1 minute read

tram track adjustment—see figure-9 5

_________________________________________________ Installation

Installation

special tools

Points to observe prior to installation

Who is allowed to carry out installation?

Installation is only allowed to be carried out by personnel having received adequate training to perform this task.

Work on:

the safety components (pressure relief valves, fire extinguishing equipment etc.)

the electrical equipment (control units, signaling devices, etc.) And

the hydraulic equipment (cylinders, directional control valves, hoses etc.)

should only be carried out by DBT America service engineers or by specially trained personnel.

Which tools are required for installation?

No special tools are required to put the Continuous Miner ® into service.

The receptacles come with a special wrench for connecting and disconnecting receptacles.

In addition, various items of auxiliary equipment and machines may be required at the point of installation.

These include i.e.:

¢ Blocking ¢ Hammer ¢ Screwdriver ¢ Retaining ring pliers ¢ Pliers ¢ Wire cutters ¢ Pry bar ¢ Chisel ¢ Punch ¢ Rose gun ¢ Welding equipment ¢ Chain falls

Installation ___________________________________________________

¢ Slide hammer (provided by DBT America) with the following adapters: ¢ 1”-8 ¢ 5/8”-11 ¢ 3/8”-16 ¢ An adjustable wrench ¢ 7/16” wrench ¢ 3/4” wrench ¢ 1 1/8” wrench ¢ 1 1/2” wrench ¢ 7/16” socket wrench ¢ 9/16” socket wrench ¢ 3/4” socket wrench ¢ 15/16” socket wrench ¢ 1 1/8” socket wrench ¢ 1 1/2” socket wrench ¢ 1 7/8” socket wrench ¢ 15/16” torque wrench ¢ 1 1/2” torque wrench with 20-to-1 multiplier ¢ 1 7/8” torque wrench with 20-to-1 multiplier ¢ 7/8” torque wrench with 20-to-1 multiplier ¢ 3/8” Allen wrench ¢ 5/16” Allen wrench ¢ 5/8” Allen wrench ¢ 3/4” Allen wrench ¢ 7/8” Allen wrench ¢ 3/8” hex torque wrench

Before attempting any repairs, a DANGER sign must be attached to the appropriate circuit at the power distribution box. It is mandatory, under United States Federal Law, that the trailing cable be uncoupled and locked-out from the power source to provide visual evidence that the miner is de-energized.

A scheduled preventative, maintenance, lubrication, and inspection system should be followed.

Only qualified and authorized personnel should be permitted to maintain, repair, adjust and inspect the miner.

general safety rules

© DBT AMERICA 2005