed. Additionally, FPUA & City staff continue to meet on a quarterly basis for project review of ongoing and upcoming projects. The most recent quarterly meeting was in March 2022.

14


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.