ASSEMBLY INSTRUCTIONS

Remove the sides, front, and back of the crate. Remove the plastic bag, shrink wrap and bubble wrap. Remove the metal clips that secure the grinder to the crate base. With a fork li ft, raise the grinder from the wood base and set it in its final position. See FIG. 1 and2. Remove shipping straps.

THE UNIT WEIGHS

750 LBS. (340 kg). TO LIFT, USE POWER EQUIPMENT.

Position Base

The BG1500 Bedknife Grinder will require an operating area of about 91" W x 72" D x 87" H (231 x 183 x 221 cm). The machine operator will operate the unit from the front of the machine. Position the base to allow sufficient operating room in front and right side of the machine. See FIG. 1 and 2.

The base should be placed on a relatively level concrete floor, with ample ceiling height to allow for the installation of the unit. Do not place the unit across two concrete slab seams or across a large crack.