prepared for Globe Kingston Limited
May 2024
summarised progress report
summarised progress report
Surrey House Island Site ā Project Honey (10372)
contents
1.0 executive summary
2.0 programme
3.0 planning update
4.0 legals
5.0 design and project update
6.0 procurement update
7.0 construction works update
8.0 health and safety matters
9.0 tenant variations and approvals update
10.0 sustainability / Net Zero Carbon
11.0 environmental status update
12.0 key risks
13.0 areas of concern
14.0 key activities in the reporting period
15.0 lookahead ā key activities in the next reporting period
appendices
appendix a ā LoR & warranties tracker
appendix b ā planning / S106 conditions
appendix c ā EAI tracker
appendix d ā outline programme
appendix e ā G&T update report
https://francishunter.sharepoint.com/sites/FH/Shared
Documents/Projects/03 current/10372 - Project Honey/10 Reports & Surveys/PM dashboard/2405 May 2024/Cube Dashboard/contents page Cube 240530.docx
appendix f ā MCLH update report
appendix g ā BREEAM tracker
appendix h ā Aecom CMT report
appendix i ā MNP CMT report
appendix j ā ORSA monthly CDM report
appendix k ā DAA CMT report
appendix l ā package review schedule
appendix m ā McLH procurement schedule
appendix n ā McLH programme
appendix o ā Lautus progress report
appendix p ā Clarkeās manufacturing update
appendix q ā LFB response
appendix r ā latest Buildzone tracker/report
https://francishunter.sharepoint.com/sites/FH/Shared
Documents/Projects/03 current/10372 - Project Honey/10 Reports & Surveys/PM dashboard/2405 May 2024/Cube Dashboard/contents page Cube 240530.docx
project: Surrey House Island Site, Project Honey
client: Globe Kingston Ltd/Cube Advisers Ltd r eport: summarised progress report ā May 2024
distribution: Cube
1.0 executive summary
The purpose of this summary statement, is to provide a periodic update of activities undertaken by the developerās project team, currently engaged to implement the redevelopment of Surrey House Island Site and to discharge Hathaway Opportunity Fund/Globe Kingstonās obligations under the Agreement for Development and Lease dated 9 December 2020 (and itās Deed of Variations dated 8 April 2021 and 25 May 2022) with Unilever; and the Development Funding Agreement with LCN exchanged on 25 May 2022 and completed on the 14 June 2022.
The Main Contractor, Mclaughlin & Harvey Construction are appointed under a JCT Design & Build Contract dated 25 May 2022. The Contract has been signed based on a fixed price for Buildings A and B, and a guaranteed maximum price (Provisional Sum) for Building C.
MCLH are reporting that works on site are currently 3 weeks behind on Building A, 4 weeks behind on Building B and 1 week behind programme on Building C The MCLH construction programme has now been issued, and progress is being tracked against this updated programme Following instruction of SMART buildings (EAI 115), it is anticipated that there will be a 5-week delay to Building B (Sectional Completion). The previous Sectional completion date was 05 August 2024 and following the 5-week delay this will now be 09 September 2024. McLH have confirmed that this does not have an impact on early access dates and will also have no impact on Building A and C ( Practical Completion). This is under review currently.
On Building A ā MEP install is progressing up to level 8 FaƧade works have commenced on the 5th floor . The stick system continues on the ground and first floor. All major roof plant has been delivered Otis have installed 3no. lifts. Feature stair install is ongoing on all floors. The main structure to the link buildings is now in place closing off the Brook Street entrance to site.
On Building B - MEP install is progressing up to level 10 FaƧade works are ongoing on the 8th and 9th floor and complete on the 7th floor The stick system glazing is ongoing on the ground and first floor All major plant has now been delivered to site and in place. Otis have installed the first 3no. lifts. Power is now in Building B.
On Building C ā FaƧade now complete above ground floor. The green brick at ground floor will commence in June The changing area fit out is ongoing with 1st fix MEPH complete. Landscape works on roof have commenced and 50% of PVs have been installed.
LFB responded on 13th May 2024 to the scheme fire strategy. This has been reviewed by the team and no critical issues have been raised. MCLH are to respond to LFB in the next reporting period with an updated Fire Strategy picking up the queries raised.
The key risk previously reported relating to the UKPN leases has now been resolved with all three signed. Building B now has power-on, with Building A and C planned for the 5th June. The impact on programme is currently being reviewed, and initial indication is that this will not impact the Practical Completion Date.
A further risk is the SMART buildings integration incurring a potential 5-week delay to Sectional Completion. This is due to the late instruction of the network infrastructure. MCLH continue to review the impact and are to provide a detailed report justifying 5-week delay impact.
The faƧade continues to be a risk on the project due to programme challenges and issues with alignment. The programme is being reported to us on a weekly basis and the latest manufacturing/ installation tracker is appended to this report. Clarkes continue to have supply issues; however, their manufacturing numbers are getting back to the target numbers.
Thames Water have installed the first phase of their works in the public highway. The second phase is currently being programmed between MCLH and RBKT as it was not installed under the previous road closure. This is to install the three branches from the trunk main to the to the site boundary. The water on date is currently scheduled for 10th June 2024.
Another key risk is the S278 works, which due to significantly elongated technical approval period is being carried out far later than envisaged. The S278 agreement has now been agreed with Highways/ Council, and tenders received from two Highway Contractors. FHPM are engaging with Statutory providers to ascertain whether any services in the pavement/ road need to be relocated as a result of the S278 works. The planned commencement date for the S278 works is beginning of September 2024.
some key activities that have been undertaken in the current reporting period include.
⢠S278 negotiations ā Agreed S278 agreement ready for engrossment
⢠Receive tenders to carry out S278 works
⢠Continue to review design packages received from MCLH and progress the approval process with UL and LCN in line with the programme.
⢠Continue to close out planning conditions as required.
⢠Completed Building B 8th floor façade.
⢠Completed Building A 3rd floor façade.
⢠Agreed UKPN leases to allow āPower-Onā
⢠Completed installation of reception link structure.
⢠Commenced Building C roof landscaping works.
⢠Power-on for Building B
⢠Commenced snagging of Building B level 2 and 3
⢠Received LFB response
some key activities that will be undertaken within the next reporting period include.
⢠S278 negotiations ā Receive technical approval
⢠S278 ā Put in place Bond for the S278 works
⢠Procure S278 works
⢠Continue to review design packages received from MCLH and progress the approval process with UL and LCN in line with the programme
⢠Submit pre-occupation conditions
⢠Complete Building B 9th floor façade
⢠Com plete Building A 4th floor façade.
summarised progress report 1
⢠Complete second phase of Thames Water works on St Jamesās Road
⢠Power-on for Building A and C
⢠Review CAT A benchmark area
⢠Formally respond to LFB
high level financials
⢠Contract Sum - £122,974,925.66
⢠Contract variations to date - -£959,230.75 (net)
⢠Projected Final Account - £122,015,694.91
2.0 programme
Following the Unconditional date being confirmed on the 14 June 2022, which has commenced the 27-month construction
Longstop period, the below schedule reflects the latest programme attached to this report in Appendix D and follows the issue of the Possession Notice on 4 July 2022 and Deferment of Possession commencing works on the 20th September 2022
MCLH are now reporting against their Construction programme May 2024 which we are reporting against.
Following a review of MCLH programme and MCLH progress on site, FHPMās current view on programme is as follows;
- Building A ā 2 weeks and 2 days behind
- Building B ā 4 weeks behind
- Building C ā 1 week behind
The key risks to MCLH programme is as follows;
- Thames Water ā Due to for install on 10th June, however a delay to this will impact commissioning
- Access to site ā Due to works required in service yard, brickwork to Building C and the works in Woodland Walk, site logistics will be significantly impacted
- Blind boxes ā Due to late instruction by tenant, there is now a significant complication to the perimeter margin detail.
- S278 works ā Works will need to commence prior to PC, and this is likely to impact on the site logistics. This will need to be managed closely and co-ordinated with MCLH to minimise any impact.
summarised progress report 2
ref. item AfDL (DoV) dates adjusted current forecast /actual variance in last reporting period 01 Unconditional date 02/06/22 15/06/22 0 02 RIBA 3 Design Release 16/02/21 16/02/21 0 03 RIBA 4 Design Release 28/09/22 28/09/22 0 04 RIBA 5 Design Release TBC TBC 0 05 Commence demo - Hippodrome 28/03/21 28/03/21 0 06 Commence demo - Surrey House 15/03/21 15/03/21 0 07 Commence demo - NCP 07/05/22 16/06/22 0 08 Issue of Possession Notice to MCLH 15/07/22 04/07/22 0 09 13 Weeks from Unconditional (Agree rent free reduction) 14/09/22 0 10 Commencement of main works 12/09/22 20/09/22 0 11 Early access ā Building A 01/06/24 09/09/24 +6 weeks 12 Early access ā Building B 18/03/24 03/06/24 0 13 Completion 23/08/24 21/10/24 0 14 Target Practical Completion Date (27 months) including Permitted Delays 02/09/24* 09/11/24* 0 * Currentearliestpossibledate EOT date issued revised section 1 completion date ( building B) revised s ection 2 completion date ( building A +C) status r eason Original Contract Dates 14/06/24 23/08/24 01 01/12/23 18/06/24 03/09/24 Issued Deferment of possession 02 08/12/23 02/07/24 17/09/24 Issued Tenant instructed design delay 03 29/03/23 05/08/24 21/10/24 Issued Tenant instructed town hall construction delay k ey milestones ref. item MCLH C04 Construction Programme current forecast /actual variance in last reporting period 01 FP McCann Commence works 31/07/23 31/07/23 0 02 Town Hall Steel works commence 01/09/23 21/08/23 0 03 MEPH (Halsion) works commence 29/08/23 04/09/23 0 04 Internal finishes commence 18/09/23 18/09/23 0 05 Topping out of buildings A and B 08/12/23 13/12/23 0 06 FaƧade (Clarkes) works commence 21/11/23 21/11/23 0 07 Power on (latest date) 16/04/24 06/06/24 0 08 Buildings substantially weathertight 12/02/24 05/08/24 0 09 Lift (Otis) works commence 08/01/24 08/01/24 0 10 Commence Commissioning 20/07/24 20/07/24 0 11 Sectional Completion 1 (B) 04/08/24 09/09/24 +5 weeks 12 Practical Completion 2 (A & C) 21/10/24 21/10/24 0 *Following instruction of SMART infrastructure.
3.0 planning update
3.1 general update
Over the next reporting period a number of the pre-occupation conditions outlined in the condition tracker will be submitted to the Council for approval. A breakdown of outstanding condition is set out below.
3.2 planning conditions & S278 agreements
Highways have now agreed the scope of the S278 works, with the S278 agreement itself agreed and ready for engrossment. Tenders have been returned for the works and are currently under review.
The scope of the Secure by Design requirements for Building C have now been agreed with the DOCO. The updated pack is being prepared to be issued to the RBKT.
Outstanding conditions set out below;
5 Detailed landscape and planting plan
To be submitted by 21/06/24
18 S278 scope Pre-Occupation Submitted to Council
21 Pedestrian Environment Review Study Pre-Occupation To be submitted by 14/06/24
24 Delivery and Servicing Plan
37 Sustainable Drainage Scheme
Pre-Occupation To be submitted by 21/06/24, awaiting information for UL
Pre-Occupation To be submitted once drainage system complete. End of July
43 Flood Void Maintenance Plan Pre-Occupation To be submitted by 21/06/24
44 Flood Resistance measures Pre-Occupation To be submitted by 21/06/24
46 Car Park Management Plan
49 Park Mark/ SBD
50 Retail Management Plan
Pre-Occupation To be submitted in July. Await input from Car Park Operator
Pre-Occupation To be submitted in July. Await input from Car Park Operator
Pre-Use To be submitted by 21/06/24, awaiting information for UL
51 Woodland Walk Management Plan Pre-Occupation To be submitted by 21/06/24, awaiting information for UL
58 Thames Water No timing Awaiting report from MCLH. To be submitted in July
64 GLA Whole Life Carbon Assessment Pre-Occupation Awaiting report from MCLH. To be submitted in July
66 Circular Economy Statement Pre-Occupation Awaiting report from MCLH. To be submitted in July
3.3 progress against S106 employment and procurement requirement
MCLH have now issued to the Council confirmation of their procurement of 15% of works in the local area as well as their current status of local employment. We await feedback from the Council.
There are now monthly meetings in place with representatives of the Council to demonstrate the teamās willingness to meet the set targets.
4.1 AfDL Conditions Update
The AfDL is now Unconditional, and therefore conditionality will not be reported on going forward.
4.2 appointments and warranties
Terms have been agreed with all of the principal consultants together with all relevant fees and cash flows based upon the current programme A schedule of appointments and warranties has been agreed with both the Fund and the Occupier.
A full schedule of appointments and contracts is being managed and monitored by Francis Hunter, a copy of which is included within the appendix.
It has been 12 months since Unconditional and therefore additional pressure is being put on MCLH and Gowlings to resolve the outstanding Warranties. Regarding Lender Warranties, the majority of current significant designers/ subcontractors have now been signed
The additional warranties requested by the Lender have been provided and are currently being executed
4.3 construction documents
The JCT D&B Contract was signed and dated on the 25th May 2022, with all terms agreed with the Contractor, Funder and Occupier. A Possession Notice was signed and issued on the 4th July 2022 to enact the Contract confirming a possession date of 12th September 2022 Following a number of obstructions and issues found on site during demolition, the Date of Possession was deferred to the 20th September 2022.
Buildings B and C were deferred until 26th September 2022, although MCLH have since confirmed the second deferment had no impact on the overall programme
A breakdown of extensions of time and expected relevant events is shown in the programme section of this report.
The Employerās Requirements are back-to-back with drawings and specifications within the DOV and DFA. FHPM prepared and issued a Contract Report on the 5th May 2022 giving an outline of the JCT Contract and its key terms.
5.0 design and project updat e
MEPH, Architectural and Structural Stage 5 design is progressing
Throughout the process, information will be shared with the Occupier and Funder so that this review process can happen alongside the Developers in order to achieve the timescales noted above.
It should be noted that variations going forward are likely to have a significant impact on the design, procurement and construction programme due to the stage the project is at. These will need to be considered when contemplating any further variations.
5 1 k ey design changes/ issues under consideration
Fire Curtains/ Shutters ā A proposal is under review whereby MCLH will only be issued a Final Certificate from SWECO on the shell & core and not the CAT A for Building A. This may remove the requirement for this to be required at PC. With Unilever fit-out then certifying the CAT A/ B. Currently reviewing whether SWECO are able to provide a letter of comfort for the CAT A works carried out by MCLH.
Public Art design ā Detailed design and damper design is now underway. Due to the Public Art interface with the faƧade and the structure of three separate buildings it continues to cause complications.
summarised progress report 3
Condition
Condition Requirement Next Step
No
Pre-Occupation
4.0 legals
Reception link pipework routes ā A route has now been agreed, which require a notch in the slab of Building A and B in the reception link to allow services to pass at high level.
6.0 procurement update
Following lengthy negotiations with MCLH, the JCT D&B Contract was signed with a Contract Sum of £122,962,469.66 dated 25th May 2022.
MCLH have issued a revised procurement schedule, which is appended to this report This will be tracked by FHPM going forward.
The G&T Report is appended in Appendix E
7.0 construction works update
Below is an update on progress in the last reporting period:
⢠Continuing MEPH works throughout A and B
⢠Continued roofing works to the roof of all buildings
⢠Continued Building A and B façade works
⢠Continued lift installation to Building A and B
⢠Continued ceiling works in Building A and B
⢠Continued raised access floor installation in Building B
⢠Continuing steelwork to the feature stair, reception steel, balustrades
8.0 health and safety matters
ORSA, as Principal Designer, are progressing key design risk assessments with the team as the design develops and continue to keep the professional team informed at all stages. ORSA are carrying out monthly site inspections of works being undertaken by MCLH and providing reports. No issued were raised in the report. ORSA carried out a site inspection on the 24th May 2024, and their findings are appended to this report.
9.0 variations and approvals update
Variations instructed in the last reporting period are set out below (and set out in more detail in the variation tracker within the appendix)
10.0 variations and approvals update
Variations instructed in the last reporting period are set out below (and set out in more detail in the variation tracker within the appendix).
⢠EAI 123 - RAF
⢠EAI 124 ā Terrazzo benches
⢠EAI 125 ā Public Art Cable and Damper Design
⢠EAI 126 ā MSCP Prov Sum
ā¢
ā¢
⢠EAI 129 ā External Lighting to Car Park Roof Terrace
⢠EAI 130 ā S278 Setting Out
There are a number of expected upcoming tenant/ developer variations requests, which are as follows;
⢠Construction cost of louvres in façade
⢠Terrace power/ lighting/ water
⢠Building A 7th Floor East Riser Ductwork
As noted earlier in the report, given the stage the project is at, variations are becoming more impactful and will potentially result in abortive design costs, cancellation charges and programme delays.
The below table sets out in more detail the variations in the last reporting period. This is the capital cost of the variation and does not include any finance costs;
External Lighting to Car Park
11.0 sustainability/ Net Zero Carbon
In line with undertakings within the AfDL the developer team continue to follow the sustainability commitments. All members of the design team are specifically charged with supporting the objectives and developing the design accordingly. Design is progressing on the basis of achieving BREEAM Excellent and EPC A. Currently achieving 79.54% which is the same projected figure as the previous month.
12.0 environmental status update
As it stands, there are no environmental issues identified on site. This will continue to be monitored as the project progresses.
summarised progress report 4
EAI 127
ā Service Notch
EAI 128
ā Soffit Lighting
variation reference variation description EAI issued/ ref variation value (including developer profit + fees) funding source CO- 174 RAF EAI 123 - Developer CO-175 Terrazzo Benches EAI 124 TBC Unilever CO-176 FLOW detailed design EAI 125 £ 12,456.00 Developer Building C - External Doors and Louvres EAI 126 TBC Prov Sum Drawdown CO-177
EAI 127 TBC Developer/ Unilever CO-178
EAI 128 TBC Developer
EAI 129 TBC Unilever
179
Setting Out EAI 130 TBC Developer TOTAL for the reporting period £ 12,456.00
Service Notch
Soffit Lighting
CO-155
Roof Terrace
CO-
S278
Principal risks during the immediate next phases that could impact on the deliverability of the scheme are as follows;
R1 Health & Safety The Principal Designer (ORSA) are fully integrated into the team and providing regular updates, as well as carrying out monthly site inspections during the construction contract
R2 Programme delays due to COVID 19
R3 Construction (Contractor) delays
R4 Planning Condition Delays
R5 Contractor/ sub-contractor insolvency
No programme impact as yet and risk mitigated within AfDL.
Tight town centre site with complex logistics will increase risks of delay significantly. This is now primarily a contractor risk item
The planning conditions are being tracked on a weekly basis, with Chartplan in discussions with RBKT. The key conditions currently with the council for review is the District Heat Network Condition
The financial status of the Main Contractor and its key supply chain is checked on a quarterly basis. The financial stability of all sub-contractors is the Contractorās risk. The latest checks were carried out in December 2023, which raised no significant concerns.
R6 Impact of the Ukraine War There is a ācarve outā in the JCT for the impact of the Ukraine War on programme. This will be monitored going forward to ensure packages are procured early enough to mitigate.
R7 Brexit import delay
There is a ācarve outā in the JCT for Brexit import delay on programme. This will be monitored going forward to ensure packages are procured early enough to mitigate. It is worth noting that the faƧade is now being procured from Northern Ireland, this further reduces the potential of this risk.
R8 Achieving areas To ensure the targeted areas are achieved, these will be checked at each design stage and as Construction progresses to ensure the development is falling within the min/max area brackets.
The first measure of Building B 2nd, 3rd and 4th floors has been carried out. We are awaiting results
R9 Cost Overrun
The Contract has been signed on a fixed price, however there are Provisional Sums which could lead to an overspend and require expenditure of the contingency. These are reported on each month by G&T and the Provisional Sums are to be closed out as early as possible.
R10 Twin Wall An alternative LDI policy with Build-Zone has been agreed, and the Deed of Variation to replace the Aviva policy has been agreed and signed. The cost and programme impact of the twin-wall has been closed with the signing of the DOV. It should be noted that delays during resolving the issue have impacted the programme and resulted in delays beyond the current reported delay.
R11 Utilities āUKPN Leases
The UKPN works are complete with substations in place and highway works complete. Legal agreements have now been signed, and power-on in Building B. Building A and C are due to have power-on 5th June 2024. Programme impact is currently under review.
R12 S278 Agreement Highways have now agreed to the scope of the S278 works and the S278 agreement itself has been agreed with the Council. A bond is ready to be put in place and the tender returns for the S278 works are currently being reviewed.
R12 Clarkes faƧade programme Clarkes faƧade manufacturing and installation programme is behind. MCLH have put forward a recovery programme which will be updated weekly. The last 4 weeks, Clarkes have met or exceeded their planned manufacturing This is still being tracked on a weekly basis, but it is likely their programme can be improved on this basis.
R13 MEPH weather damage MEPH works are progressing on floors prior to the faƧade being installed. This is not necessarily an issue; however, a concern has been raised by Aecom and the tenant team. MCLH have provided an uplifted testing regime to deal with these out of sequence works. This is under review
R14 Building A āFeature Stair Finish
and
and
Unilever have raised some concerns regarding the timber finish of the tread on the feature stair not matching the timber finish of the handrail An alternative is being reviewed currently.
R15 LFB Sign off LFB response was received in the previous reporting period with no critical issues raised. MCLH have summarised the response which has been circulated.
R16 Network Infrastructure McLH to issue a detailed narrative this week confirming the main issues in relation to the 5-week delay of Sectional Completion due to the late instruction of the network infrastructure This is under review
Risk Register Key
14.0 areas of concern
FaƧade - The faƧade manufacturing and installation programme is currently behind Meetings are being held on a weekly basis to discuss progress and a tracker will be circulated to all parties Progress has been improved in the last reporting period however there are still significant concerns regarding the faƧade that has been installed, particularly regarding alignment.
UKPN leases and works ā Power-on for B and power-on for A and C is due on the 5th June. The programme impact of this delay is being reviewed.
S278 Agreement - Highways have now agreed to the scope of the S278 works and the S278 agreement itself has been agreed with the Council. A bond is ready to be put in place and the tender returns for the S278 works are currently being reviewed.
Fire Curtains/ Shutters ā Still awaiting instruction to proceed with the 6th and 7th floor fire curtain. An alternative proposal is under review which will negate the requirement for these works to form part of the basebuild development works.
15.0 k ey activities in the reporting period
I UKPN Lease agreements signed
II. Progress tenant variations.
III. Concluded S278 legal discussions.
IV. Review design release packages issued by MCLH.
V. Continue to look at options of reducing the carbon impact of the development.
VI. Issued S106 Procurement Targets to RBKT.
VII. Received LFB response to scheme
VIII. Received tenders for S278 works
IX. Achieve power on for Building B
X. Completed Thames Water works outside of site
XI. Submitted Condition 11
XII. Progress ed design for connection details and cables for the public art to Buildings A, B and C.
XIII. G99 application signed by LCN for Building A and B.
summarised progress report 5 13.0 key risks
ref. risk item status update likelihood of risk impact of risk contractor
developer risk
or
L H Contractor
Developer
L M Contractor
L M Contractor
Developer
L M Contractor
Developer
and
L H Contractor
L H Developer
L H Developer
L H Contractor
M H Developer
M Contractor
L
M H Developer
M M Developer
H M Contractor
M M Contractor
M H Occupier
M M Contractor
H H Contractor/ Occupier
High
Medium
Low risk ā
risk -
risk -
lookahead
ā k ey activities in the next reporting period
I. Complete Building B facade
II. Progress tenant variations
III. Engross S278 Agreement
IV. Review design release packages issued by MCLH
V. Continue to look at options of reducing the carbon impact of the development
VI. Appoint Highways Contractor to carry out S278 works
VII. Issue updated SBD document to RBKT
VIII. Agree early access protocol with Unilever and their fit-out Contractor
IX. Achieve power on for Buildings A and C
X. Complete Thames Water works inside site
XI. Submit further conditions as per 3.2
XII. Progress design for connection details and cables for the public art to Buildings A, B and C
XIII. Close out Park Mark with Car Park Operator
appendices
A. LoR & warranties tracker
B Planning/ S106 Conditions
C EAI Tracker
D Outline Programme
E G&T Update Report
F MCLH Update Report
G BREEAM Tracker
H Aecom Update Report
I MNP Update Report
J ORSA Update Report
K DAA Update Report
L Package Review Schedule
M. McLH Procurement Schedule
N. McLH Construction Programme
O. Lautus Progress Report
P. Clarkes Manufacturing Update
Q. LFB Response
R. Buildzone tracker/ report
summarised progress report 6
FH090-151015 appendix a LoR
warranties tracker
&
warranty and PI schedule
date: 04/06/24 ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty primary warranties 1.00 main consultants 1.01 Employers Agent FHPM Ā£10m expires 08/08/24 Signed 25//5/22 Completed Gwlng May Tracker Signed 8/6/22 Issued by Gwlngs for Docusign 7/7/23ā¦signed TA email 19/7/23 Warranty required per building CLOSED 1.02 Monitoring Architect DAA Ā£5m expires 27/08/24 Signed 25//5/22 N/A for monitor Signed 8/6/22 Issued by Gwlngs for Docusign 7/7/23ā¦signed TA email 19/7/23 Only one monitoring architect's appointment. TA email 5/7/23 CLOSED 1.03 Monitoring Civil and Structural Engineer (main and monitoring) MNP Ā£5m expires 18/04/25 Signed 19/10/22 Completedā¦Gwlng May Tracker. Tenan Warranty not required for Monitoring. Signed 19/10/22 Issued by Gwlngs for Docusign 7/7/23ā¦.13/9/23 Lender to sign all warranties in one go. 29/11/23 Lender warranty (Main) signed by Lender. CLOSED 1.04 MEP Engineer Aecom Ā£10m expires 01/04/24 ā¦new certificate requested Signed 19/10/22 Completed- Gwlng May Tracker. Signed 19/10/22 29/11/23 Lender signed. CLOSED 1.05 Cost Consultant G & T Ā£10m expires 01/05/24 Signed 25//5/22 N/A Signed 8/6/22 .signed TA email 19/7/23 CLOSED 1.06 Main Contractor MCLH Ā£20m expires 31/12/24 Contract dated 16/11/22 With Tenant Fund warranties completed Contractor lender warranty sent out for Docusign by Gwlngs 7/7/23. Lender to sign all warranties in one go. GOWLINGS/MAYER BROWN 1.07 Demolition Contractor Shorts Ā£1m expires 01/06/24 (Ā£5m) Contract dated 3/2/23 Fund warranties completed 25/7/23 Shorts have signed. GOWLINGS
Warranties/LoR within 12 months of unconditional or no more drawdowns for relevant trades 2.01 Architect Novated x 3 appointments DAA £10m expires 27/08/24 signed 25/5/23 Completed- Gwlngs May Tracker Fund warranty completed Email of 30/1/24 COMPLETED CLOSED 2.02 Contractors Engineer RBG £10m expires 31/12/24 COMPLETED COMPLETED- Gwlng May Tracker 30/1/24 Fund Warranty "COMPLETED" 30/1/24 Lender Warranty COMPLETED CLOSED https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
project: Surrey House
2.00
project: Surrey House
warranty
PI
and
schedule
date: 04/06/24 ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty 2.03 Cladding consultant x 3 appointments Eckersley O'Callaghan (EOC) Ā£10m expires 23/03/25 Signed by Consultantā¦and by Employer COMPLETED- Gwlng May Tracker Funder warranty issued and completed by Gwlngs Docusign 11/7/23 Issued by Gwlngs for Docusign 7/7/23. 29/11/23 COMPLETED CLOSED 2.04 Right of light consultant Point2 Ā£10m expires 19/12/24 Appointment COMPLETED COMPLETED- Gwlng May Tracker FUNDER WARRANTY COMPLETED LENDER WARRANTY COMPLETED CLOSED 2.05 Measurement Surveyor consultant Plowman & Craven Ā£5m expires 01/06/24 (new certificate requested) Signed, to be completed once Funder/Lender warranties are signed. Reliance letters to be issued once reports are prepared. With Funder for signture With Lender for signature GOWLINGS 2.06 Validation Engineer Inhabit Ā£2m expires 31/12/24 (Ā£10m) Gwlng awaiting details Gwlng awaiting details Gwlng awaiting details Gwlng awaiting details Services not carried out until completion.
Environmental consultant GEA £5m expires 31/03/25 Gowlngs awaiting details. Report dated February 2022 COMPLETED COMPLETED COMPLETED 2.08A Landscape Architect Gillespies £5m expires 25/09/24 signed 13/02/22 Completed Gwlng May Tracker COMPLETED COMPLETED CLOSED
Landscape ArchitectContractor Appointment McIIlwaine £2m expires 08/11/24 30/1/24 TA says that draft has been received. Not required June 2024-Drafted, awaiting signatory details June 2024-Drafted, awaiting signatory details GOWLINGS
2.07
2.08B
appointments ORSA Ā£10m expires 24/02/25 Signed 19/10/22ā¦.check
completed Completed Gwlng May Tracker Signed 19/10/22ā¦check if completed COMPLETED CLOSED
2.09 Principal Designer x 3
if
Strategy
SWECO Not required No longer engagedā¦replaced by Marshall Fire.
ā¦.see
Marshall £5m aggregate expires 25/07/24 COMPLETED Completed Gwlng May Tracker COMPLETED COMPLETED CLOSED
Appointment Marshall £5m aggregate expires 25/07/24 Draft received
Not required
FHPM to check
2.10A Fire
Consultant
2.10B Fire Strategy Consultant x 2 (one direct/retained and one with contractor)
below for contractor appointment
2.10C Fire Strategy ConsultantContractor
ā¦.30/4/24 email...Client Warranty sent out to Consultant for signature.
1/3/24 Marshall have confirmed they can accept the draft warranty. Gwlng May Tracker-issued to Consultant for signature. 29/11/24 TA to be issued. ā¦.Gwlng May Trackerissued to Consultant for signature
subcontractor Van Elle £5m aggregate expires 29/04/25 Redacted order signed and dated 2/11/22 received and filed on Centrodoc. Completed Completed Gwlng May Tracker COMPLETED COMPLETED CLOSED https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
2.11 Piling Bored.Sheet
Ā£10m aggregate expires 28/02/25 Fully executed order dated 30/5/23 received and filed on Centrodoc. redacted . 6/3/24 Certified copy required.
2.16 Acoustic consultantContractor Appointment Hann Tucker £1m expires 24/7/24
2.17 Lift subcontractor Otis £5m aggregate expires 30/11/24 Redacted subcontract order dated 4/5/23 received and filed on Centrodoc.. 6/3/24 Certified copy required.
2.18 Car Park Contractor (if separate) FP McCann £10m aggregate expires 31/01/25
2024- Issued to the sub-contactor
Gwlng May TrackerDraft received. 30/4/24 emailā¦Client Warranty sent to Consultant by Docusign
29/1/24 Signed by subcontractor, to be sent to the contactor with Funder and Lemder warranties
Fully executed subcontract order dated 26/7/23 received and saved on Centrodoc.. 6/3/24 Certified copy
June 2024- Issued to the sub-contactor
Not required Gwlng May Trackerissued to Consultant for signature. Gwlng May Tracker- with Consultant for signature
Completed- Gwlng May Tracker .June 2024 Signed by the sub-contractor. Sent to the Tenant. 12/4/24 Issued to Otis again by GWLNGS
June 2024 Still with subcontractor. Issued to Otis by Docusign by GWLNGS ā¦.12/4/24
June 2024- Issued to the sub-contactor
June 2024- Issued to the sub-contactor
June 2024- Issued to the sub-contactor
warranty
PI
and
schedule
date:
ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty 2.12 Concrete frame subcontractor Mitchellson £10m
Redacted
received
Centrodoc. COMPLETED Completed Gwlng May Tracker COMPLETED COMPLETED. CLOSED 2.13 Roofing subcontractor AYM
aggregate expires
Received, certified
required. Issued to sub-contactor for signature Issued to sub-contactor for signature ā¦.2 warranties, Building A and Building B Issued to sub-contactor for signature Issued to sub-contactor for signature GOWLINGS
project: Surrey House
04/06/24
aggregate expires 18/11/24
subcontract order dated 5/1/23
ā¦saved on
Ā£10m
11/10/24
copy
Halsion
Completed Gwlng May Tracker Completed Gwlng May Tracker Completed Gwlng May Tracker Completed Gwlng May Tracker CLOSED
2.14 MEPH subcontractor
Ā£10m AOC expires 11/12/24 Redacted order dated 21/11/22 received and saved on Centrodoc. Certified copy required.
Clarkes
June
June 2024-
June 2024-
GOWLINGS
2.15 FaƧade, cladding and curtain walling
June
2024- Issued to the sub-contactor
Issued to the sub-contactor
Issued to the sub-contactor
GOWLINGS
GOWLINGS
GOWLINGS https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
project: Surrey House
warranty and PI schedule
date: 04/06/24 ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty 2.19 Architectural metalwork/secondary steelwork CMF Limited £10m in the aggregate certificate provided expires 03/07/24 Fully executed subcontract order dated 4/9/23 received and saved on Centrodoc. 6/3/24 Certified copy required. Completed- Gwlng May Tracker Completed- Gwlng May Tracker Completed- Gwlng May Tracker Completed- Gwlng May Tracker CLOSED 2.20 Plant screens and Louvres (if separate) TBA 2.21 Soffit cladding (if appropriate) Clarkes See Clarkes above 2.22 Steelwork connections (if appropriate) TBA Included in Mitchellsons 2.23 Fire curtains TBA
Feature staircase TBA 29/11/23 requested from LN 2.25 Mansafe system PTSG £10 m in the aggregate Expires 31/3/25 Signed sub-contract order dated 5/9/23 received and filed and Centrodoc. 6/3/24 Certified copy required. Completed- Gwlng May Tracker Completed- Gwlng May Tracker Completed- Gwlng May Tracker Completed- Gwlng May Tracker GOWLINGS 2.26 Internal glazed screen subcontractor TBA £2m 2.27 Greenwall ANS Global 2.28 Flood protection equipment TBA 2.29 Car park cladding (if separate) Maple 2.30 Other subcons with material design responsibility. TBA 3 Secondary consultants supporting Planning Application only 3.01 Acoustic consultant Hann Tucker £1m expires 24/07/24 (£10m) Appointment completed Funder warranty completed CLOSED 3.02 Air Quality consultant AQ Consultants £2m expires 06/03/25 Appointment completed Funder warranty completed CLOSED 3.03 Arboriculture consultants Landmark Trees £2m continuous Appointment completed Funder warranty completed CLOSED 3.04 Archeological consultants RPS Consultancy £1m expires 30/9/24 (£10m) Appointment completed Funder warranty completed CLOSED https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
2.24
warranty
PI schedule
date: 04/06/24 ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty 3.05 Asbestos consultant Search Environmental Ā£1m expires 21/8/24 Appointment completed Funder warranty completed CLOSED 3.06 Ecological consultant Ecology Practice Ā£2m expires 17/12/24 Appointment completed Funder warranty completed CLOSED 3.07 Planning consultant Chart Plan Ā£2m expires 30/7/24 Appointment completed Funder warranty completed CLOSED 3.08 Security consultant Kabsec Ā£5m expires 03/01/25 L of R agreed. 6/3/24 Reliance letter signed by Consultantā¦to be sent to Funder. CLOSED 3.09 Blast consultant Aibara Ā£1m expires Appointment completed ā¦but Gwlng May Tracker "Awaiting details". Funder warranty completed CLOSED 3.10 Cladding Access consultant PTSG (Through MCLH) Ā£5m expires 31/03/25 Awaiting details to prepare Appt. TA 6/3/24 To be issued with Appt. Missing from TA schedule on 6/3/24 but CMS have been informed that it is PTSG through MCLH. 3.11 Transport consultant Milestone Ā£5m expires 5/12/24 Appointment completed Funder warranty completed CLOSED 3.12 Environmental Impact Statement consultant Stantec Ā£1m expires 1/10/24 COMPLETED N/A COMPLETED COMPLETED CLOSED
Approved Inspector Sweco Ā£10m expires 29/5/24 Not requiredā¦statutory service. 4.00 Other 4.01 Wind and microclimte consultant BRE With Consultant ā¦Letter of Reliance. 4.02 Heritage and Townscape Consultant Peter Stewart Consultancy Completed CLOSED 4.03 Viability study Housing Expectations Completed CLOSED 4.04 Building Control MLM (Sweco) Completed CLOSED 5.00 Product and Component Guarantees ( Tenant Guarantees) 5..01 To be added if required in this document 6.00 Sub-sub- contractor warranties https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
and
project: Surrey House
3.13
project: Surrey House
sub-sub contractor)
6.02 Design of PT slabs (Mitchelson sub-sub contractor)
6.03 Design, manufacture, installation (Mitchelson sub-sub contractor)
contractor)
6.05 Design and manufacture(Mitchelson sub-sub contractor)
6.06 Sub-sub-contractor (Halsion)
23/2/24 TA confirmed that she has sent a draft form of warranty to BCLP for all 5 of these sub-subbiesā¦....and will arrange for these to be issued once approved.
warranty and PI schedule
ref consultant PI level & wording certifciate provided redacted order sent employer tenant fund lender comments status/ responsibilty
date: 04/06/24
Kilsaran Awaited TA 6/3/24 ..To be issued
with
approval) To be issued To be issued To be issued
6.01 Design and supply of twin wall (Mitchelson
(currently
the Funder for
CCL Received, certified
TA 6/3/24
be issued
To be issued To be issued To be issued See
copy required.
..To
(currently with the Funder for approval)
Kilsaran above
Received, certified
required. TA 6/3/24 ..To be issued
with the
for approval) To be issued To be issued To be issued See Kilsaran above
Creagh Received, certified
required. TA 6/3/24
be issued
To be issued To be issued To be issued See Kilsaran above
Intersteel
copy
(currently
Funder
6.04 Design and manufacture (Mitchelson sub-sub
copy
..To
(currently with the Funder for approval)
FP McCann Awaited TA 6/3/24 ..To be issued
with
approval) To be issued To be issued To be issued See Kilsaran above
(currently
the Funder for
Carbon3 Received, certified copy required To be issued (currently with Funder for approval) To be issued To be issued To be issued https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/01 Appts Contracts & Proc/Warranty & LOR tracker/Warranty and PI ScheduleTracker/Warranty PI schedule for Honey 240604 v35
planning/S106 conditions
FH090-151015 appendix
b
Detail Planning Application No: 22/02905/FUL ā Consented 11/01/2023
Updated 31/05/2024
Surrey House, 34 Eden Street NCP Car Park, St James Road Former Hippodrome, Eden Street And Bo Concept, The Roundhouse 20 Eden Street
PROPOSAL: Application under S73 of the Town & Country Planning Act 1990 to carry out development without compliance with condition 1 (Approved plans) of planning permission ref: 21/04022/FUL (Application under Section 73 of the Town and Country Planning Act 1990 to carry out development without compliance with Condition 1 (Approved Plans) of Planning Permission ref: 20/02495/FUL (Full Planning application for the demolition of Surrey House, Multi Storey Car Park, Hippodrome and Bo Concept and the erection of 2 (two) Office buildings [Use Class - E(g)(i)] Building A and Building B: Building A 9 storeys (22,144 (GEA) sqms) Building B 11 storeys (11,587 (GEA) sqms). The erection of a replacement multi storey car park of 354 spaces plus cycle parking (for use as a public car park at weekends) landscaping, public realm upgrades, servicing, pedestrian and vehicular access) dated 02/12/2021. Variations to include alterations to bridge link, elevations, floorplates, ground floor level access, rooftop plant and screen, service yard, reduction to height of Buildings A and B, alterations to landscaping/public realm, removal of basements and stairs on sides of Building A. This application is accompanied by an Environmental Statement.)
Variation to consist of revisions to the Car Park (Building C). This application is accompanied by an Environmental Statement.
Taking into account the Environmental Information contained within the Environmental Statement and addenda thereto, which was submitted under the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 and subject to a āLegal Agreementā, PERMIT subject to the following conditions:
This application is accompanied by an Environmental Statement.
BRIEF OUTLINE OF CONDITIONS
(See Notice of Decision of Planning Application 22/02905/FUL for Full Specification)
1 The approved development shall be carried out in accordance with the following drawings/details: (See consent for full list of drawings)
App deposited re cladding deposited and validated 27/04/23
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
TIME LINE SENSITIVITY DETAIL/A CTION TO BE ACTIONE D BY APPLICATION SUBMISSION PROGRESS APPROVAL DATE
Informative
Consented
NMA
25/05/23
2 The development hereby permitted shall begin before the expiration of three years from 2nd December 2021 (2nd December 2024)
3 . The development shall be completed in accordance with samples for all facing materials including fenestration and boundary treatments (gates, fences / walls, other) including details of manufacturing specification which shall be submitted to and approved in writing by the Local Planning Authority before above ground works on site are commenced. The development shall then be built in accordance with these approved samples and completed prior to occupation.
Pre above ground works condition
Ref: 23/01117/NMA
MCLH 11th November 2022
Validation details 22/03576/CLC Consented 30/01/23
22/03576/CLC
4 Notwithstanding the details shown on the approved plans additional architectural detailing plans at scale 1:10/ 1:5 showing all openings and key elements of the building / landscape (windows, doors, facade glazing, fins and parapets, spandrel panels, entrance and associated publicly visible features, signage, lighting in publicly accessible areas, vents / intakes / exhausts, grilles / louvres, rooftop plant, other elevational features shall be submitted to and approved in writing by the Local Planning Authority before the relevant element is commenced on site. The development shall be constructed in accordance with the approved details.
5 Prior to any occupation an updated full and detailed landscape and planting plan, including details of additional tree planting on Brook Street shall have been submitted to and approved in writing by the local planning authority. The Strategy shall include the details of the 6 trees to be planted in Brook Street along with the proposed locations and details of the tree pits and tree grilles. The Trees planted on Brook Street shall comprise of 3no. Fastigiate Hornbeam (Carpinus betulus āFastigiataā) planted at a minimum of 550cm tall with a minimum single clear stem of 200cm and a girth of 30-35cm, and 3no. Fastigiate Hornbeam (Pyrus calleryana āChanticleerā)
Pre development condition, relevant to each section
Pre above ground development
Pre-occupation condition
MCLH Application deposited 15/08/23
Ref: 23/02245/CLC
Validated 22/08/23
Consented 10/10/23
Park Road,
RH2 0DD
Suite 21, High Cedars, 20 Wray
Reigate
ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Informative
MCLH
planted at a minimum of 450cm tall with a minimum single clear stem of 200cm and a girth of 25-30cm. The Strategy shall be implemented within the first planting season following completion of the development and the landscape and planting shall thereafter be maintained for five years to the satisfaction of the Local Planning Authority. Any trees or planting that die during this period shall be replaced during the following planting season, and the areas shown to be landscaped shall be permanently retained for that purpose.
6 No above ground development shall take place until details of all external lighting have been submitted to and approved in writing by the Local Planning Authority. The external lighting shall be installed in accordance with the approved details and thereby retained as such unless a variation is subsequently submitted to and approved in writing by the Local Planning Authority.
7 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any Order revoking or re-enacting this Order) No fans, louvres, ducts, external lighting or other external plant other than those shown on the drawings hereby approved shall be installed without the prior written approval of the Local Planning Authority.
Application
8 All works on site shall take place in accordance with the details approved pursuant to 22/00273/CLC (Details of Demolition and Construction Environmental Management Plan)
9 The development shall be carried out in accordance with details approved by 22/00759/CLC (Levels).
10 The development shall be carried out in accordance with details approved under 22/00371/CLC pursuant to Condition 10 (Site Waste Management Plan).
11 Within 6 months of above ground works a Public Realm Management Plan, including measures to minimise any adverse
Within 6 months of MCLH Application deposited 10/05/24
Suite
20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
21, High Cedars,
Pre above groundworks condition MCLH
deposited 31/10/22 Validated Ref: 22/03480/CLC Consented 23/01/23 22/03480/CLC
Informative
Informative
Informative
Informative
microclimatic impacts of the development have been submitted to and approved in writing by the Local Planning Authority. Prior to the beneficial occupation of the development hereby approved the hard and soft landscaping shall be fully implemented and made available for all residents and thereafter maintained for the lifetime of the development. commencement of above ground works Ref 24/01192/CLC
Decision due by 05/07/24 12
The development hereby permitted shall be carried out in accordance with the approved Transport Statement. Informative
13 Prior to the commencement of any development above ground level, details of secure cycle parking facilities to serve the development to which this permission relates shall be submitted to and approved in writing by the local planning authority. The cycle parking facilities as shown in the approved details shall be provided prior to beneficial occupation of the development to which this permission relates and shall be permanently retained for that purpose and kept free from obstruction thereafter. Pre development condition (above ground)
14 The hard surfaces hereby approved shall be made of porous materials and retained thereafter or provision shall be made and retained thereafter to direct run-off water from the hard surface to a permeable or porous area or surface within the /curtilage of the property.
Informative
15 The revised energy strategy as approved by 22/00683/CLC on 3rd January 2023 shall be implemented throughout the development of the site. Informative 16
Any flat roofed area that is not identified as communal or private amenity space or roof terrace shall not be converted or used as a balcony or sitting out area, and no access shall be gained except for maintenance purposes. Informative
17
A public art and way-finding strategy should be submitted to the local planning authority for approval prior to commencement of above ground works. The public art and wayfinding strategy shall identify proposed public art and way-finding works to be installed Pre above groundworks condition
Consented 21/03/23
Ref: 22/03873/CLC
0DD
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2
ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
MCLH
Ref:
Consented 30/01/23
22/03841/CLC
MCLH
as part of the detailed landscaping strategy. The Strategy shall detail the mechanism for selecting the public art and way-finding works and the maintenance and management of the art works. The works of art shall be installed prior to the beneficial use of the car park or in accordance with the timeframe set out in the public art and wayfinding strategy and thereafter retained in accordance with the agreed maintenance and management plan.
18 Prior to the occupation of the development hereby approved, details of the works relating to highway works required in connection with the proposed bus stop and bus stand, including any relocation of services and pedestrian crossings, shall be submitted to and approved by the Local Planning Authority or by the Council as Highway Authority pursuant to Section 278 of the Highways Act 1980, and carried out in accordance with the approved details. Such details shall include the agreement of levels and construction details. All works are to be to the Council's adoptable highway standards and shall include any associated drainage works, lighting improvements, landscaping, street furniture, road markings, signage, traffic orders, and any necessary alterations to statutory undertakers equipment. Any widening to the public footways shall be retained permanently available for pedestrian circulation and the widened areas dedicated as highway pursuant to the Highways Act 1980.
19 The development shall be carried out in accordance with the details approved on 25.02.2022 Reference 22/02595/CLC (Written Scheme of Investigation WSI - Archaeology). No development shall take place other than in accordance with the agreed WSI, and the programme and methodology of site evaluation and the nomination of a competent person(s) or organisation to undertake the agreed works. If heritage assets of archaeological interest are identified by stage 1 then for those parts of the site which have archaeological interest a stage 2 WSI shall be submitted to and approved by the local planning authority in writing. For land that is included within the stage 2 WSI, no demolition/ development shall take place other than in accordance with the agreed stage 2 WSI which shall include: A. The statement of significance and research objectives, the programme and methodology of site
Pre occupation condition
MCLH Application deposited
Ref: 24/01313/CLC
Decision due: 18/07/24
Pre demolition condition
FHPM/Ch art Plan DOC app deposited
31.12.21
App validated 05/01/22
Ref: 21/04117/CLC
Additional Archaeology report submitted to LPA, validated 10/08/22
Ref: 22/02595/CLC
Consented 25/02/22
Consented 23/09/22
Suite
20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
21, High Cedars,
investigation and recording and the nomination of a competent person(s) or organisation to undertake the agreed works; B. The programme for post-investigation assessment and subsequent analysis, publication & dissemination and deposition of resulting material. This part of the condition shall not be discharged until these elements have been fulfilled in accordance with the programme set out in the stage 2 WSI.
20 The servicing of commercial unit(s) hereby permitted shall only take place between 0700 and 2000 on any day, including Sundays and Bank Holidays.
21 Prior to occupation a Pedestrian Environment Review Study (PERS), considering the ten Healthy Streets indicators, as set out in the Mayorās Transport Strategy, 2018 shall be submitted to and agreed in writing by the Local Planning Authority, the findings of which shall be implemented in accordance with timeframes agreed with the Local Planning Authority and thereafter permanently retained.
22 Prior to the occupation of the office, details as to how the approved development has been designed to connect to a future District Heating Network in the surrounding area and provision for the developmentās connection shall be submitted to and agreed in writing by the Local Planning Authority and thereafter permanently retained.
Pre occupation condition Milestone
Pre occupation condition MCLH Application deposited and validated 23/11/23 Ref: 23/03103/CLC Decision due by 16.01.24
23 The development shall be carried out in accordance with details approved pursuant to 22/00463/CLC in relation to Condition 23 (Ecological Management Plan) Informative
24 Prior to the occupation of development a Delivery and Servicing Management Plan shall be submitted to and approved in writing by the Local Planning Authority.
25 The rating level of the noise determined by the cumulative sound emissions of the plant hereby permitted shall be at least 5dBA lower than the existing background noise level at any
Pre occupation condition Chart Plan/Unilv er/MIlest one
Informative
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Informative
given time of operation. The noise levels shall be measured or predicted 1m externally to any window at the nearest residential facade. Measurements and assessment shall be made according to British Standard 4142:2014.
26 The site and building works required to implement the development shall be only carried out between the hours of 08.00 and 18.00 Mondays to Fridays and between 08.00 and 13.00 on Saturdays and not at all on Bank Holidays and Sundays.
27 The demolition secured through demolition PD Consent 20/02696/PRA and construction works shall be implemented in accordance with details approved pursuant to Condition 27 (Section 61 of Control of Pollution Act 1974).
28 The Development shall be carried out in accordance with the details approved on 08.03.2022 Reference 22/00411/CLC (Air Quality Technical Note Technical Note J13011 F1)
29 All Non-Road Mobile Machinery (NRMM) of net power of 37kW and up to and including 560kW used during the course of the demolition, site preparation and construction phases shall comply with the emission standards set out in chapter 7 of the GLAās supplementary planning guidance āControl of Dust and Emissions During Construction and Demolitionā dated July 2014 (SPG), or subsequent guidance. Unless it complies with the standards set out in the SPG, no NRMM shall be on site, at any time, whether in use or not, without the prior written consent of the local planning authority. The developer shall keep an up to date list of all NRMM used during the demolition, site preparation and construction phases of the development on the online register.
30 Prior to commencement of above ground works on the development hereby permitted, a Damage Cost Assessment in line with the requirements of the GLA Sustainable Design and Construction Practice must be submitted to and approved in writing by the local authority.
31 The development shall be implemented in accordance with the Fire Statement approved under 22/00557/CLC and retained as such for the lifetime of the development.
Informative
Informative
Informative
Informative
Pre above ground works condition AQ Consultan ts / Chart Plan App deposited 25/10/22 PP-11645457
Validated Ref: . 22/03432/CLC
Informative
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Consented 23/01/23
22/03432/CLC
32 The development shall be carried out in accordance with details approved by 22/03872/CLC on 5th January 2023 regarding the exhaust point to ensure the health and safety of residents nearby.
33 The Development shall be carried out in accordance with the details approved 11.03.2022 Reference 22/00359/CLC (Contamination Ground Investigation Report).
34 Should remedial works be required in relation to contaminated land, the remedial strategy shall be submitted to and agreed in writing by the Local Planning Authority, prior to the commencement of the development works and remedial works. On completion of the agreed remedial works, a closure report and certificate of compliance endorsed by the interested party/parties, shall be submitted to and agreed in writing by the Local Planning Authority, prior to the occupation of the site by end users.
35 If during implementation of this development, contamination is encountered which has not previously been identified, the additional contamination shall be fully assessed and a specific contaminated land assessment and associated remedial strategy shall be submitted to and agreed in writing by the Local Planning Authority before the additional remediation works are carried out. The agreed strategy shall be implemented in full prior to completion of the development hereby approved.
Informative
InformativeRemedial works condition
InformativeContamination condition
36 Prior to commencement of groundworks (excluding site investigations and demolition), a final detailed drainage design, including drawings, supporting calculations, SuDS Statement and Drainage Assessment Form shall be submitted to and approved in writing by the local planning authority. A detailed management plan confirming routine maintenance tasks for all drainage components must also be submitted to demonstrate how the drainage system is to be maintained for the lifetime of the development. The system shall be implemented and thereafter managed and maintained in accordance with the approved details Pre above groundworks condition MCLH Application deposited and validated 22/09/22 Ref: 22/03000/CLC
Consented 09/05/23
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Informative
37 No building hereby permitted shall be occupied until evidence (photographs and installation contracts) is submitted to demonstrate that the sustainable drainage scheme for the site has been completed in accordance with the submitted details. The sustainable drainage scheme shall be managed and maintained thereafter in accordance with the agreed management and maintenance plan for all of the proposed drainage components
38 Within 6 months of the commencement of any development above ground level, details of waste and recycling facilities to serve the development to which this permission relates shall be submitted to and approved in writing by the local planning authority.
Within 6 months of commencement of above groundworks condition
39 The development (including any works of demolition) shall be carried out in accordance with details approved under 22/00306/CLC (Arboricultural Report and Drawings). Informative
40 The approved protection scheme (Condition 39) shall be implemented prior to commencement of any work on site including demolition, and be maintained to the reasonable satisfaction of the Local Planning Authority until the completion of the development or until such stage as detailed within the approved AMS.
Informative
41 The development shall be carried out in accordance with the submitted Flood Risk Assessment (FRA) by Cole Easdon Consultants Limited (dated November 2022; issue no. 2; job no. 8922) and the Design Note by Robert Bird Group titled āFlood Volume Attenuation Strategy Clarifications ā Updated MSCPā (dated 02/09/2022; project no. 4881; document no. 4881-RBGZZ-XX-DN-CV-87002, issue 02) and the following mitigation measures it details:
Finished floor levels shall be set no lower than 8.8mAOD for more vulnerable residential uses
Informative
MCLH Application deposited with LPA 07/08/23
Ref: 23/02158/CLC
Validated 09/08/23
Consented 11/10/23
Park Road,
RH2 0DD ā
661 054 E: barry@chartplan.co.uk
Suite 21, High Cedars, 20 Wray
Reigate
Registered in England: 5204488 T: 01883 730 877 M: 07843
Pre occupation condition MCLH
⢠Finished floor levels shall be set no lower than 8.4mAOD for less vulnerable commercial uses
⢠Finished floor levels shall be set no lower than 7.9mAOD for the commercial reception area
⢠Flood storage mitigation shall be provided
⢠Flood voids shall be installed
These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the schemeās timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development.
42 The development shall be carried out in accordance with the submitted Interim Flood Storage Scheme detailed within the letter from MNP to the Environment Agency (SV/ib/220051-04; dated 15 February 2021), with the location of the temporary storage amended in the Design Note by Robert Bird Group titled āFlood Volume Attenuation Strategy Clarifications ā Updated MSCPā (dated 02/09/2022; project no. 4881; document no. 4881-RBG-ZZ-XX-DN-CV-87002, issue 02). The car park ramp tank will be implemented at the trigger points specified and remain in perpetuity until the demolition of Lever House is complete.
43 Prior to occupation, a maintenance plan to manage the flood voids and grilles over the lifetime of the development will be submitted to, and approved in writing by, the local planning authority in consultation with the Environment Agency. The Plan should cover general maintenance and inspection as well as maintenance after a flood event. The approved management plan will then be implemented in full throughout the lifetime of the development.
44 Prior to occupation, a scheme detailing the flood resistance measures must be submitted to, and approved in writing by, the local planning authority with guidance from the Environment
Suite
High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
21,
Informative
occupation
MCLH
Pre
condition
Pre
MCLH
occupation condition
Agency. The scheme should include details on the passive flood barriers up to 8.31 metres above Ordnance Datum (mAOD) to protect: The shared reception of the Hive and Honey Buildings The car park basement access ramp, stairwell and lift lobbies The scheme shall be fully implemented and subsequently maintained, in accordance with the schemeās timing/phasing arrangements, or within any other period as may subsequently be agreed, in writing, by the local planning authority.
45 Surface water draining from areas of car park hardstanding shall be passed through an oil separator or series of oil separators, prior to being discharged into any watercourse, soakaway or surface water sewer. The separator(s) shall be designed and constructed to have a capacity compatible with the area being drained, shall be installed prior to the occupation of the development and shall thereafter be retained and maintained throughout the lifetime of the development. Clean roof water or vehicle washdowns and detergents shall not pass through the separator(s) and should be drained instead to foul sewer or sealed system.
46 A Car Park Management Plan demonstrating how the use of the car park will be controlled, including any restrictions and detailing the signage necessary within the site to direct pedestrians and vehicles shall be submitted to and approved in writing by the local planning authority before the first occupation of the development. The development shall be carried out in accordance with the approved details. Pre occupation condition
47 By the time the development hereby permitted is substantially complete, pedestrian/vehicular intervisibility splays of 2.8 m x 3.3 m shall have been provided in each direction where the access meets the back edge of footway, and shall be permanently retained free from any obstruction to visibility higher than 1.0m above ground level.
Informative
MCLH / Occupier
48 Within 6 months of MCLH Application deposited 03/04/23 Consented 31/05/23
Suite
Park Road,
RH2 0DD ā
054 E:
21, High Cedars, 20 Wray
Reigate
Registered in England: 5204488 T: 01883 730 877 M: 07843 661
barry@chartplan.co.uk
Informative
'Within six months of the commencement of the above ground development' details regarding the relocated bus driver welfare facilities on Brook Street, have been submitted to and agreed in writing by the Local Planning Authority. The relocated bus driver welfare facilities shall be delivered in accordance with time frames agreed with the Local Planning Authority prior to development, other than demolition and thereafter permanently retained.
Bus driver welfare facilities will be retained throughout development.
49 A. The development hereby permitted shall incorporate security measures to minimise the risk of crime and disorder and meet the specific security needs of this development in accordance with Secured by Design Commercial 2015 or its equivalent required security standards. Details of these measures shall be submitted to and approved in writing by the local planning authority prior to commencement of the development and shall be implemented in accordance with the approved details prior to occupation.
B. As the proposed development is in close proximity to Kingston Town Centre, a crowded place, I would seek that that a blast assessment be completed by a member of the Register of Security Engineers & Specialists (RSES); this is order to determine the appropriate glazing specification for the building(s).
C. Prior to occupation of the offices a Secured by Design accreditation certificate or its equivalent from the Metropolitan Police Design Out Crime Office shall be submitted to and approved by the Local Planning Authority.
commencement of above groundworks condition
Ref: 23/00892/CLC
D) Prior to the functioning of the multi-story carpark Park Mark Certification is achieved. Pre development condition MCLH / FHPM / Kabsec App deposited 21/02/22
49 REVISED
. A. The development hereby permitted shall incorporate security measures to minimise the risk of crime and disorder and meet the specific security needs of this development in accordance with Secured by Design details approved under
Within 3 months post commencement of ground works.
Validated 22/02/22
Ref: 22/00558/CLC
(Originally submitted under Planning Consent 20/02499 /FUL ā App form sent to LPA to request transfer to this app 19/04/2022)
(TRANSIT APPLICATION )*
Consented 28/04/22
TO BE REVISED AS BELOW
Park Road,
RH2 0DD ā Registered
730 877
07843 661 054 E: barry@chartplan.co.uk
Suite 21, High Cedars, 20 Wray
Reigate
in England: 5204488 T: 01883
M:
22/00558/CLC (other than the car park/ cycle parking proposed in Building C which is superseded by this permission.) Details of the car park/ cycle parking measures shall be submitted to and approved in writing by the local planning authority within 3 months of commencement of above ground works of the car park. The development shall be implemented in accordance with the approved details prior to occupation. B. As the proposed development is in close proximity to Kingston Town Centre, a crowded place, I would seek that a blast assessment be completed by a member of the Register of Security Engineers & Specialists (RSES); this is in order to determine the appropriate glazing specification for the building(s). C. Prior to occupation of the offices a Secured by Design accreditation certificate or its equivalent from the Metropolitan Police Design Out Crime Office shall be submitted to and approved by the Local Planning Authority. D. Prior to the functioning of the multi-storey car park, Park Mark Certification is achieved. The development shall be implemented in accordance with the approved details.
50 A retail management plan to include opening hours and the link to the wider occupation of the site shall be submitted to the local planning authority for approval prior to commencement of the use of the Eden St retail units. The retail units shall operate in accordance with the approved management plan.
51 Prior to occupation of the new office building, the woodland walk shall be made available to members of the public in accordance with hours of access and a management plan to be submitted to the local planning authority for approval. The woodland walk shall operate in accordance with the approved details.
52 The car park shall be implemented in accordance with the details approved under 22/03504/CLC dated 29th December 2022.
53 The development shall be implemented in accordance with the details approved on 07.03.2022 under reference 22/00292/CLC (Water re-use/harvesting).
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Pre use condition Occupier
Pre
Occupier
occupation condition
Informative
Informative
54 Details shall be submitted to the local planning authority prior to commencement of development to demonstrate how the comprehensive landscaping strategy would achieve the proposed Urban Greening Factor of at least 0.3 within the site. The development shall be carried out in accordance with the approved details prior to occupation of the development.
55 The minimum water consumption targets as per The London Plan 2021, i.e. 105 l/person/day for residential units and a BREEAM rating of āExcellentā for the Wat 01 credits for non-residential uses. It should be stressed that these are the minimum requirements and need to be improved upon where possible
56 . Air Quality Neutral Assessment: A Damage Cost Assessment using the most up to date damage cost toolkit from Defra and the most recent version of the EFT must be submitted to and approved in writing by the local planning authority within 3 months of commencement of development.
57 The development must be carried out in accordance with the Dust Management Plan Reference 22/00618/CLC approved on 07.03.2022. The applicant must install PM10 monitoring equipment at the site boundary, with exact locations to be determined through discussion with the local authority Environmental Health department.
58 No construction shall take place within 5m of the water main. Information detailing how the developer intends to divert the asset / align the development, so as to prevent the potential for damage to subsurface potable water infrastructure, must be submitted to and approved in writing by the local planning authority in consultation with Thames Water. Any construction must be undertaken in accordance with the terms of the approved information. Unrestricted access must be available at all times for the maintenance and repair of the asset during and after the construction works.
condition
Within 3 months of commencement of development condition
Report to be submitted ā No time constraint specified.
Application deposited 03/04/23 Ref: 23/00893/CLC Consented 22/05/23
Consultan ts App deposited 25/10/22 PP-11645457
Consented 23/01/23
22/03432/CLC
Suite
High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
21,
MCLH
Pre development
Informative
AQ
Informative
MCLH
59 Any piling must be undertaken in accordance with the terms of the approved piling method statement approved under 22/00390/CLC.
60 In order to demonstrate compliance with the ābe seenā postconstruction monitoring requirement of Policy SI 2 of the London Plan, the legal Owner shall at all times and all in all respects comply with the energy monitoring requirements set out in points a, b and c below. In the case of non-compliance the legal Owner shall upon written notice from the Local Planning Authority immediately take all steps reasonably required to remedy noncompliance. a. Within eight weeks of planning permission being issued by the Local Planning Authority, the Owner is required to submit to the GLA accurate and verified estimates of the ābe seenā energy performance indicators, as outlined in Chapter 3 āPlanning stageā of the GLA āBe seenā energy monitoring guidance document, for the consented development. This should be submitted to the GLA's monitoring portal in accordance with the āBe seenā energy monitoring guidance. b. Once the as-built design has been completed (upon commencement of RIBA Stage 6) and prior to the building(s) being occupied (or handed over to a new legal owner, if applicable), the legal Owner is required to provide updated accurate and verified estimates of the ābe seenā energy performance indicators for each reportable unit of the development, as per the methodology outlined in Chapter 4 āAsbuilt stageā of the GLA āBe seenā energy monitoring guidance. All data and supporting evidence should be uploaded to the GLAās monitoring portal. The owner should also confirm that suitable monitoring devices have been installed and maintained for the monitoring of the in-use energy performance indicators, as outlined in Chapter 5 āIn-use stageā of the GLA āBe seenā energy monitoring guidance document. c. Upon completion of the first year of occupation following the end of the defects liability period (DLP) and for the following four years, the legal Owner is required to provide accurate and verified annual in-use energy performance data for all relevant indicators under each reportable unit of the development as per the methodology outlined in Chapter 5 āIn-use stageā of the GLA āBe seenā energy
Various submissions
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Informative
monitoring guidance document. All data and supporting evidence should be uploaded to the GLAās monitoring portal. This condition will be satisfied after the legal Owner has reported on all relevant indicators included in Chapter 5 āIn-use stageā of the GLA āBe Seenā energy monitoring guidance document for at least five years. .
61 The development shall be carried out in accordance with the approved details ref. 22/00622/CLC and maintained as such in perpetuity.
62 The development shall be carried out in accordance with the plans and details approved under 22/03626/CLC (Drinking Water Infrastructure) approved 30/12/22, and drinking water made available to the public for free in accordance with the plans and details prior to occupation of the development, and in perpetuity.
63 The measures set out in the Air Quality Positive Statement AQPS approved on 08.03.2022 under reference 22/00412/CLC shall be implemented in accordance with the details so approved, and thereafter retained, unless otherwise agreed in writing by the local planning authority.
64 Prior to the occupation of each building the post-construction tab of the GLAās whole life carbon assessment template should be completed accurately and in its entirety in line with the GLAās Whole Life Carbon Assessment Guidance. The post-construction assessment should provide an update of the information submitted at planning submission stage, including the whole life carbon emission figures for all life-cycle modules based on the actual materials, products and systems used. This should be submitted to the GLA at: ZeroCarbonPlanning@london.gov.uk. along with any supporting evidence as per the guidance. Confirmation of submission to the GLA shall be submitted to, and approved in writing by, the local planning authority, prior to occupation of the relevant
65 The development shall be carried out in accordance with the Ducting Space for Full Fibre Connectivity Infrastructure Plans approved on 07.03.2022 under reference 22/00681/CLC these
Informative
Informative
Informative
Informative
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
building
Pre occupation condition MCLH
plans shall be implemented prior to occupation and maintained as such in perpetuity.
66 Prior to the occupation any building, a Post Completion Report setting out the predicted and actual performance against all numerical targets in the relevant Circular Economy Statement shall be submitted to the GLA at: circulareconomystatements@london.gov.uk along with any supporting evidence as per the GLAās Circular Economy Statement Guidance. The Post Completion Report shall provide updated versions of Tables 1 and 2 of the Circular Economy Statement, the Recycling and Waste Reporting form and Bill of Materials. Confirmation of submission to the GLA shall be submitted to, and approved in writing by, the local planning authority, prior to occupation. Pre occupation condition
67 Notwithstanding the submitted details, prior to commencement of any above ground development (excluding demolition), details of a plant screen on top of Block A and Block B shall have been submitted to and approved in writing by the local planning authority. The approved plant screen shall be installed in accordance with the approved details prior to the occupation of the development hereby approved.
NMA APPLICATIONS
NMA Application deposited re amendments to Building A and B Spandrel Panels
Prior to commencement of above ground works MCLH/ DAA App deposited 25/10/22 PP-11631141
Consented 26/01/23
22/03431/CLC
NMA Condition 3 (Facing Materials)
Foot Bridge Link
Deposited with LPA 09/08/23
Ref: 23/02182/NMA
Validated 09/08/23
Deposited 25/09/23
Validated 27/09/23 23/02623/NMA
Deposited and validated 03/10/23
Ref: 23/02702/NMA
Consented 07/09/23
01883
Registered in England: 5204488
Consented 23/04/24
Consented 23/04/24
RH2 0DD
Suite 21, High Cedars, 20 Wray Park Road, Reigate
ā
T:
730 877 M: 07843 661 054 E: barry@chartplan.co.uk
MCLH
Application submission Progress Consent
Section 106 Obligations
1 Affordable Workspace contribution The Owner covenants to pay the Affordable Workspace Contribution to the Council prior to Occupation of the Development.
2 Kingston Employment Support Services Contribution Kingston Employment Support Services Contribution" means the sum of £232,000 Index Linked to be paid by the Owner to the Council towards the Council's work match brokerage initiative;
3 Skills Employment and Apprenticeship Plan Contribution.
4 The Owner covenants to submit to the Council for approval a Skills Employment and Apprenticeship Plan āConstruction Phase within 3 months of Commencement of the Development to include the following provisions:
Skills Employment and Apprenticeship Plan Contribution" means the sum of £50,000 Index Linked to be paid by the Owner to the Council towards implementation of the Skills Employment and Apprenticeship Plan.
⢠70 employment opportunities for residents of the South London Partnership Boroughs or students and graduates of the Mayor's Construction Academy.
⢠20 apprenticeships for Local Residents.
⢠Two Local Businesses to be invited to quote for
Ā£250,000 Prior to Occupation of the development
Ā£232,000, Prior to Commencement of the development. Paid - 6th February 2023
Ā£50,000 Prior to Commencement of the development Paid - 6th February 2023
Pre-Construction SEP & Stakeholder Allocation sent to LPA 03.07.23
Within 3 month of commencement of the development
Submitted to the Council for approval
Suite
Park Road,
RH2 0DD ā Registered in England: 5204488
054 E: barry@chartplan.co.uk NMA Condition 1 ā Louvre NMA Application validated
Consented 23/04/24
21, High Cedars, 20 Wray
Reigate
T: 01883 730 877 M: 07843 661
02/04/24 Ref: 24/00017/NMA
Value / percentage Timescale Latest Status
No. Item Description
5 Skills Employment and Apprenticeship Plan āOperational phase
6 Carbon Dioxide Emissions Target
7 Carbon Dioxide Offsetting Contribution
contracts less than £150,000 in value; and
⢠Not less than 15% of the total value of goods and services procured throughout the construction phase to be procured from Local Businesses or businesses based in Neighbouring Boroughs The Owner covenants to use its best endeavours to comply with the Skills Employment and Apprenticeship Plan āConstruction Phase during the construction of the Development PROVIDED THAT the Owner and the Council may agree amendments to the Skills Employment and Apprenticeship Plan ā Construction Phase in writing from time to time.
Skills Employment and Apprenticeship Plan ā Operational Phase" means a plan setting out targets for local employment, skills and training and detailing mechanisms for delivering such opportunities during the operational phase of the Development
Carbon Dioxide Emissions Targetā means a 35% carbon reduction against Part L2a of the Building Regulations 2013. 35% carbon reduction against part L2a of the Building Regulations 2013
Carbon Dioxide Offsetting Contribution" means a sum of money (Index Linked) calculated on the basis of £60 per tonne for 30 years to be agreed between the Council and Owner (both parties acting reasonably) and paid by the Owner to the Council in the event that the Development cannot achieve the Carbon Dioxide Emissions Target and the shortfall in
Ā£60 per tonne for 30 years to be agreed
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2
Within 18 months of commencement of the development.
Following practical completion
Following practical completion
0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Action for Unilever.
emissions reduction has not been offset through an accredited scheme or alternative off site off setting has not been agreed with the Council, to be used if payable towards the Council's Carbon Offset Fund which seeks the delivery of carbon dioxide emissions reductions projects within the Royal Borough of Kingston Upon Thames inter alia through retrofit of social housing, schools and civic buildings, investment in renewable energy projects and low-carbon lighting projects;
8 Energy Monitoring Portal āEnergy Monitoring Portalā means the āBe seenā webpage of the GLAās website and the email address ZeroCarbonPlanning@london.gov.uk, or any other such method of submission that may replace this N/A
9 Construction Environmental Management Plan Construction Environmental Management Planā means the plan to be submitted by the Owner to the Council for approval in accordance with paragraph 15 of Schedule 1; N/A
10 Construction Phase Flood Management Plan Construction Phase Flood Management Strategy" means the measures set out in the flood risk assessment prepared by Cole Easdon Consultants Limited dated November 2020 (issue 5) submitted with the Planning Application and the supplementary letter issued by Mason Navarro Pledge Limited dated February 2021 attached to this deed at Appendix 2 as the same relate to the Land;
N/A
To be submitted within 8 weeks of the grant of the Planning Permission Completed
Prior to Commencement of the Development the Owner shall submit the Construction Environmental Management Plan Submitted and approved
The Development shall be constructed and completed in accordance with the approved Construction Phase Flood Management Strategy. Ongoing
11 Rooftop Garden Management Plan Rooftop Garden Management Plan" means the plan for the provision of managed public access to the Rooftop Garden as may be varied from time to time in writing; N/A
Prior to Occupation of the Development Action for Unilever.
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
12 Car Park Management Plan
13 Delivery and Service Management Plan
14 District Heating Network
"Car Park Management Plan" means a management plan detailing measures for the management of the use of the car park within the Development including restrictions on use of the car park by users other than the occupier(s) of the offices within the Development. N/A
Delivery and Servicing Management Planā means the plan to be submitted by the Owner to the Council for approval in accordance with paragraph 16 of Schedule 1; N/A
Prior to Occupation of the Development
Prior to Occupation of the Development Action for Unilever
15 Highway and Public Realm Enhancement Works
āDistrict Heating Network" means a third party district heating network to be developed within the Council's area and which is capable of providing electricity to the Development; N/A DHN rooms provided within Building A and B.
āHighway and Public Realm Enhancement Works" means the highway and public realm enhancements identified for indicative purposes only on the Highway and Public Realm Enhancements Plan N/A
16 TFL Works TfL Works" means the relocation of Transport for London's welfare facility from Brook Street near the corner of Eden Street as shown for indicative purposes only on the Highway and Public Realm Enhancements Plan; N/A
17 Travel Plan
18 Woodland Walk Management Plan
Travel Planā means a full travel plan to be submitted to the Council for approval in consultation with Transport for London pursuant to paragraph 14 of the First Schedule; N/A
Woodland Walk Management Planā means a management plan to be submitted to and agreed by the Council in accordance with paragraph 8 of the First Schedule which shall contain arrangements for management of the Woodland Walk N/A
Following an agreement pursuant to section 278 of the Highways Act 1980 Discussions ongoing
Within 12 months following first Occupation of the Development Will form part of S278 works
Prior to Occupation of the Development Action for Unilever
Prior to Occupation of the Development Action for Unilever
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk
Suite 21, High Cedars, 20 Wray Park Road, Reigate RH2 0DD ā Registered in England: 5204488 T: 01883 730 877 M: 07843 661 054 E: barry@chartplan.co.uk including the management of public access
the
Walk;
to
Woodland
FH090-151015 appendix c EAI
Tracker
project: Project Honey - Surrey House Island Site client: Globe Kingston Limited date: 05-Jun-24 EAI no. EAI date description CRF / other ref. cost agreed 1 25-May-22 BIM CO-034 382,720.00 £ 2 25-May-22 Town Hall CO-024(S1) 54,080.00 £ 3 26-May-22 Gym Loadings Study CO-039 8,268.00 £ 4 26-May-22 Kerb Drop - Lever House CO-093 2,508.42 £ 5 31-May-22 S106 - Latest Version N/A - £ 6 24-Jun-22 Town Hall and Gym Piling/ Substructure CO-041 27,473.05 £ 7 13-Jul-22 Additional Basebuild Energy Modelling, for ASHRAE 90.1 / for LEED CO-042 57,686.57 £ 8 28-Sep-22 Below ground drainage design changes CO-046 15,552.26 £ 9 29-Sep-22 Omission of CAT A across a number of floor on Building A and B CO-053 3,391,861.52 -£ 10 29-Sep-22 Bridge Link Widening to 7.5m CO-035 33,422.00 £ 11 05-Oct-22 Town Hall and Gym full instruction CO-024(S4) 1,658,599.00 £ 12 10-Oct-22 MER/ SER Building A and B changes CO-043 8,840.00 £ 13 13-Oct-22 S73 Façade and Plant Screen Amendments 47,098.21 £ 14 13-Oct-22 MER SER Building B 6th Floor Change CO-043 8,941.00 £ 15 28-Oct-22 Instruction to proceed with the column changes in Building B - £ 16 28-Oct-22 Instruction to proceed 130 additional penetrations and connections into drainage stacks in Building A and B CO-046A 40,052.16 £ 17 28-Oct-22 Instruction to proceed with design of rainwater harvesting under Building C CO-049 9,260.00 £ 18 28-Nov-22 Instruction to proceed with additional pile matt TBC 19 28-Nov-22 All items currently referenced as RAL9010 to be updated to RAL 9016. CO-057 - £ 20 28-Nov-22 Gym full instruction including increase in size of columns CO-059 49,568.31 £ 21 01-Dec-22 Building C Design Fees - Expenditure of Prov Sum N/A 360,000.00 £ 22 14-Dec-22 Building A Ground Floor Amendment CO-060 48,047.41 £ 23 14-Dec-22 Signage Design Costs CO-050 11,400.00 £ 24 27-Jan-23 Rainwater Harvesting tank procurement CO-064 26,406.96 £ 25 27-Jan-23 CHW/ LTHW Uplift Design CO-065 16,473.60 £ 26 27-Jan-23 Ventilation Uplift Design CO-066 11,980.80 £ 27 27-Jan-23 Town Hall Splice Details CO-067 Included in EAI 11 28 27-Jan-23 White and Green Brick confirmation CO-068 82,836.00 £ 29 27-Jan-23 GRC Alternative CO-069 350,000.00 -£ 30 03-Feb-23 Building C FP McCann Procurement - Expenditure of Prov Sum CO-120 Prov Sum Expenditure 31 10-Feb-23 Green Wall Design CO-115 15,858.13 £ 32 14-Feb-23 Town Hall Amendments CO-024 6,507.30 £ 33 15-Feb-23 Building C Below Ground Obstruction CO-109 3,668.78 £ 34 06-Mar-23 LV Panel Design CO-071 11,980.80 £ 35 06-Mar-23 Domestic Water CO-072 10,483.20 £ 36 06-Mar-23 Structural Penetrations CO-073 15,498.08 £ FH020- 151015 https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/08 Instructions/EAI Tracker and Instructions/230605 EA instructions inc register Project Honey 103721 R20 LIVE CHANGE
employer's agent instruction register
employer's agent instruction register
EAI no. EAI date description CRF / other ref. cost agreed 37 09-Mar-23 Wicona CO-114 - £ 38 10-Mar-23 Rainwater Harvesting Tank below ground works CO-098 161,811.10 £ 39 20-Mar-23 New Sewer Connection and Manhole Connection CO-097 Prov Sum Expenditure 40 22-Mar-23 Internal Ramps CO-088 - £ 41 22-Mar-23 Town Hall Design Amendments CO-095 28,570.47 £ 42 24-Mar-23 Building B Spandrels CO-110 - £ 43 28-Mar-23 Terrace Doors CO-082 21,820.70 £ 44 31-Mar-23 Smart Buildings Design CO-078 29,996.37 £ 45 05-Apr-23 Building A penetrations in slab for tenant drainage CO-083 TBC 46 06-Apr-23 Building B penetrations in slab for tenant drainage CO-083 TBC 47 14-Apr-23 MSCP Cast In Channels CO-121 107,121.68 £ 48 17-Apr-23 WC Corridor RCPs CO-085 - £ 49 19-Apr-23 Secondary CAT A Omission CO-061 1,948,328.40 -£ 50 01-May-23 CCTV and access control omission CO-089 206,282.00 -£ 51 16-May-23 Terrace Finishes CO-087 - £ 52 16-May-23 Building A and B Spandrel Panels CO-111 - £ 53 18-May-23 Building C Ducts CO-103 5,517.57 £ 54 31-May-23 Building A Column Size Increase CO-112 - £ 55 31-May-23 Building A Metal Soffit Options CO-113 - £ 56 16-Jun-23 Building C Lift Order N/A - £ 57 16-Jun-23 Circle Sliding Doors CO-079 89,386.00 £ 58 16-Jun-23 Generator Uplift CO-091 21,378.42 £ 59 16-Jun-23 Domestic Water CO-072 18,060.41 £ 60 20-Jun-23 Gym Floor Design Fees CO-099 13,917.93 £ 61 20-Jun-23 Building B Feature Stair 02 Glazed Screen Omission CO-101 175,606.68 -£ 62 23-Jun-23 Utilities Provisional Sum N/A 250,861.60 -£ 63 26-Jun-23 Omission of Undefined Provisional Sums N/A 15,774.00 -£ 64 06-Jul-23 Service Yard Door Clear Opening CO-86 22,176.00 £ 65 11-Jul-23 Mullion Cover Strips Expended in prov sum 66 17-Jul-23 Ventilation Uplift CO-066 356,442.34 £ 67 17-Jul-23 LV Panel Enhancement CO-071 68,345.42 £ 68 17-Jul-23 Modified CAT A CO-074 353,735.16 -£ 69 21-Jul-23 Building C Prov Sum Maple Halsion - £ 70 25-Jul-23 Gym Floor Dead Load Increase CO-131 TBC 71 27-Jul-23 Omission of Soap Dispenser CO-118 31,284.00 -£ 72 15-Aug-23 MSCP Additional Fire Alarm Protection CO- 125 7,810.73 £ 73 15-Aug-23 CHW and LTHW Uplift CO-65 386,303.69 £ 74 15-Aug-23 RAL 9010 Reversion CO-106 5,821.83 £ 75 21-Aug-23 BOH Corridor Ceiling CO-116 95,947.93 £ 76 23-Aug-23 Building A & B Shell and Core Cleaners Sockets CO-123 69,128.09 £ 77 25-Aug-23 Rainwater Harvesting Tank Above Ground CO-100 57,018.51 £ 78 25-Aug-23 WC Hand Dryers (Provision) CO-127 5,938.91 £ 79 25-Aug-23 Building B Door Opening CO-128 - £ 80 09-Oct-23 Corian Alternative CO-135 20,282.52 £ 81 11-Oct-23 Building C Prov Sum Expenditure N/A Prov Sum Expenditure 82 11-Oct-23 Bridge Link Design CO-117 23,135.20 £ 83 25-Oct-23 Feature Stair Nosing CO-137 8,327.36 £ 84 25-Oct-23 Toilet Roll Holders CO-138 10,945.53 -£ 85 25-Oct-23 Temporary Measures CO-139 160,022.22 £ 86 31-Oct-23 Façade Lighting CO-75 129,624.46 £ 87 03-Nov-23 Internal & External Doors CO-133 8,412.80 £ 88 03-Nov-23 Building B Changing Places CO-124 14,196.60 £ 89 03-Nov-23 External Louvres CO-130 TBC 90 10-Nov-23 Door Vision Panel Beads CO-141 3,259.96 £ 91 10-Nov-23 Building A & B GF Screed & RAF Omission CO-136 TBC 92 10-Nov-23 Building C Planning Approval CO-142 175,936.00 £ 93 10-Nov-23 BREEAM Man02 CO-143 - £ 94 21-Nov-23 Building C Fitout & Metalwork Packages CO-148 TBC 95 29-Nov-23 Town Hall Steel Intumescent Paint CO-149 21,991.00 £ 96 29-Nov-23 Public Art CO-150 3,680.60 £ 97 01-Dec-23 Fire Curtains CO-152 517,266.00 £ 98 12-Dec-23 MSCP park mark requirements CO-153 5,300.00 £ 99 20-Dec-23 Blind Box Design CO-144 3,680.60 £ 100 20-Dec-23 Woodland walk path widening design CO-155 10,663.23 £ 101 11-Jan-24 WC Frameless Grilles CO-157 24,886.53 £ 102 11-Jan-24 Omission of Tea Point Ductwork and Fan Provision CO-156 29,891.91 -£ 103 12-Jan-24 Wiring Accessories CO-158 - £ 104 12-Jan-24 Blind Box Construction CO-144 TBC FH020- 151015 https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/08 Instructions/EAI Tracker and Instructions/230605 EA instructions inc register Project Honey 103721 R20 LIVE CHANGE
EAI no. EAI date description CRF / other ref. cost agreed 105 17-Jan-24 Disabled Refuge Emergency Phone Recess CO-159 13,998.16 £ 106 23-Jan-24 Public Art Schematic & Connection Design CO-160 15,248.20 £ 107 26-Jan-24 RAF Omission CO-161 138,611.42 -£ 108 26-Jan-24 Facade Galvanised Steel Brackets CO-162 - £ 109 12-Feb-24 Building A Baby Changing CO-164 5,681.37 £ 110 12-Feb-24 Building C Roof Landscape and Floor Finishes TBC 111 13-Feb-24 Building A Lv9 AHU Clash & BWIC CO-165 2,629.00 £ 112 15-Feb-24 Service Yard Door Proposal CO-166 - £ 113 21-Feb-24 Building A & B Manifestation CO-163 5,994.12 £ 114 23-Feb-24 Building C Shower Shelf & Soap Dispenser Omission CO-154 7,663.42 £ 115 18-Mar-24 Network Infrastructure CO-167 371,916.59 £ 116 19-Mar-24 BOH Door CO-122 23,976.48 £ 117 21-Mar-24 Building B Changing Places Construction CO-144 TBC 118 22-Mar-24 Access Control Hardware/ Containment & CCTV Mounts CO-168 177,601.07 £ 119 26-Mar-24 Brook Street Trees CO-169 TBC 120 26-Mar-24 Water Reduction CO -084 TBC 121 19-Apr-24 Floor Screed CO-172 - £ 122 19-Apr-24 Irrigation to Building C Roof Terrace CO-173 50,085.76 £ 123 08-May-24 RAF CO-174 - £ 124 15-May-24 Terrazzo Benches CO-175 TBC 125 15-May-24 FLOW detailed design CO-176 12,093.00 £ 126 17-May-24 Building C - External Doors and Louvres Prov Sum Expenditure 127 03-Jun-24 Service Notch CO-177 TBC 128 03-Jun-24 Soffit Lighting CO-178 TBC 129 04-Jun-24 External Lighting to Car Park Roof Terrace CO-170 TBC 130 04-Jun-24 S278 Setting Out CO-179 TBC FH020- 151015 https://francishunter.sharepoint.com/sites/FH/Shared Documents/Projects/03 current/10372 - Project Honey/08 Instructions/EAI Tracker and Instructions/230605 EA instructions inc register Project Honey 103721 R20 LIVE CHANGE
employer's agent instruction register
outline programme
FH090-151015 appendix d
FH090-151015 appendix e G&T
update report
Project Honey
Gardiner & Theobald Progress Report at 30 May 2024
General Update
Building facades and fit out are progressing.
Activities & Progress in Period
Contractor
Valuation and recommendation no 28 of MCLH works for April 2024.
Ongoing review of general & tenant variations.
Interface with tenant team
Ongoing dialogue with MACE cost team in relation tenant changes
Interface with funder team
None in the period
Cost Status
Gardiner & Theobald Cost Report 23 issued 26 April 2024 and Report 24 to be issued 5 May 2024
Procurement
S278 works to be reviewed when issued by MCLH
Design Development
None in the period
Project Honey
Gardiner & Theobald Progress Report at 30 May 2024
Future Works
Continuing valuation of the works. Valuation 29 due date 3 June 2024.
Agreement of remaining provisional sums.
Agreement of further tenant changes.
Agreement of costs with MACE against AFL position.
Information Required
MCLH final costs for deck car park.
MCLH response to outstanding TVOāS
Team
No changes
MCLH update report
FH090-151015 appendix f
Progress
2024 Progress
Report 25 - 30.05.24
Report25 ProjectHoney
Progress Report 25 - 30.05.24 Contents 1. CDM / Health and Safety ......................................................................................................3 2. List of sub-contractors on site: 3 3. Construction Update.............................................................................................................3 4. Progress/Programme Dropline..............................................................................................3 5. Lookahead Activities.............................................................................................................4 6. Key Risk Schedule.................................................................................................................4 7. Outstanding Instructions/Tennant Variations........................................................................4 8. Site Wide Issues / Matters Affecting Progress........................................................................5 9. Quality and Environmental ...................................................................................................5 10. Sustainability.......................................................................................................................6 11. Architects Report.................................................................................................................7 12. Civils/Structures Report ............................................................. Error! Bookmark not defined. 13. MEP Report ............................................................................... Error! Bookmark not defined. 14. Utility Tracker......................................................................................................................8 15 Contract and Commercial Matters...................................................................................... 14 15.1 Valuation........................................................................................................................... 14 15.2 Projected Final Account ..................................................................................................... 14 15.3 Provisional Sum................................................................................................................. 14 15.5 Project Cash Flow .............................................................................................................. 18 16 Warranty Tracker............................................................................................................... 19 17 Progress Photos ................................................................................................................. 19 18 SHEQ Audit 24 19 Planning Tracker/Update ................................................................................................... 31 20 Building Control Tracker..................................................................................................... 31 21 AOB........................................................................................... Error! Bookmark not defined.
1. CDM / Health and Safety
⢠Construction Phase and Environmental plans are in place and updated as required.
⢠All risk assessments / method statements and COSHH assessments currently up to date for the work activities on site.
2. List of sub-contractors on site:
⢠OāNeill & Brennan ā Logistics/Waste Management
⢠Trident ā Temporary Electrics & Water
⢠LTC ā Tower Cranes
⢠ATJ ā Partitions/Ceilings
⢠Halsion ā MEP
⢠RECO ā Hoists
⢠CMF ā Metalwork
⢠Clarkes ā FaƧade
⢠AYM ā Roofing & Cladding
⢠Swiftcrafted ā Core fit out/Joinery.
⢠Kingspan ā Raised Access Flooring
⢠Original Joinery ā Building C Fitout
⢠OWS ā Glazed Doors
⢠Frost ā Car Park Landscaping
⢠Coopers - Concertina Fire Curtains
⢠A1S ā Lift Lobby Fire Curtains
3. Construction Update
⢠Partitions are complete up to level 8 building A, and level 10 building B.
⢠CAT A - Ceilings ongoing to all floors.
⢠MEP is progressing up to level 8 building A, and level 10 building B
⢠Building B Power on ā Live commissioning has commenced.
⢠UKPN have completed their installations.
⢠Clarke Façades currently progressing:
Block A: Unitised progressing to level 5. Stick CW from GF ā Level 2 ongoing. Block B: Unitised complete to level 7, level 8 & 9 ongoing Stick CW from GF- Level 2 ongoing
⢠AYM Roofing complete on Buildings A, B & C.
⢠Swift crafted progressing with joinery/tiling/vanity units/doors to Building A & B cores
⢠Car park fit out ongoing.
⢠All Key plant positioned on to the roof.
⢠Otis have completed 6No. lifts (Tested). Currently working on the next batch of lifts.
⢠Raised Access Flooring complete in Building B to levels 2,3,4, 5 and progressing with 6 Building A Level 2 has commenced
⢠Link bridge steelwork and metal decking installed.
⢠Feature stair steelwork complete
⢠Feature Stair Fire Curtains
4. Progress/Programme Dropline
⢠Block A ā 3 weeks behind programme due to Twin wall delay
⢠Block B ā 4 weeks behind programme due to Twin wall delay
⢠Block C ā 1 week behind programme
Report
- 30.05.24
Progress
25
5. Lookahead Activities
⢠CAT A ceilings ongoing
⢠MEP works ongoing.
⢠Commissioning ongoing
⢠CMF steelwork ongoing (Reception steel, balustrades etc)
⢠Frost Landscaping to Block C roof
⢠Clarkes Façade progressing to buildings A & B
⢠Lift installations ongoing
⢠Power on to A & C
⢠Building C Fitout ongoing
⢠Kingspan progressing in Blocks A&B
6. Key Risk Schedule
⢠Future client variations/TVRās
⢠Twin Wall Core impact
⢠MSCP Provisional Sum
⢠Planning
o Building A & B Spandrel Panel ā NMA Granted 7th September 23
o Building A & B Equitone ā NMA Granted 24th April 24
o Building C FaƧade ā NMA Granted 24th April 24
⢠LFB āsign offā
o CAT A Omissions / Temporary Measures ā discussions ongoing regarding Building Control Final Certification
o Building C FaƧade ā LFB submission agreed on current Maple proposal
o Building C Sprinkler Requirements ā Insurance Acceptance issued via email from client
⢠Building Control Certification
o Discussions ongoing with SWECO regarding Final Cert and Letter of Comfort
o MCLH responded to Shore Comments (12st May 24)
⢠Building C Parkmark Accreditation ā instruction issued in part
⢠Tenant Fit-Out design potentially not aligned with MCLH ERās / Instructed works (e.g. Modified CAT A / Omissions)
⢠Access Control ā Omitted from MCLH Contract ā EAI 118 Issued
⢠S278 Works
o Tender Pack issued for pricing. Quotations received.
o Works will not be completed for Practical Completion
⢠SMART Buildings ā EAI 115 issued and programme impact being discussed
7. Outstanding Instructions/Tenant Variations
⢠Integration of Smart Building Technology ā EAI 115 issued
⢠External Entrance Lighting ā cost submitted ā EAI to be issued
⢠EAI 29 Rev 1 to be reviewed and comments updated: Anti Drumming, Reverberation etc
⢠EOT 3 to be updated ā Removal of Early Access Dates Schedule, draft dates and protocol submitted to Francis Hunter
⢠EOT 4 to be issued ā SMART Buildings to Building B ā awaiting response
⢠EAI 115 - SMART Buildings; to be updated to reflect agreed Scope and Programme
⢠Terrace FaƧade Penetrations (RFC 54) ā cost submitted, EAI to be issued
⢠General Instructions ā future RFCās instructed will more than likely impact Programme, for example -
- RFC 005 ā External Building Signage; MCLH awaiting revised brief
- 30.05.24
Progress Report 25
- RFC 061 & 070 ā Woodland Walk and Building C Roof Terrace ā costs submitted, awaiting urgent EAI
- EAI 089 ā Louvres to FaƧade; design instruction received, design completed and submitted Client reviewing current design, MCLH awaiting direction. Impact on construction to be reviewed. Advised works to be completed following Sectional Completion
- EAI 096 / EAI 125 Public Artwork ā RBG & Clarkeās design instructed and completed. FH have further instruction (EAI 125) for RBG detailed design
- EAI 104 Rev 3 ā Blind Boxes have been instructed including recommencement of Curved Grill procurement. Potential Programme impact as already advised
- EAI 117 ā Building B GF Changing Layout; reduced Scope instructed, potential risk to Programme.
8. Site Wide Issues / Matters Affecting Progress
⢠Twin Wall impact
⢠Wayleaves
9. Quality and Environmental
⢠Environmental plan in place
⢠Section 61 approved
⢠CPDs carried out: Pudlo Waterproofing, quelfire (fire collars), CCL (post tensioning), Imperial Ductwork, British Gypsum and Wicona.
Progress Report 25 - 30.05.24
Progress Report 25
30.05.24 10. Sustainability
-
BREEAM (Tracker attached)
Progress Report 25 - 30.05.24
Progress Report 25
- 30.05.24
11. Utility Tracker
Progress Report 25
12 MEP Report
- 30.05.24
Progress Report 25
13 Civils
Structures Report
- 30.05.24
&
Report 25 - 30.05.24
Progress
14.
Architectural Report
Progress Report 25 - 30.05.24
Progress Report 25 - 30.05.24
15.1 Valuation
- Valuation Nr 29 to be submitted on the 28th May 2024
- Next payment Cert. due on the 7th June 2024
15.2 Projected Final Account
Ā£121,511,301
15.3 Provisional Sums
⢠Statutory Authorities £735,000
o £735,000 Omitted (under EAI 063)
o £461,993.51 Addition (under EAI 063)
⢠Bird Deterrent to Facades Ā£50,000 ā to be omitted
⢠Fibre Backbone Cabling for Wired Score Ā£180,000 ā awaiting instruction
⢠Public Art Works £50,000 (design instructed under EAI 096 & EAI 125)
⢠Asbestos £5,000 (Omitted under EAI 063)
⢠Newts, bats & bat roosts, Japanese knotweed and hogweed. £5,000 (Omitted under EAI 063)
⢠UXO £5,000 (Omitted under EAI 063)
⢠Cycle Path Works including Green Wall to Carpark Ā£295,000 ā to be omitted
Progress Report 25 - 30.05.24 15 Contract and Commercial Matters
15.4 Employer Instructions
⢠EAI 001 ā BIM Level 2
⢠EAI 002 ā Townhall design feasibility
⢠EAI 003 ā Gym design feasibility
⢠EAI 004 ā Drop kerb
⢠EAI 005 ā S106
⢠EAI 006 ā Townhall & Gym additional piles (only)
⢠EAI 007 ā ASHRAE
⢠EAI 008 ā Below ground drainage
⢠EAI 009 ā CAT A Omission
⢠EAI 010 ā Bridge Link Widening
⢠EAI 011 ā Townhall & Gym
⢠EAI 012 ā MER and SER Loading Design
⢠EAI 013 ā S73 FaƧade and Plant Screen Amendment Rev1
⢠EAI 014 ā MER and SER Loading Changes - 6th Floor Building B
⢠EAI 015 ā Building B Column Sizes
⢠EAI 016 ā Above Ground Drainage
⢠EAI 017 ā Greywater and Rainwater Design
⢠EAI 018 ā Additional Pile Mat
⢠EAI 019 ā Change in RAL Colours
⢠EAI 020 ā Gym Structural Changes
⢠EAI 021 ā Building C Fees
⢠EAI 022 ā Building A Ground Floor Amendments
⢠EAI 023 ā Signage Design Costs
⢠EAI 024 ā Rainwater Harvesting Tank (Supply Only)
⢠EAI 025 ā CHW and LTHW Design
⢠EAI 026 ā Ventilation Uplift Design
⢠EAI 027 ā Splice Details
⢠EAI 028 ā Green and White Brick Confirmation
⢠EAI 029 ā GRC Alternative
⢠EAI 030 ā Expenditure of FP McCann MSCP Structure
⢠EAI 031 ā Green Wall Design
⢠EAI 032 ā Town Hall Design Amendments
⢠EAI 033 ā Building C Below Ground Obstruction
30.05.24
Progress
Report 25 -
⢠EAI 034 ā LV Design
⢠EAI 035 ā Domestic Water
⢠EAI 036 ā Structural Penetrations
⢠EAI 037 - Wicona
⢠EAI 038 ā Rainwater Harvesting Tank
⢠EAI 039 ā New Sewer Connection & Manhole
⢠EAI 040 ā Internal Ramps
⢠EAI 041 ā Townhall Amendments
⢠EAI 042 ā Spandrel Panels
⢠EAI 043 ā Terrace Doors
⢠EAI 044 ā SMART Buildings Design
⢠EAI 045 ā Building A ā Slab Penetrations for Future MEP
⢠EAI 046 ā Building B Slab Penetrations
⢠EAI 047 ā MSCP Cast In Channels
⢠EAI 048 ā WC Corridor RCPs
⢠EAI 049 ā Secondary CAT A Omissions
⢠EAI 050 ā CCTV and Access Control Omissions
⢠EAI 051 ā Terrace Finishes
⢠EAI 052 ā Building A and B Spandrels
⢠EAI 053 ā Building C Ramp Ducts
⢠EAI 054 ā Building A Column Sizes
⢠EAI 055 ā Building A Soffit to Retail Entrance
⢠EAI 056 ā Expenditure of Building C Lifts
⢠EAI 057 ā Circleslide Doors
⢠EAI 058 ā Generator Uplift TVR Construction Works
⢠EAI 059 ā Domestic Water TVR Construction Works
⢠EAI 060 ā Gym Floor Design
⢠EAI 061 ā Building B Stair Glazed Screen/Fire Curtain Omission (Levels 1-10)
⢠EAI 062 ā Expenditure of Utilities Prov Sum
⢠EAI 063 ā Omission of Undefined Provisional Sums
⢠EAI 064 ā Service Yard Door
⢠EAI 065 ā Mullion Cover Strips
⢠EAI 066 ā Ventilation TVR Construction Works
Progress Report 25 - 30.05.24
⢠EAI 067 ā LV Panel Enhancement Construction Works
⢠EAI 068 ā Modified CAT A
⢠EAI 069 ā Maple & Halsion MSCP Construction Works
⢠EAI 070 ā Gym Floor Dead Load Increase
⢠EAI 071 ā Omission of Soap Dispensers
⢠EAI 072 ā MSCP Additional Fire Alarm Protection
⢠EAI 073 ā CHW & LTHW Uplift
⢠EAI 074 ā RAL 9010
⢠EAI 075 ā BOH Corridor Ceilings
⢠EAI 076 ā Building A & B Shell and Core Sockets
⢠EAI 077 ā Rainwater Above Ground
⢠EAI 078 ā WC Hand Driers
⢠EAI 079 ā Building B Opening
⢠EAI 080 ā Corian Alternative
⢠EAI 081 ā Building C Packages (Brick, Block, Roof)
⢠EAI 082 ā Bridge Link Design
⢠EAI 083 ā Building A Feature Stair Nosing
⢠EAI 084 ā Omission of Toilet Roll Holders
⢠EAI 085 ā CAT A Temporary Measures
⢠EAI 086 ā FaƧade Lighting
⢠EAI 087 ā Internal & External Doors (Design)
⢠EAI 088 ā Building B Changing Places (Design)
⢠EAI 089 ā External Louvres (Design)
⢠EAI 090 ā Door Vision Panel Beads
⢠EAI 091 ā Building A & B GF Screed and RAF Omission
⢠EAI 092 ā Building C Planning Approval
⢠EAI 093 ā BREEAM MAN02 Credit omission
⢠EAI 094 ā Building C Fitout and Metalwork Packages
⢠EAI 095 ā Town Hall Intumescent paint
⢠EAI 096 ā Public Art Design
⢠EAI 097 ā Feature Stair Curtains
⢠EAI 098 ā MSCP Access Control/Park Mark/CCTV
⢠EAI 099 ā Blind Box Design
Progress Report 25 - 30.05.24
⢠EAI 100 ā Woodland Walk Widening Design
⢠EAI 101 ā WC Frameless Grilles
⢠EAI 102 ā Omission of Tea Point Fans & Ducts
⢠EAI 103 ā Wiring Accessories
⢠EAI 104 ā Blind Box Construction Rev3
⢠EAI 105 ā Disabled Refuge Phone Recess
⢠EAI 106 ā Public Art Schematic & Connection
⢠EAI 107 ā RAF Omissions
⢠EAI 108 ā Galv Brackets
⢠EAI 109 ā Building A Baby Changing
⢠EAI 110 ā Building C roof Landscaping
⢠EAI 111 ā Building A Level 9 AHU Clash
⢠EAI 112 ā Service Yard Door
⢠EAI 113 ā Building A & B Manifestation
⢠EAI 114 ā Building C Shower Shelf
⢠EAI 115 ā SMART Network Infrastructure
⢠EAI 116 ā BOH Door
⢠EAI 117 ā Building B Changing Places Instruction
⢠EAI 118 ā Access Control Hardware & CCTV Mounts
⢠EAI 119 ā Brook Street Trees
⢠EAI 120 ā Water Reduction
⢠EAI 121 ā Floor Screed
⢠EAI 122 ā Irrigation to Building C
⢠EAI 123 ā RAF Levels
⢠EAI 124 ā Terrazzo Benching (Building C)
⢠EAI 125 ā Public Art Detailed Design
⢠EAI 126 ā MSCP Expenditure (Ext. Doors, Louvres, Vinyl, Cycle Storage)
15.5 Project Cash Flow
⢠Cashflow issued on 1st December 22 in line with Townhall Instruction
⢠Cashflow Rev 1 issued on 8th August 23
⢠Cashflow Rev 2 issued on 6th February 24
⢠Cashflow Rev 3 issued on 6th March 24
Progress Report 25 - 30.05.24
16 Warranty / Sub-Contract / Appointment Tracker
⢠See attached
⢠Key Changes in the period
o Warranties ā Francis Hunter have issued client version as a REV E Tracker
o Certified Sub-Contracts
āŖ Sub-Sub-Contracts ā clarity needed around certifying of these
āŖ MCLH to issue any further redacted Sub-Contracts upon signing
17 Procurement schedule
Key Changes in the Period
⢠Building A & B - see attached
⢠Building C - see attached
18 Commercial and Contractual (in the Period)
⢠Early Access Protocol
o DRAFT issued to Francis Hunter
āŖ Overbury/Mace have returned comments
o Early Access Protocol meetings ongoing with Overbury & Mace
o Point cloud Survey Parameters issued by MCLH
⢠Early Warnings
o EWN 001 ā Brooke Street Closure; issued on 24/03/23
o EWN 002 ā Thames Water; issued on 18/10/23
o EWN 003 ā UKPN Wayleaves; issued on 19/03/24
⢠Relevant Events
o RE 001 ā Deferment ā EOT 01 issued
o RE 002 ā Deferment ā EOT 01 issued
o RE 003 ā Townhall Design ā EOT 02 issued
o RE 004 ā Townhall Construction ā EOT 3 issued
o RE 005 ā Smart Buildings ā EOT to be issued
Progress Report 25
30.05.24
-
Progress Photos
Progress
19
Report 25 - 30.05.24
Block A Unitised Progressing
Progress Report 25 - 30.05.24
Block B Pump Room Progressing
Progress Report 25 - 30.05.24
Building C Roof Progressing
Progress Report 25 - 30.05.24
Car Park Metalwork Ongoing
Progress Report 25
20 SHEQ Audit
- 30.05.24
Progress Report 25 - 30.05.24
Report 25 - 30.05.24
Progress
Progress
Report 25 - 30.05.24
Progress Report 25 - 30.05.24
Report 25 - 30.05.24
Progress
Report 25 - 30.05.24
Progress
Progress Report 25 - 30.05.24 21
22 Building
23
Planning Tracker/Update *Latest planning condition tracker has been issued
Control Tracker *Meeting arranged for Friday 31st May
Change Control Tracker
FH090-151015 appendix g
BREEAM tracker
Project Honey BREEAM Tracker - Design Stage
Ref Issue Credit Credit requirements Credits available Targeted Stage 4 Design Stage credit status Credit evidence responsibility Target completion date Credit progress Project delivery planning Project delivery stakeholders have met to identify and define their roles, responsibilities and contributions for each of the key phases of project delivery 1 1 Complete McLH / Design Team Evidence should demonstrate activities have taken place prior to RIBA stage 2 completion Evidence provided in support of this credit: ⢠Design responsibility matrix confirms roles, responsibilities and contributions. ⢠Project Execution Plan ⢠Communication Strategy (covered in digital collaboration plan) ⢠Initial Project Brief (early sustainability options appraisal has been provided) Also provided: ⢠DAA - Completed Man 01 stakeholder consultation matrix - this will summarise contribution stakeholders made in influencing the design and delivery of project throughout the concept (and technical) design stages. Stakeholder consultation (interested party) Prior to completion of the Concept Design stage, all relevant third party stakeholders have been consulted by the design team Demonstrate how the stakeholder contributions and consultation exercise outcomes influence the Initial Project Brief and Concept Design Prior to completion of the detailed design (RIBA Stage 4, Technical Design or equivalent), all interested parties give and receive consultation feedback 1 1 Complete McLH / DAA Evidence should demonstrate activities have commenced prior to RIBA stage 2 completion and continue to RIBA Stage 4 As above, Please complete the Man 01 stakeholder consultation matrix - this will demonstrate how the engagement exercise influenced the brief and design and how this was communicated to stakeholders. DAA have completed Man 01 matrix (with input from McLH as appropriate) BREEAM AP (Concept Design) A BREEAM AP has been appointed to facilitate the setting and achievement of BREEAM performance targets for the project (Stage 1) 1 1 Evidence provided in support of credit - accreditation number of the BREEAM AP and examples of concept design stage pre-assessment activity and support. BREEAM AP (Developed Design) A BREEAM AP has been appointed to monitor progress against the agreed BREEAM performance targets throughout the design process 1 1 As above Elemental life cycle cost (LCC) An outline, entire asset elemental life cycle cost (LCC) plan has been carried out at Process Stage 2 2 2 Elemental LCC report has been prepared. Component level LCC Plan A component level LCC option appraisal has been developed by the end of Process Stage 4 1 No longer targeted. Component level LCC report - team report that this has been completed?? McL&H please confirm appointment and share completed component level LCC reporting, complete with options appraisal and demonstrate how this has influenced building and systems design and specification to minimise life cycle costs. Capital cost reporting The capital cost for the building in pounds per square metre (Ā£k/m²) is reported Capital cost The capital cost for the building includes the expenses related to the initial construction of the building: ā Construction, including preparatory works, materials, equipment and labour ā Site management ā Construction financing ā Insurance and taxes during construction ā Inspection and testing Costs related to land procurement, clearance, design, statutory approvals and post occupancy aftercare are not included 1 1 Work in progress McLH QS (G&T) Client (commitment) Feb-23 Please predict capital cost. This should be confirmed in writing on headed paper and signed by appropriate individual. Environmental management All timber and timber-based products used during the construction process of the project must be legal and sustainable timber (e.g. FSC PEFC recycled). The principal contractor operates an environmental management system (e.g. ISO 14001) covering their main operations and implements best practice pollution prevention policies and procedures (e.g. PPG6 ). 1 1 Almost complete Demolition (Shorts) and Principal Contractor (McLH) Jan-23 Draft letter template under review with McL&H, this will help to confirm: All timber and timber-based products used during the construction process of the project are legal and sustainable timber and provide copies of PEFC / FSC certificates. McLH Please sign and return letter. McLH Please complete, sign and date a copy of the attached Man 03 Pollution Prevention checklist. McLH has provided a copy of their ISO 14001 cert. Shorts have provided: A copy of the ISO 14001 cert has been receievd. Early site activity: copies of FSC certs have been provided from McLH please also provide copiesof invoices from relevant suppliers.
Agreed target rating: BREEAM Excellent (score of >70% required PLUS mandatory credits / issues highlighted in red) Current projected design stage score (All 'Targeted' credits): 79.54% Latest revision:02/02/2024 BREEAM New Construction, 2018 - Shell and Core assessment EDC-ARM-xx-xx-SH-A0100 Management (0.61% per 1 credit) Man 01 McLH to apt QS (G&T) Sustainable Procurement Man 02 Life Cycle Cost and Service Planning BREEAM AP Complete Complete
Please
Training,
Monitoring
principal contractor. The principal contractor analyses these items.
Draft letter template under review with McL&H - please sign and send back
Early stage site activity: CLOCS and CCS accreditation being sought by McL&H certificate of compliance and 1st CCS repor issued, performance on track.
Draft letter template under review with
McL&H has registered the site with SMARTWaste - this is the confirmed method for monitoring and reporting energy and water consumption
PLEASE CONTINUE TO PROVIDE MONTHLY UPDATES AND AN UPDATED REPORT ON COMPLETION OF PROJECT
Draft
Transport impacts must be monitored. This information must be recorded in SMARTWaste (or similar) for credit to be targeted.
PLEASE ENSURE THIS IS MONITORED AND PROVIDE MONTHLY UPDATES AND AN UPDATED REPORT ON COMPLETION OF PROJECT
BREEAM AP (Site) BREEAM AP is appointed during construction stage to monitor the project to ensure ongoing compliance with the relevant sustainability performance/process criteria, and therefore BREEAM target(s), during the Construction, Handover and Close Out stages 1 1 Complete BREEAM AP (ARMILA) BREEAM AP appointed. On-going engagement. Performance targets to be agreed and worked towards. Responsible site management One credit mandatory for Excellent Site managed in accordance with the BREEAM responsible site management requirements as highlighted in BREEAM table 4.1. 2 2 Jan-23
letter template under review with McL&H . McL&H has registered site with CCS scheme and will commit to targeting a score of no less than 39.
recent site visit and CCS score of 43 noted. Exemplary level criteria All site management requirements, as outlined in BREEAM table 4.1, will be addressed. 1 1 Jan-23 AS above PLUS
Draft
Most
also provide evidence to confirm the following will be committed to: Tidiness
Ensure clear and safe access in and around the buildings at the point of handover.
g.
awareness and feedback
The fleet operators, undertakes driver training and awareness to promote safety within the development footprint and off site.
p.
and reporting
The fleet operators, captures and investigates any road accidents, incidents
near misses
reports them back to the
q.
and
and
Monitoring of construction site impacts - Utility consumption (energy and water) Monitor and record data on energy consumption (kWh) and water consumption (m3) as a result of the use of construction plant, equipment and site accommodation 1 1 Jan-23
McL&H
.
Monitoring
construction site impacts
Transport
construction materials
waste Monitor
record data
consumption (litres) and total carbon dioxide emissions (kgCO2 eq)) on transport movements and impacts resulting from delivery of the majority of construction materials to site and construction waste from site 1 1 Jan-23
of
-
of
and
and
(fuel
letter template under review with McL&H .
Commissioning testing schedule and responsibilities One credit mandatory for Excellent Prepare a schedule of commissioning and testing. Appropriate project team member(s) is appointed to monitor and programme pre-commissioning, commissioning, testing and, where necessary, re-commissioning activities in compliance with Building Regulations, BSRIA and CIBSE guidelines. Fully train the occupier or facilities team in the operation of the system. 1 1 Jan-23
letter template under review with McL&H . Please provide copies of commissioning schedule, confirming testing schedule and inspection of building fabric (in accordance with required standards, within suitable timescales
prior to handover).
training requirements.
individual
responsibility
monitor
programme pre-commissioning,
testing (and where necessary include re-commissioning
on behalf
client). Commissioning design and preparation During the design stage, the client or the principal contractor appoints an appropriate project team member, provided they are not involved in the general installation works for the building services systems: .a Undertaking design reviews and giving advice on suitability for ease of commissioning. .b Providing commissioning management input to construction programming and during installation stages. .c Management of commissioning, performance testing and handover or post-handover stages. 1 1 By end of RIBA 4 Draft letter template under review with McL&H . Please provide confirmation of the individual (who is not involved in the general installation works for the building services systems and who is a specialist commissioning manager) who at design stage can provide: a.design reviews and giving advice on suitability for ease of commissioning.
commissioning management input to construction programming and during installation stages.
Management of commissioning, performance testing and handover or post-handover stages. Testing and inspectingbuilding fabric The integrity of the building fabric, including continuity of insulation, avoidance of thermal bridging and air leakage paths is quality assured through completion of post construction testing (thermographic survey and air pressure test) 1 1 Almost complete McLH Jan-23 Draft letter template under review with McL&H. Please provide confirmation that the following will be allowed for: post-construction testing and inspection to quality-assure the integrity of the building fabric, including continuity of insulation, avoidance of thermal bridging and air leakage paths. Commitment to rectify any defects identified during post-construction testing and inspection prior to building handover and close out. Handover BUGs One credit mandatory for Excellent A Building User Guide (BUG) is developed prior to handover AND a training schedule is prepared for building occupiers/premises managers 1 1 Almost complete McLH Jan-23 Draft letter template under review with McL&H. McLH committed to preparing BUGs for FM and everyday user and a training schedule for building occupiers / managers. Copies of POs provided in support of evidence requirements. Commitment to deliver training within letter template - please sign and return letter. Almost complete Almost complete Man 03 Responsible Construction Practices McLH McLH Commissioning and Handover Man 04 McLH Health and Wellbeing (0.72% per 1 credit) Complete
Draft
and
Confirm
Confirm
with
to
and
commissioning and
activities
of the
b.
c.
View out 95% of the floor area in 95% of spaces for each relevant building areas is within 8m of a wall which has a window or permanent opening that provides an adequate view out AND window/opening must be ā„ 20% of the surrounding wall area Where the room depth is greater than 8m, the percentage of window or opening must instead be the same as, or greater than, the values in Table 1.0 BS8206 1 1 Complete DAA Complete Marked-up drawings and elevations have been provided by DAA for Building A and Building B. The room depth is greater than 8m, therefore the percentage of window / glazing has been calculated and confirmed to be greater than the values in Table 1.0 BS8206: Part 2 (i.e. likely required to be at least 35%) . Marked-up drawings recived for Building A and Building B demonstrate an adequate view out will be achieved from a seated position. It is confirmed that this is of a landscape or buildings (rather than just the sky) at seated eye level (1.2ā1.3m) within the relevant building areas and will be through an external window glazing. Internal and external lighting levels, zoning and control Internal: Internal lighting in all relevant areas of the building is designed to provide illuminance (lux) levels and colouring rendering index in accordance with the SLL Code for Lighting 2012 and any other relevant industry standard. Internal lighting should be appropriate to the tasks undertaken, accounting for building user concentration and comfort levels. For areas where computer screens are regularly used, the lighting design complies with CIBSE Lighting Guide 7 sections 2.4, 2.13 to 2.15, 2.20, and 6.10 to 6.20. This gives recommendations highlighting: a. Limits to the luminance of the luminaires to avoid screen reflections. (Manufacturersā data for the luminaires should be sought to confirm this.) b. Any area where a surface is used to reflect light in to a space, such as uplighting, the recommendations refer to the luminance of the lit ceiling rather than the luminaire; a design team calculation is usually required to demonstrate this. c. Recommendations for direct lighting, ceiling illuminance, and average wall illuminance. External: External lighting design in accordance with BS 5489-1:2013 Lighting of roads and public amenity areas3 and BS EN 12464-2:2014 Light and lighting Lighting of work places Part 2: Outdoor work places. External Lighting should provide illuminance levels that enable users to perform outdoor visual tasks efficiently and accurately, especially during the night. Zoning: Internal lighting is zoned to allow for occupant control (In office areas, zones of no more than four workplaces Workstations adjacent to windows or atria and other building areas separately zoned and controlled Seminar and lecture rooms: zoned for presentation and audience areas demonstration area Auditoria: zoning of seating areas, circulation space and lectern area) AND lighting designed in accordance with CIBSE Lighting Guide 5 1 1 More information required External lighting designer May 2023 External lighting designer to confirm: External lighting design in accordance with BS 5489-1:2013 Lighting of roads and public amenity areas3 and BS EN 12464-2:2014 Light and lighting - Lighting of work places - Part 2: Outdoor work places. External Lighting should provide illuminance levels that enable users to perform outdoor visual tasks efficiently and accurately, especially during the night. External lighting plan and calculations to be provided.
provided from Halsion confirms: 'All internal lighting to be LED and designed to LG7. External lighting to be designed to BS12464-2. Zonal philosophy to be produced. LG5 not applicable.' Internal lighting calculations provided for Building A and Building B. written confirmation (email / letter) that these meet the BREEAM requirements as noted opposite. Indoor air quality (IAQ) plan An indoor air quality plan has been produced, must consider the following: .a Removal of contaminant sources b Dilution and control of contaminant sources: .i Where present, consideration is given to the air quality requirements of specialist areas such as laboratories c Procedures for pre-occupancy flush out d Third party testing and analysis e Maintaining good indoor air quality in-use. pre-requisite More information required McL&H May 2023 IAQ planprovided by Halsion. MCL&H Please prepare compliant IAQ plan as per guidance issued. Ventilation Provide fresh air into the building in accordance with the criteria of the relevant standard for ventilation; Ventilation pathways are designed to minimise the ingress and build-up of air pollutants inside the building (The building has been designed to minimise the concentration and recirculation of pollutants in the building (intakes and exhausts 10m apart and in accordance with relevant standards); Where present, HVAC systems must incorporate suitable filtration to minimise external air pollution, as defined in BS EN 16798-3:2017. The specified filters should achieve supply air classification of at least SUP 2; Areas of the building subject to large and unpredictable or variable occupancy patterns have carbon dioxide (CO ā or air quality sensors specified and: i. In mechanically ventilated buildings or spaces: sensors are linked to the mechanical ventilation system and provide demand-controlled ventilation to the space ii. In naturally ventilated buildings or spaces: sensors either have the ability to alert the building owner or manager when CO ā levels exceed the recommended set point, or are linked to controls with the ability to adjust the quantity of fresh air, i.e. automatic opening windows or O36 For naturally ventilated or mixed mode buildings, the design demonstrates that the ventilation strategy provides adequate cross flow of air to maintain the required thermal comfort conditions and ventilation rates in accordance with CIBSE AM10 1 1 Complete Halsion May 2023 Halsion confirm design will be developed to be BREEAM compliant and any required sensor locations will be included on final layouts.
of the ventilation layout plan drawings have been provided. Mark-up drawings confirming CO2 sensor locations have been provided. Relevant specifications to be provide and confirmation that these comply with requirements (as per letter template provided). - email 2/2/2024 Please ensure spec is updated to read: ' The specified filters should achieve supply air classification of at least SUP 2'. Page 7 provides a 'sample' Thermal modelling Thermal modelling has been carried out using software in accordance with CIBSE AM11 demonstrating required thermal comfort levels have been achieved The modelling demonstrates that: For air-conditioned buildings, summer and winter operative temperature ranges in occupied spaces are in accordance with the criteria set out in CIBSE Guide A Environmental design(80), Table 1.5; or other appropriate industry standard (where this sets a higher or more appropriate requirement or level for the building type); or the thermal environment in occupied spaces meet the Category B requirements for PPD, PMV and local discomfort set out in Table A.1 of Annex A of ISO 7730:2005. For air-conditioned buildings, the PMV (predicted mean vote) and PPD (predicted percentage of dissatisfied) indices based on the above modelling are reported via the BREEAM assessment scoring and reporting tool. 1 1 Complete Halsion May 2023 Copies of thermal comfort modelling report received and compliance demondtrated. Suitably Qualified Acoustician Holds a degree, PhD or equivalent qualification in acoustics/sound testing Has a minimum of three years relevant experience Holds a recognised acoustic qualification and membership of an appropriate professional body (e.g. Institute of Acoustics) - Complete Acoustician Confirmation of SQA qualification. Hea 04 Thermal comfort Visual comfort Hea 01 Hea 02 Indoor Air Quality
Feedback
Copies
A copy of the architectural acoustic and BS reports confirm that the requirements are being targeted.
SQA has provided confirmation proposed design is expected to achieve indoor ambient noise levels that comply with the design ranges given in Section 7 of BS 8233:2014.
McLH - confirmation has been provided SQA is appointed to provide this post-completion review. McLH to provide written confirmation as per letter template.
Marked-up
McL&H
Proposed plan to be discussed:
Dedicated and safe cycle paths are provided from the site entrance to any cycle storage, and connect to offsite cycle paths where applicable.
Adequate external lighting in accordance with BS 5489-1:2013 Lighting of roads and public amenity areas.
2. Appropriate sized, designed and constructed. The following publications offer guidance on how to demonstrate this:
a. Local transport Note 2/08 Cycle infrastructure design, Department of Transport, 2008. b. Sustrans design guidance (www.sustrans.org.uk), specifically the Sustrans design manual handbookfor cyclefriendly design
Dedicated and safe footpaths are provided on and around the site providing suitable links for the following:
a The site entrance to the building entrance
b Car parks (where present) to the building entrance
c The building to outdoor space
d Connecting to off-site paths where applicable.
Pedestrian drop-off areas are designed off, or adjoining to, the access road and should provide direct access to other footpaths.
Where vehicle delivery access and drop-off areas form part of the assessed development, the following apply: Delivery areas are not accessed through general parking areas and do not cross or share the following: a pedestrian and cyclist paths b outside amenity areas accessible to building users and general public.
There is a dedicated parking or waiting area for goods vehicles with appropriate separation from the manoeuvring area and staff and visitor car parking.
Parking and turning areas are designed for simple manoeuvring according to the type of delivery vehicle likely to access the site, avoiding the need for repeated shunting.
Indoor ambient noise level
the indoor ambient noise level standards set out within performance criteria given in Section 7 of BS 8233:2014. A programme of pre-completion acoustic testing is carried out by a compliant test body in accordance with the acoustic testing and measurement procedures outlined in BREEAM Methodology. 1 1 Complete DAA / Acoustician / McLH
Achieve
Hea 06 Security Security of site and building A Suitably Qualified Security Specialist (SQSS) conducts an evidence-based Security needs assessment (SNA) during or prior to Concept Design. The purpose of the SNA will be to identify attributes of the proposal, site and surroundings which may influence the approach to security for the development. The SQSS develops a set of security controls and recommendations for incorporation into the proposals. Those controls and recommendations shall directly relate to the threats and assets identified in the preceding SNA. The controls and recommendations shall be incorporated into proposals and implemented in the as-built development. Any deviation from those controls and recommendations shall be justified and agreed with the SQSS 1 1 Almost complete McL&H May 2023
SQSS
addressed.
drawings have been provided which demonstrate how the
feedback recommendations have been
SQSS
Safe access Safe access for pedestrians and cyclists is provided (to, from and within site), and deliveries areas are not directly accessed through general parking areas and do not cross or share pedestrian and cyclist routes 1 1 Complete Gillespies & DAA Drawings submitted confirming safe access routes to / from / within site.
- Please provide confirmation that recommendations have been taken on-board and reflected in designs, as per
report.
Outside space There is an outside space providing building users with an external amenity area 1 1 Comeplete DAA Plan drawings demonstrate outside space will be provided for users to enjoy. Energy performance Four credits mandatory for Excellent Up to 9 credits based on energy performance rating and carbon emissions 9 6 Complete Halsion Updated BRUKLs report has been provided and .inp file.
updated BRUKL suggesting that 6 credits should be targeted (this is an increase of 2 credit from previous predictions). Safe and healthy surroundings Reduction of energy use and carbon emissions Ene 01 Hea 07 Energy (0.66% per 1 credit) Acoustic Performance Hea 05
Halsion confirmed
Specifications
Watt AND All external light fittings are automatically controlled for prevention of operation during daylight hours and presence detection in areas of intermittent pedestrian traffic.
The above requirements include decorative & floodlighting.'
Emergency light fittings, including security lighting, that are also used for normal operation are assessed for this issue - please confirm if this will be the case.
External lighting drawings still to be provided confirming compliance with requirements.
Please obtain appropriate confrimation and spec and drawings from external lighting designer.
LZCT feasibility study has been
Specified local LZC technologies for the building have been shown in line with the feasibility study recommendation.
The reduced regulated carbon dioxide (CO ā -eq) emissions have been reported.
Copies of Part L received. energy specialist - Patel Jayesh, CIBSE reg.
Sub-metering of major energy consuming systems One credit mandatory for Excellent Energy metering systems are installed that enable at least 90% of the estimated annual energy consumption of each fuel to be assigned to the various end-use categories of energy consuming systems Building users can identify the energy consuming end uses, for example through labelling or data outputs. All pulsed output meters to be connected to Building Energy Management System 1 1 Complete Halsion May 2023 Halsion confirm credit is being targeted. Schematics have been provided. On Page 4 of the Specifications please confirm sub-metering will meet BRREAM requirements: 'Install energy metering systems so that at least 90% of the estimated annual energy consumption of each fuel is assigned to the end-use categories' End-use categories include: 1. Space heating 2. Domestic hot water heating 3. Humidification* 4. Cooling* 5. Ventilation, i.e. fans (major)* 6. Pumps 7. Lighting 8. Small power 9. Renewable or low carbon systems (separately) 10. Controls 11. Other major energy consuming systems or plant, where appropriate. Depending on the building type, this might include for example: plant used for swimming or hydrotherapy pools; other sports and leisure facilities; kitchen plant or catering equipment; office equipment; cold storage plant; laboratory plant; sterile services equipment; transportation systems (e.g. lifts and escalators); drama studios and theatres with large lighting rigs; telecommunications; dedicated computer room or suite; server rooms; dealing rooms; covered car parks; ovens or furnaces; and floodlighting. Sub-metering of high energy load and tenancy areas Sub-meters provided per floor plate and for relevant function areas (e.g. where catering is provided) 1 1 Complete Halsion May 2023
confirm credit is being targeted.
have been provided. On Page 4 of the Specifications please confirm sub-metering will meet BRREAM requirements: 'Monitor a significant majority of the energy supply with an accessible energy monitoring and management system for relevant function areas or departments; Sub-meter per floor plate.' Ene 03 External lighting External lighting The average initial luminous efficacy of the external light fittings within the construction zone is not less than 70 luminaire lumens per circuit Watt AND All external light fittings are automatically controlled for prevention of operation during daylight hours and presence detection in areas of intermittent pedestrian traffic. The above requirements include decorative & floodlighting. Emergency light fittings, including security lighting, that are also used for normal operation are assessed for this issue. 1 1 More information required External lighting designer May 2023
Halsion
Schematics
credit is being targeted.
Halsion confirm
average
luminous efficacy
external light fittings
zone
less than 70
lumens
circuit
page 257 clause E3-8 more details, please confirm: 'The
initial
of the
within the construction
is not
luminaire
per
Passive design analysis Hea 04 Thermal comfort credit must be achieved. Project team carries out an analysis of the proposed building design to influence decisions made during Concept Design stage (RIBA Stage 2 ) and identifies opportunities for the implementation of passive design solutions that reduce demands for energy consuming building services 1 1 Complete AECOM A copy of the report confirming Passive design analysis findings and quantified energy reductions has been received Low zero carbon (LZC) feasibility study A feasibility study has been carried out by the completion of the Concept Design stage (RIBA Stage 2 ) by an energy specialist to establish the most appropriate low or zero carbon energy source(s) for the building Quantify the reduced regulated carbon dioxide (CO -eq) emissions resulting from the feasibility study 1 1 Complete Halsion May 2023
shared.
Energy monitoring Ene 02 Low carbon design Ene 04
Energy consumption Analyse the transportation demand and usage patterns for the building to determine the optimum number and size of lifts Energy consumption must be calculated in accordance with BS EN ISO 25745 Part 2 for one of the following: At least two options for each transportation type (e.g. for lifts, hydraulic, traction or machine roomless (MRL)) OR ii At least two options considering different system arrangements and control strategies. Consider the use of regenerative drives only where a saving can be demonstrated Specify the transportation system with the lowest energy consumption 1 1 Complete DAA Jan-23 A copy of the Transport demand analysis has been received. Specification currently being considered in consultation with manufacture. Of the energy efficient lift options available, the most efficiecnt has been selected (OTIS Gen2 lifts). Please populate the ENE06_Lift Data sheet with the energy consumption figures for the two types of lift options that were considered - this will confirm that the lowest energy consuming lift has been selected (manufacture may provide the calculations please request these). Energy efficient features For each lift, the following three energy efficient features are specified: a. The lifts operate in a standby condition during off-peak periods b. The lift car lighting and display lighting provides an average luminous efficacy across all fittings in the car of > 70 luminaire lumens per circuit Watt c. The lift uses a drive controller capable of variable speed, variable-voltage, and variable-frequency (VVVF) control of the drive motor. Where the use of regenerative drives is demonstrated to save energy, they are specified 1 1 Complete DAA Jan-23 Manufacturers confirmation received - the specified lift benefits from the three energy efficient features recognised by BREEAM. Lift manufacturers literature has been shared and confirms the following energy efficient features would be possible with OTIS Gen2 Stream: The lifts can operate in a standby condition during off-peak periods. Variable speed, voltage and frequency options. LED lightning in car and for hall fixture - confirmation received from manufacturer that the lift car lighting and display lighting provides an average luminous efficacy across all fittings in the car of > 70 luminaire lumens per circuit Watt. Regenerative drive option is available and has been specified - please provide calculations demonstrating the savings with and without regenerative drive option. Currently with OTIS. Tra 01 Transport assessment and travel plan Transport assessment and travel plan No later than Concept Design stage, undertake a site-specific transport assessment (or develop a travel statement) and draft travel plan, which can demonstrably be used to influence the site layout and built form 2 2 Complete Milestone Transport assessment and travel plan has been prepared. Tra 02 Sustainable transport options Transport options implementation Identify the sustainable transport measures, see BREEAM Table 7.4 Credits awarded according to the existing Accessible Index (AI) of the project, and the total number of points achieved for the options implemented 10 9 Complete DAA / McL&H May 2023 Relevant confirmation, confirming sustainable transport options that will be provided for: Accessibility index calculated previously as 8 (as per Tra 01 - complete) EV charging (10% car charging spaces min 3kW) Cyclist spaces (Building A = 1 covered space per 20 predicted staff = 94 spaces AND Building B = 46 spaces) Cycle facilities (showers Building A = 10 & Building B = 5; changing rooms; lockers Building A = 95 & Building B = 48; drying space) Local amenities (at least 3 within 500m) On site amenities (provision of outdoor open space) Halsion has confirmed- Pubic transport Information system in a publicly accessible area - Halsion please identify a suitable location for power outlet that would allow for the public transport informaiton system to be installed and send a marked-up drawing. Confirmation received for cycle storage, demonstrating that compliance with requirements can be met: Cycles can be secured within spaces in racks with overhead covering. The cycle racks are set in or fixed to a permanent structure (building or hardstanding) or alternatively, may be located in a locked structure fixed to, or part of, a permanent structure with appropriate surveillance The distance between each cycle rack, and the cycle racks and other obstructions, e.g. a wall, allows appropriate access to the cycle storage space for easy storage and access to bikes The storage facility or entrance to the facility is in a prominent site location visible to potential users from either an occupied building or a main access to a building Halsion - evidence received confirms the cycle storage facility has adequate lighting. The lighting must be controlled to avoid out-of-hours use - PIR spec issued. Wat 01 Water consumption Water consumption One credit mandatory for Excellent An assessment of the efficiency of the buildingās domestic water-consuming components is undertaken using the BREEAM Wat 01 calculator: a. WCs b. Urinals c. Taps (wash hand basins and where specified kitchen taps) d. Showers e. Baths f. Dishwashers (domestic and commercial sized) g. Washing machines (domestic and commercial/industrial) 5 3 Complete DAA 20-Jan-23 Wat 01 calc confirms improvement. Manufacturers information has been indicated (e.g. confirming sanitary / taps / domestic goods water consumption spec) - water consumption determined for each item. Transport (0.95% per 1 credit) Water (0.77% per 1 credit) Energy efficient transportation system (lifts) Ene 06
3
2
1
Schenatics
Water
1.a
supply and the buildings under assessment.
2 The leak detection system is:
2.a A permanent automated water leak detection system that alerts the building occupants to the leak OR an inbuilt automated diagnostic procedure for detecting leaks
2.b Activated when the flow of water passing through the water meter or data logger is at
2.c
high or low level, over set time periods. Although high and low level leakage rates are not specified, the leak detection equipment installed must have the flexibility to distinguish between different flow rates to enable it to be programmed to suit the building type and owner's or occupier's usage patterns.
2.d Programmable to suit the owner's or occupier's water consumption criteria
2.e Where applicable, designed to avoid false alarms caused by normal operation of large water consuming plant such as chillers.
Where there is physically no space for a leak detection system between the utilities water meter and the building, alternative solutions can be used, provided that a major leak can still be detected.
Schematics have been provided confirming presence.
Leak detection - Page 334 clause M1-7 - Please provide additional specifications details: 1.a On the utilities water supply within the buildings, to detect any major leaks within the buildings AND
1.b Between the buildings and the utilities water supply, to detect any major leaks between the utilities
2 The leak detection system is:
2.a A permanent automated water leak detection system that alerts the building occupants to the leak OR an inbuilt automated diagnostic procedure for detecting leaks - PLEASE CONFIRM
2.b Activated when the flow of water passing through the water meter or data logger is at a flow rate above a pre āset maximum for a pre āset period of time. It does not necessarily require a system that directly detects water leakage along part or the whole length of the water supply system
2.c Able to identify different flow and therefore leakage rates, e.g. continuous, high or low level, over set time periods. Although high and low level leakage rates are not specified, the leak detection equipment installed must have the flexibility to distinguish between different flow rates to enable it to be programmed to suit the building type and owner's or occupier's usage patterns.
2.d Programmable to suit the owner's or occupier's water consumption criteria
2.e Where applicable, designed to avoid false alarms caused by normal operation of large water consuming plant such as chillers.
Wat 02 Water monitoring Water monitoring Mandatory for Excellent - Specification of a water meter on the mains water supply Water-consuming plant or building areas, consuming 10% or more of the buildingās total water demand are sub metered - Each meter has a pulsed output or is linked to a BMS 1 1 Complete Halsion May 2023
been provided confirming presence.
have
meters Spec claue
348
provide specifications confirming compliance with requirements:
M1-31-1 page
- Please
Specify a water meter on the mains water supply to each building. This includes instances where water is supplied via a borehole or other private source.
For water-consuming plant or building areas consuming 10%
more of the buildingās total water demand:
Fit easily accessible sub-meters OR 2.b Install water monitoring equipment integral to the plant or area.
or
2.a
For each meter (main and sub):
Install a pulsed or other open protocol communication output AND 3.b Connect it to an appropriate utility monitoring and management system, e.g. a building management system (BMS), for the monitoring of water consumption. If there is no BMS system in operation at PostConstruction stage, award credits provided that the system used enables connection when the BMS becomes operational. Leak detection system A leak detection system which is capable of detecting a major water leak on the mains water supply within the building and between the building and the utilities water meter is installed
3.a
On the utilities water supply within the buildings, to detect any major leaks within the buildings AND 1.b Between the buildings and the utilities water supply, to detect any major leaks between the utilities
a flow rate above a pre āset maximum for a pre āset period of time. It does not necessarily require a system that directly detects water leakage along part or the whole length of the water supply system
identify different flow and therefore leakage rates,
continuous,
Able to
e.g.
1
May 2023
1
Flow control devices Flow control devices that regulate the supply of water to each WC area/facility according to demand are installed 1 1 May 2023 Plan drawings showing flow restriction valves have been issued. written confirmation provided Wat 04 Water efficient equipment Water efficient equipment Unregulated water demand: Identify all water demands from uses other - Where there is no water demand from uses other than domestic-scale, sanitary use components in the building, this issue is not applicable. Identify systems or processes to reduce the relevant water demand (relevant to the above), and establish, through either good practice design or specification, a demonstrable reduction in the total water demand of the building. This issue includes, but is not limited to the following: ā Swimming pools ā Recreational hot tubs and hydrotherapy pools ā Equipment used for irrigation ā Vehicle wash equipment ā Project-specific industrial processes ā Water filtration and treatment processes ā Building services (e.g. cooling towers and humidification systems) 1 1 Complete Halsion McLarc Mar-23 Plan drawings received. Please provide information on the energy efficient irrigation systemsIdentify systems or processes to reduce the relevant water demand, and establish, through either good practice design or specification, a demonstrable reduction in the total water demand of the building Life cycle impacts Carry out a building LCA on of the superstructure design, substructure and hard landscaping 7 4 RIBA 4 Stage 3 LCA received . Exemplary level criteria Core Building Services LCA During Concept Design identify opportunities for reducing environmental impacts 1 1 Complete Concept Stage LCA received. Pre-requisite Mandatory All timber and timber-based products used on the project is Legally harvested and traded timber - Y Complete McLH Jan-23 Draft letter with McL&H for review Please provide written confirmation statement as per letter template. Sample FSC certification has been provided. Sustainable procurement plan The principal contractor sources materials for the project in accordance with a documented sustainable procurement plan 1 1 Complete AECOM & McLH Complete Copy of sustainable procurement plan previously provided Complete Comeplete Materials (1.25% per 1 credit) Halsion Life cycle impacts Mat 01 McLH Water leak detection Wat 03
Template
Certs being
Calculation is underway.
DAA has
review and assessment additional narrative has been provided in addition to the drawings issued.
Confirmation design provides adequate protection for exposed parts of the building from material degradation.
Drawings and strategy confirm and demonstrate i) there is convenient access to the roof and faƧade for costeffective cleaning, replacement and repair in the building's design and ii) the roof and faƧade has been designed to prevent water damage, ingress and detrimental ponding
Progess is on-going. - report has been updated to include Technical Design Stage. consider methods that have been adopted that aim to optimise the use of materials to cover all of the following stages:
a. Preparation and Brief (e.g. re-use, adaption and expansion of existing building / services, need for flexibility and adaptability etc.)
b.
Responsible sourcing of materials Responsible sourcing is demonstrated for major building elements, through ISO 14001, FSC and BES 6001 certificates for the following: - Ceiling (including ceiling finishes) Door/window Floor (including floor finishes) - Insulation Internal partition/internal walls (including finishes) Roof (including roof finishes) - Structural frame, foundation and substructure - External wall - Building service - Hard landscaping Stairs and ramps 3 1 Almost complete McLH May 2023
responsible sourcing of construction materials has been provided for materials listed.
Confirmation of
for gathering information has been issued and
being populated.
is
sought
quants
calculated by McLH.
and
being
Protecting vulnerable parts of the building from damage The building incorporates suitable durability and protection measures or design features/solutions to prevent damage to vulnerable parts of the internal and external building and landscaping elements These measures must provide protection against: 1.a Negative impacts of high user numbers in relevant areas of the building (e.g. corridors, lifts, stairs, doors etc.). 1.b Damage from any vehicle or trolley movements within 1m of the internal building fabric in storage, delivery, corridor and kitchen areas. 1.c External building fabric damage by a vehicle. Protection where parking or manoeuvring areas are within 1 metre of the building faƧade and where delivery areas or routes are within 2 metres of the faƧade, i.e. specifying bollards or protection rails. 1.d Potential malicious damage to building materials and finishes, in public and common areas where appropriate. Marked-up drawings confirm how the design provides protection to vulnerable parts of the building from damageadditional narrative has been added to the drawings provided. Protecting exposed parts of the building from material degradation Relevant building elements incorporate appropriate design and specification measures to limit material degradation due to environmental factors, such as: Environmental agents, including: a. Solar radiation b. Temperature variation c. Water/moisture d. Wind e. Precipitation, e.g. rain and snow f. Extreme weather conditions: high wind speeds, flooding, driving rain, snow Biological agents, including: a. Vegetation b. Pests, insects Pollutants, including: a. Air contaminants b. Ground contaminants
summarised
Mat 06 Material efficiency Material efficiency Opportunities have been identified, and appropriate measures investigated and implemented, to optimise the use of materials in building design, procurement, construction, maintenance and end of life - a summary report should be provided to cover: a. Preparation and Brief b. Concept Design c. Developed Design d. Technical Design e. Construction. 1 1 Complete DAA with McLH and wider team input
Concept Design
structural, architectural, building services)
Developed Design
designing to standard sizes
reduce waste, optimise resource use etc.) d. Technical Design
material efficiency measures) e. Construction (e.g. waste reduction strategies, resource efficiency etc.) Construction resource efficiency Prepare a construction resource management plan complete with targets. Amount of waste generated per 100m² (gross internal floor area): 1 credit: ⤠13.3 m3 or ⤠11.1 tonnes 2 credits: ⤠7.5 m3 or ⤠6.5 tonnes 3 credits: ⤠3.4 m3 or ⤠3.2 tonnes 3 1 May 2023 Draft letter with McL&H for review please confirm resource targets Resource management plan in place (SMARTWaste template used). Please include demolition waste info. SMARTWaste being used by McL&H to monitor. Pre-demo audit Complete a pre-demolition audit of any existing buildings, structures or hard surfaces being considered for, no later than RIBA Stage 2. Maximise the opportunity for reuse and recovery of materials for high-grade/ value application. 1 1 May 2023 A copy of the pre-demo audit has been provided. Diversion of resources from landfill Diversion from landfill targets: Non-demolition waste: 70% by volume or 80% by tonnage Demolition (if appropriate): 80% by volume or 90% by tonnage 1 1 Complete Almost complete May 2023 McLH DAA and wider team update Construction waste management Responsible sourcing of materials Mat 03 Designing for durability and resilience Mat 05 1 1 Waste (0.63% per 1 credit) Draft letter with McL&H for review Please confirm processes and aspirations of project to meet required targets. Wst 01
(e.g.
c.
(e.g.
to
(e.g.
Please
This
of overheating
- Ene 01 approach, Maximise energy efficiency to tackle energy demand
- Ene 04 approach, passive design - Maximise opportunities to avoid unnecessary carbon emissions
- Mat 05 approach - durability and resilience - Avoid increased risks of deterioration and higher maintenance demands
- Pol 03 - Minimise the risks of increased flood risk and surface water run-off affecting the site or others Conduct
Wst 03 Operational waste Operational waste One credit mandatory for Excellent Dedicated space is provided for the segregation and storage of operational recyclable waste volumes: a. Clearly labelled b. Accessible to building occupants or facilities operators c. Of a capacity appropriate to the building type The design team demonstrates that the provision of waste management facilities for the assessed building is adequate given the building type, occupier (if known), operational function and likely waste streams and volumes to be generated. Where it is not possible to determine what provision should be made, use the following guide for minimum storage space provision: 1. At least 2m² per 1000m² of net floor area for buildings < 5000m² 2. A minimum of 10m² for buildings ā„ 5000m² 3. An additional 2m² per 1000m² of net floor area where catering is provided (with an additional minimum of 10m² for buildings ā„ 5000m²). The net floor area should be rounded up to the nearest 1000m². 1 1 Complete DAA Jan-23 Adequate space will be provided to accommodate operational waste streams (as per requirements) Marked-up drawings have been provided showing dedicated space as per requirements - please confirm the space will be clearly labelled, to assist with segregation, storage and collection of the recyclable waste streams Wst 04 Speculative finishes Flooring and Ceiling Finishes Office building types only For tenanted areas, where the future occupant is not known and carpets or other floor or ceiling finishes are installed, these must be limited to a show area only. OR Only install floor and ceiling finishes selected by the known occupant of a development. Alternatively, where only ceiling finishes and no carpets are installed, the building owner confirms that the first tenants will not be permitted to make substantial alterations to the ceiling finishes. 1 1 Complete DAA / Client Jan-23 DAA has confirmed - Raised Floor access and Ceilings to be provided as part of CAT design. Office floor finishes and ceilings to townhall and Gym subject to tenantsā fitout. DAA Please confirm in writing as per letter template. Structural and fabric resilience Conduct a climate change adaptation strategy appraisal for structural and fabric resilience by the end of Concept Design (RIBA Stage 2 or equivalent) through a risk assessment to identify and evaluate the impact on the building over its projected life cycle from expected extreme weather conditions arising from climate change and, where feasible, mitigate against these impacts. The assessment should cover the following stages: i. Hazard identification ii. Hazard assessment iii. Risk estimation iv. Risk evaluation v. Risk management. 1 1 Complete DAA Civil and structural engineer wider team input complete
adaptation strategy demonstrates how the climate change adaptation strategy appraisal has influenced the technical design.
Updated
consider risk
mitigation: i. Hazard identification ii. Hazard assessment iii. Risk estimation iv. Risk evaluation v. Risk management.
and
could include:
- Hea04 approach, preventing increasing risk
functional
potential
different design scenarios by Concept
Stage 2) Develop
study,
aim to enable and facilitate disassembly and functional adaptation 1 1 Complete DAA / McLH complete Stage 2 study received - confirms how the ease of disassembly and the functional adaptation of different scenarios was considered and responded Provide an update, during Technical Design, on: a How the recommendations or solutions proposed by Concept Design have been implemented where practical and cost effective. Omissions have been justified in writing to the assessor. b Changes to the recommendations and solutions during the development of the Technical Design Produce a building adaptability and disassembly guide to communicate the characteristics allowing functional adaptability and disassembly to prospective tenants 1 1 Complete DAA / McLH complete Updated report covers technical design stage - final contributions being added. This confirms how proposals were evaluated and progressed during technical development stage, justifying any omissions. A building adaptability and disassembly guide has been developed to communicate the characteristics allowing functional adaptability and disassembly to client. Previously occupied land At least 75% of the proposed developmentās footprint is on an area of land which has previously been occupied 1 1 Complete DAA Complete Confirmation provided - planning documentation and google map Contaminated land A contaminated land professional's site investigation, risk assessment and appraisal has deemed land within the site to be affected by contamination 1 0 Under review McL&H May-23 SI reports shared confirms conamination and remediation options. Assuming no remediation required McL&H to confirm and draft letter template to be signed? Removed from scoring. Suitably qualified ecologist Holds a degree or equivalent qualification in ecology or a related subject. - Is a practising ecologist, with a minimum of three years relevant experience Is covered by a professional code of conduct and subject to peer review - Y Complete Ecologist Feb-23 Original Ecology report has been shared. Details of the SQE appointment have been shared. LUE 01 Site selection Land Use and Ecology (1.15% per 1 credit) Wst 06 Design for disassembly and functional adaptability Design for disassembly and functional adaptability Adaptation to climate change Wst 05
a study to explore the ease of disassembly and the
adaptation
of
Design (RIBA
recommendations or solutions based on the
during or prior to Concept Design, that
Ecological value of site
Site survey:
A Suitably Qualified Ecologist (SQE) carries out a survey and evaluation for the site early enough to influence site preparation works, layout and, where necessary, strategic planning decisions (typically Preparation and brief stage) .
The SQEās survey and evaluation determines the siteās ecological baseline, including:
a Current and potential ecological value and condition of the site and related areas within the Zone of Influence.
b Direct and indirect risks to current ecological value from the project.
c Capacity and feasibility for enhancement of the site's ecological value and, where relevant, areas within the Zone of Influence.
Recommendations and data collected from the survey and evaluation are shared with appropriate project team members to influence decisions made for activities during site preparation, design and construction works, which can support ecological features.
Determining ecological outcomes:
The project team liaise and collaborate with representative stakeholders early enough to influence key planning decisions (typically Concept Design stage), to:
a Identify the optimal ecological outcomes for the site.
b Identify, appraise and select measures to meet the optimal ecological outcomes for the site, in line with the mitigation hierarchy of action, according to the route being used:
1. Avoidance
2. Protection
3. Reduction or limitation of negative impacts
4. On site compensation and 5. Enhancement, considering the capacity and feasibility within the site, or where viable, offsite. 2
LE 02's 'Survey and evaluation and Determining ecological outcomesā criteria have been achieved.
1 credit: Further planning to avoid and manage negative ecological impacts on-site is carried out early enough to influence the concept design and design brief as well as site preparation planning (typically Concept Design stage). On-site measures for managing negative ecological impacts during site preparation and construction are implemented inpractice.
The above is based on input from the project team in collaboration with representative stakeholders and data collated as part of the āDetermining ecological outcomesā in LE 02 Ecological risks and opportunities
1 or 2 credits: Achieve 1st credit.
Negative impacts from site preparation and construction works are managed according to the mitigation hierarchy: No overall loss of ecological value has occurred (two credits).
OR The loss of ecological value has been minimised (Minimising Loss) (one credit)
where this is not feasible, b Off site within the Zone of Influence.
Data collated are analysed and where potentially valuable, provided to the local environmental records centres nearest to, or relevant for, the site 1 1 Feb-23
A copy of the ecology report has been provided and confirms site is of low ecological value.
Written confirmation required from Landscpae architect: - that the ecologist report was received at an early enough stage to help inform the landscaping and ecological enhancement strategy
- that the project team liaised and collaborated with representative stakeholders early enough to influence key planning decisions (typically Concept Design stage), to:
a Identify the optimal ecological outcomes for the site.
b Identify, appraise and select measures to meet the optimal ecological outcomes for the site, in line with the mitigation hierarchy of action:
1. Avoidance
2. Protection
3. Reduction or limitation of negative impacts
4. On site compensation and 5. Enhancement, considering the capacity and feasibility within the site, or where viable, offsite.
Ecologist has visited site and confirms compliance is being met.
McL&H to sign and return letter template, confirming below
One credit ā Planning and measures on-site
Further planning is required to be carried out for activities during site clearance and construction. McLH to confirm mitigation strategy - requirement for On-site measures for managing negative ecological impacts during site preparation and construction are implemented in-practice (e.g. mitigation measures to protect existing ecological features), as per ecologist recommendations.
Two credits Managing negative impacts the following hierarchy must be followed when managing negative impacts of the site preparation and construction works:
ā Avoidance of negative impacts on habitats and features of ecological value on the site.
ā If it is not possible to avoid negative impacts completely; protect habitats and features of ecological value from damage during development works in accordance with best practice guidelines to minimise negative impacts.
- If it is not possible to achieve the above, fully reduce, limit or control negative impacts as far as possible
- Where it is not possible for avoidance, protection, limitation or control of the negative impacts on features of ecological value on site; compensation has taken place to ensure the existing ecological value is maintained during and after the project.
This builds on the measures agreed for delivering optimal ecological outcomes in LE 02 Ecological risks and opportunities.
Commit to ensuring measures are implemented that enhance ecological value, which are based on input from the project team and SQE in collaboration with representative stakeholders and data collated as part of the āDetermining ecological outcomesā in LE 02.
This issue intends to recognise enhancement measures that have been carried out in line with good practice recommended by an SQE, which build on mitigation measures taken in LE 03. enhancement measures must meaningfully enhance the site's ecological value - it would be benefical to discuss and agree this with input from the SQE.
McLH - please complete letter template - written confirmation compliance will be monitored against all relevant UK, EU or international legislation relating to the ecology of the site, as per SQE recommendation and that measures will be implemented as per SQE recommendations.
Landscape architect - please confirm final design. ecologist has deemed current proposals appropriate.
Three credits are to be targeted and will be awarded based on the change in ecological value occurring as a result of the project. This must be calculated in accordance with the process set out in GN36 - BREEAM, CEEQUAL and HQM Ecology Calculation Methodology ā Route 2. Credits are awarded in line with the Reward Scale table in GN36 where there are no residual impacts on protected sites or irreplaceable habitats.
Biodiversity metric confirms significant net gain.
2 May 2023
LUE 03 Managing impacts on ecology Managing impacts on ecology
3 Complete Ecologist DAA / McLH Feb-23
3
Pre-requisite Confirmation that the following LUE 03 issues has been achieved: Negative impacts from site preparation and construction works have been managed according to the mitigation hierarchy, in line with the SQE's recommendations - - Feb-23 SQE confirmationprovided as per LUE 02. Ecological enhancement Measures have been implemented that enhance ecological value, which are based on input from the project team and SQE in collaboration with representative stakeholders and data collated as part of the āDetermining ecological outcomesā in LE 02 Measures are implemented in the following order: a On site, and
Change and enhancement of ecology Up to three credits are awarded based on the change in ecological value occurring as a result of the project. 3 3 Feb-23
Exemplary level criteria The change in ecological value calculated under criterion above confirms significant net gain has been achieved as 1 1 Feb-23 The change in ecological value calculated as above confirms significant net gain has been achieved. Almost complete Complete Ecologist Landscape architect LUE 04 Ecological change and enhancement Ecologist Landscape architect Ecological risks and opportunities LUE 02
Pre-requisite
The client or contractor has confirmed that compliance is being monitored against all relevant UK, EU and international standards relating to the ecology of the site.
Comprehensive route (Route 2) - Criterion 8 in LE 03 has been achieved (Negative impacts from site preparation and construction works have been managed according to the mitigation hierarchy, in line with the SQE's recommendations) and at least one credit under LE04 for 'Change and Enhancement of Ecology' has been awarded.
Measures have been implemented to manage and maintain ecology throughout the project. These measures are based on input from the project team in collaboration with representative stakeholders and data collated as part of the āDetermining ecological outcomesā in LE 02 To ensure the optimal ecological outcomes agreed in LE 02 are met in-practice, these measures must monitor and review the effectiveness of the mitigation and enhancement measures in place for LE 03 & LE 04 to ensure they are implemented.
Management and maintenance throughout the project
- Contractor nominates biodiversity champion - Contractor trains the site workforce on how to protect site ecology during the project - Contractor records actions taken to protect biodiversity and monitor their effectiveness A new ecologically valuable habitat appropriate to the local area is created
- Where flora and/or fauna habitats exist on-site, the contractor programmes site works to minimise disturbance to wildlife
A section on Ecology and Biodiversity has been included as part of the tenant or building owner information supplied, to inform the owner or occupant of local ecological features, value and biodiversity on or near the site. This should include detailed management and maintenance plans as required by landscape and asset managers as well as relevant parts of the handover information for occupiers written in a format that encourages understanding and supportive behaviours 1 1
Contractor to confirm compliance will be monitored against all relevant UK, EU and international standards relating to the ecology of the site.
McLH to please confirm measures will be implemented to manage and maintain ecology throughout the project - as per letter template.
- Y Comeplete Ecologist /McLH Feb-23
Complete
Ecologist
McLH
Feb-23
the first five years, includes: Actions and responsibilities of relevant individuals prior to handover The ecological value and condition of the site at handover and how this is expected to develop and change over time Identification of opportunities for ongoing alignment with activities beyond the development project, which support the aims of BREEAM's Strategic
1 1 Complete Ecologist McLH May 2023 Landscape
plan provided. McL&H to confirm via letter template Pre-requisite All systems with electric compressors comply with the requirements of BS EN 378:2016(207) (parts 2 and 3). Refrigeration systems containing ammonia comply with the Institute of Refrigeration Ammonia Refrigeration Systems code of practice - Y May 2023 Halsion has provided manufacturers guidance and confirmation that all systems meet requirements Impact of refrigerant The systems using refrigerants have Direct Effect Life Cycle CO2 equivalent emissions (DELC CO2e) of ⤠100 kgCO2e/kW cooling/heating capacity OR Where air-conditioning or refrigeration systems are installed the refrigerants used have a Global Warming Potential (GWP) ā¤10 2 2 Complete Halsion shas issued guidance for refrigerant R513A. Pol 01 calculator confirms 2 credits. Impact of refrigerant OR 1 credit Where the systems using refrigerants have Direct Effect Life Cycle CO2 equivalent emissions (DELC CO2e) of ā¤1000 kgCO2e/kW cooling/heating capacity. 1 1 Complete as above Pol 02 NOx emissions NOx Emission levels for heating and hot water (mg/kWh) All heating and hot water is supplied by non-combustion systems OR The plant installed to meet the buildingās delivered heating and hot water demand has, under normal operating conditions, a Maximum NOā emission levels as follows: GAS boiler: 1 credit: ā¤27 mg/kWh 2 credits: ⤠24mg/kWh 2 2 Complete Halsion Complete Halsion has confirmed no gas boilers to be provided. Flood resilience A site-specific flood risk assessment (FRA) confirms the development is situated in a flood zone that is defined as: 2 credits: having a low annual probability of flooding 1 credit: having a medium high annual probability of flooding AND increase the resilience and resistance of the development to flooding To increase the resilience and resistance of the development to flooding, one of the following must be achieved: a The ground level of the building and access to both the building and the site, are designed (or zoned) so they are at least 600 mm above the design flood level of the site's flood zone. OR b The final design of the building and the wider site reflects the recommendations made by an appropriate consultant in accordance with the hierarchy approach outlined in section 5 of BS 8533:2017 2 1 Complete 1 Credit to be targeted. Flood Risk Assessment has been updated and report shared. Confirmation provided from team that additional resilience is being added. Design team to confirm that the final design of the building and the wider site reflects the recommendations made by the flood risk consultant letter from Maggie should suffice Pollution (0.75% per 1 credit) Impact of refrigerants Pol 01 Halsion LUE 05 Long term ecological management and maintenance Complete
Ecologist satisfied with first visit.. Jack Monaghan was appointed as Biodiversity Champion and his responsibilities were clearly defined. Landscape and ecology management plan Landscape and habitat management plan is produced, in accordance with BS 42020:2013 Section 11.1, covering at least
Ecology Framework Identification and guidance to trigger appropriate remedial actions to address previously unforeseen impacts Clearly defined and allocated roles and responsibilities for delivering the plan The landscape and management plan or similar will be updated to support maintenance of the ecological value of the site
and ecology management
For brownfield sites, drainage measures are specified so that the peak rate of run-off from the site to the watercourses (natural or municipal) shows a 30% improvement for the developed site compared with the predeveloped site. This should comply at the 1-year and 100-year return period events.
For Greenfield sites, drainage measures are specified so that the peak rate of run-off from the site to the watercourses (natural or municipal) is no greater for the developed site than it was for the pre-development site. This should comply at the 1-year and 100-year return period events.
Relevant
Surface water run-off rate calcs have been provided for 1-year and 100-year.
Calculations appear to demonstrate that a 40% allowance for climate change has been provided.
Written summary confirmation has been provided demonstrating compliance can be met: Confirmation that surface water run-off design solutions are bespoke, i.e. they take account of the specific site requirements and natural or man-made environment of and surrounding the site. Please confirm the priority levels detailed in BREEAM have been followed, with justification given where water is allowed to leave the site. For brownfield sites, drainage measures are specified so that the peak rate of run-off from the site to the watercourses (natural or municipal) shows a 30% improvement for the developed site compared with the predeveloped site. This should comply at the 1-year and 100-year return period events. OR For Greenfield sites, drainage measures are specified so that the peak rate of run-off from the site to the watercourses (natural or municipal) is no greater for the developed site than it was for the pre-development site. This should comply at the 1-year and 100-year return period events.
Please confirm calculations and reports are for both buildings, noted Building A and Building B on the submitted drawings.
Please confirm maintenance agreements for the ownership, long term operation and maintenance of all specified Sustainable Drainage Systems (SuDS) are in place.
Calculations have been provided.
Calculations and reports are for both buildings, noted Building A and Building B on the submitted drawings.
Flooding of property will not occur in the event of local drainage system failure (caused either by extreme rainfall or a lack of maintenance); AND EITHER
Drainage design measures are specified so that the post-development run-off volume, over the development lifetime, is no greater than it would have been prior to the assessed siteās development. This must be for the 100year 6-hour event, including an allowance for climate change.
Any additional predicted volume of run-off for this event is prevented from leaving the site by using infiltration or other SuDS techniques.
OR (only where criteria above cannot be achieved):
Justification from the appropriate consultant indicating why the above criteria cannot be achieved, i.e. where infiltration or other SuDS techniques are not technically viable options.
Drainage design measures are specified so that the post-development peak rate of run-off is reduced to the limiting discharge. The limiting discharge is defined as the highest flow rate from the following options:
a.The pre-development one-year peak flow rate
b. The mean annual flow rate (Qbar)
c. 2L/s/ha.
For the one-year peak flow rate, the one-year return period event criterion applies.
For either option, above calculations must include an allowance for climate change; this should be made in accordance with current best practice planning guidance.
Please also confirm relevant maintenance agreements for the ownership, long term operation and maintenance of all specified SuDS are in place.
Surface water run-off rate
maintenance agreements for the ownership, long term operation and maintenance of all specified Sustainable Drainage Systems (SuDS) are in place.
planning guidance 1 1 Complete
Calculations include an allowance for climate change. This should be made in accordance with current best practice
Surface water run-off volume Flooding of property will not occur in the event of local drainage system failure AND Drainage design measures are specified so that the post-development run-off volume, over the development lifetime, is no greater than it would have been prior to the
1 1 Complete
assessed siteās development. This must be for the 100-year 6-hour event, including an allowance for climate change, Any additional predicted volume of run-off for this event is prevented from leaving the site by using infiltration or other SuDS techniques
Pol 04 Reduction of night time light pollution Reduction of night time light pollution The external lighting strategy has been designed in compliance with Table 2 of the ILP Guidance notes for the reduction of obtrusive light, 2011 AND All external lighting (except for safety and security lighting) can be automatically switched off between 23:00 and 07:00 If safety or security lighting is provided and will be used between 23:00 and 07:00, this part of the lighting system complies with the lower levels of lighting recommended during these hours in Table 2 of the ILP guidance notes 1 1 Complete Halsion May 2023 Halsion has confirmed all external lighting will be designed to IPL guidance notes. Spec - page 257 clause E3-8 External Lighting Pol 05 Reduction of noise pollution Reduction of noise pollution There are no noise-sensitive areas within the assessed building or within 800 m radius of the assessed site OR Noise level from the proposed site/building, as measured in the locality of the nearest or most exposed noise-sensitive development, is a difference no greater than +5dB 1 1 Complete Acoustician / McLH Jan-23 Draft letter with McL&H for review. Copy of the acoustician report received - noise impact assessment
confirm commitment to undertaking a noise impact assessment compliant with BS 4142:2014 at an appropriate time. Surface water run-off Pol 03 Robert Bird Almost complete
Please
FH090-151015 appendix h
Aecom CMT report
To: FrancisHunter ā Luke Nurser
CC: meeting distribution
Monthly Report : TA/CMT No 23: 29/05/24
Report up to 28/05/2024
1. Key Actions in Month
1.1 Review meeting to clear comments on Stage 5 drgs & tech subs
1.2 Review of packages on Viewpoint ā Stage 5 tech subs are ongoing .
1.3 Site visit No7 for MEP ā SVR issued.
1.4 Review of power on & HV/LV switchrooms
1.5 Meeting re proposed commissioning/demo process.
2. Status of Document Submittals
AECOM Sunley House 4 Bedford Park Croydon CR0 2AP, UK T +44(0)203 043 9200 aecom.com
Project name: Project Honey - Kingston Project ref: 60627560
By : D Emerson
Date: 29/05/24
2.1 Workshop held to agree remaining comments - Comments issued on submittals as per MCLH notes of review.
3. Any key issues / comments / quality issues related to site/Test activities
3.1 see SVR007. Installation benchmarks reviewed on visit & comments noted.
3.2 Comments raided on power on & HV/LV rooms ā response awaited.
4. Key actions for next month
4.1 Review of o/s package comments to be submitted as per MCLH list
4.2 Continue schedule of visits.
4.3 Agreement on close out process
4.4 Comments on HV/LV switchrooms
5. Key decisions required / variations
5.1 Commissioning / demo and completion programme.
6. Any CDM issues
6.1 n/a
Memo \\na.aecomnet.com\lfs\EMEA\London-UKLON06\Legacy\UKLON06PFPSW001\UFI\Jobs\PR469433_Project_Honey\500_Deliverables\570_Reports\PHK_AECOM_CMT report 23 2024_05_29.docx
FH090-151015 appendix i
MNP CMT report
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
1 General Progress of the Works: Site Works
No. of CMR site visits to date: 19
MNP last attended site on 14th May 2024.
⢠The focus of MNP work this month has been on the review of low concrete cube results, which have been reported on by RBG and issued for review on 28th March 2024. The final MNP CMR report will be issued before the end of the Month.
⢠We also met with McL&H on site and reviewed line-by-line our ongoing site observations tracker, and closed items where evidence has been provided by McL&H. A number of items remain open and McL&H are collating evidence to demonstrate which have been closed.
⢠MNP attended site at the invitation of McL&H for the final snagging walk over Block C ā The Car Park. Observations are reported within this document. Our general observation is that the car park is yet to be completed, and as such, is not in a position to be snagged. We have made recommendations in this report to show the matters to be addressed, many of which have been reported in earlier site observation reports. The design architect and engineer are to review and provide input in the close out process. MNP will next attend when McL&H snagging is completed.
⢠The majority of defects in the car park can be addressed by making good, but we draw attention to the water ingress which appears to be ongoing after waterproofing installation. An architectural rview of the waterproofing is required. We have raised some concerns in this report.
⢠The water entry continues to affect concrete and steel beams which must be made good. Steel delta beams are corroding and we highlight concerns about how these can be effectively remediated given that the concrete now obscures the steel
⢠We are informed that the planning condition tracker is currently being updated. We will report on final condition status on receipt of this document.
General view on Level 7 mezzanine deck roof
Waterproofing has been completed and insulation is in place ready for the creation of the landscaped area. The inspection followed a night of heavy rain and the photographs at lower levels will show how there is still substantial water ingress to the building. The source of the water is unknown as there are some open aspects to the car park, but we have to question whether the waterproofing is effective.
It is important that this is determined before the landscaping is installed to avoid having to remove finishes at a later date to access waterproofing.
Ref
Observations ā 14th May 2024 1
Block C Snagging Visit
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024 2
General view on south side high level roof
Waterproofing is complete on the deck but there is no waterproofing or finish to the top of the parapet walls at the opening Normal cracks in the top of the wall will be subject to wet and dry / freeze and thaw and we expect that cracks will degrade over time. The waterproofing partly laps over the parapet, and around temporary posts. Is there to be a capping applied later?
We noted area of local damage in the top of the wall and grout holes that were not fully infilled, leading to pooling. Looking down the shaft we see that the joints between PCC are rough and partly filled. Will the shaft be covered to prevent water entry?
The outlet to the roof is not to a hopper so water will run down the wall. There is some pooling of rainwater on the waterproofing so we can conclude that a positive fall has not been made to the gully point.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Visible water ingress through PCC joists indicates that waterproofing is not as required above. Damage to PCC staircase nosing to be made good. External waterproofing at deck level is installed. Architect to comment on system which appears to be a bitumen single layer bonded system
3.
Level 7 Mezzanine South Staircase
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
4
Steel angle supports to underside of high-level roof are pointed but surface rust is visible and appears to be developing. The steels must be protected to prevent corrosion. Details of the paint and confirmation of design life requested. Environment is external but sheltered from rain.
Visible water ingress through PCC joists to soffit of slab. Concrete fillet is de-bonded in placed and came loose when pressed. Joints to be made good.
Level 7 Mezzanine North Staircase
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024 5.
Level 7 Mezzanine North
15mm deep pooled water against the access to the north staircases shaft. Incomplete waterproofing at junction to be made good after removal of temporary edge barrier.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
6. Steel beams within body of main car park
Steel Delta Beams are protected by a paint system which has failed under constant wetting during the construction period. Water is still trapped within the beams, which are wet, and water is seeping out from the elastomeric bearing strip, indicating that there is water trapped in the system.
The paint has failed and must be repaired to give a full design life. Access is easily achieved from the soffit but there is no access to the steel below the bearing strip. The designer must provide a solution. The steel requires protection and cannot be accepted as unprotected. We are concerned that an effective repair may not be achievable without some sort of intrusive works / investigations. The designer is to make a proposal for investigation and repair.
Furthermore, concrete repairs close to the ends of the Delta Beams are rough and poorly designed. In places the concrete traps water against the steel beams and obscures repair to the paint system. The concrete has been moulded to form a detail, but does not appear to be aesthetically acceptable in our view. The architect must provide comment before this can be accepted.
A sample repair to the paint system has been completed at level 2. This appears to provide a good level of coverage to the soffit but the paint protects only the visible face of the steelwork. The paint appears patchy and we would recommend that a full repaint may be required to achieve an acceptable product.
We must receive an acceptable plan of action to protect the steel before snagging is completed to avoid potentially abortive works No works can be effectively undertaken until water is excluded from the system and the steels dry out in our opinion
Bear in mind, the final in-use structure will be subjected to de-icing salts so we expect corrosion so accelerate in-use. Solutions must be fit for the final use.
Sample of photographs follows to demonstrate the issue of concern, which are widespread;
Water trapped within hollow core and joint has compromised the paint protection.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Water ingress at bearing. Hand trowelled concrete repair. Rust stains on concrete,
Water ingress at joint in slabs has caused corrosion
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Examples of concrete repair mortar up against painted steelwork The concrete repair prevents paint repair and must be removed locally. Paint has been scuffed and damaged ā visible in rust pattern.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Untidy detail. Concrete infill to be improved and please remove protecting film from bearing to improve aesthetic Steel has water damage and was wet to touch (u/s L07 mezz).
Water ingress affecting paint system and causing rust. Underside of beam wet after overnight rain.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Active water ingress at a lower level leading to wetting of the hidden steel.
Repaired beam at Level L02 ā paint to soffit only
Repaired beam at Level L02 ā paint to soffit only
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Staircases within body of main car park Concrete formed to a basic level of finish
7. Concrete structures within body of main car park
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
7.
Water trapped in hollow pot flooring is seeping out Wet to touch. Stalactites forming.
Water seeping out of bearing of PCC to edge beams.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Damaged concrete bearing and exposes PT strand rusting. Water ingress appears to be live.
Water staining at joints between PCC units. Appears to be historic. Laitance to be removed.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Water staining at joints between PCC units and edge beam. Appears to be historic. Laitance to be removed.
Water staining at joints between PCC units at depth change. Appears to be historic Light laitance but it should be removed.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Saw cut movement joint has been stopped each side of longitudinal joint Joint must continue to avoid cracking. Joints to be sealed to prevent debris ālocking offā movement joints.
Active water ingress running down ramp walls at hollow-core joints, suggesting hollow cores may be water filled and that waterproofing maybe ineffective above. To be resolved and laitance and staining to be addressed.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Long term water run off onto ramp slab has revealed aggregate in top surface. Water ingress to be dealt with and concrete to be cleaned of debris.
Heavy laitance and staining and local repair to spine beam. Concrete must be prepared to remove laitance and staining prior to final inspection. The level of staining is not as expected in a new concrete car park and requires significant improvement.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Heavy laitance and staining and local repair to spine beam. Concrete must be prepared to remove laitance and staining prior to final inspection. The level of staining is not as expected in a new concrete car park and requires significant improvement.
Open gap at central spine to be protected to prevent falls. Bearing of PCC spine beam appears to have a difference of circa 25mm Responsible structural engineer to comment as to whether this is acceptable within design criteria
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Uneven bearing and heavy laitance and staining. Active water ingress ā dripping off stalactites. Ensure waterproofing above is effective. RE: stepped bearing; responsible structural engineer to comment as to whether this is acceptable within design criteria Concrete to be cleaned and prepared in final snagging. Rough joint between PCC hollow-core planks to be made good.
Rough finished concrete at floor gully requires repair to avoid degradation over time. Not acceptable in current form.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Stepped corbel cracking has been repaired over part of the column head only. Complete repair work as part of final snagging.
Untidy detail at PCC interfaces and some debris in joint. To be revisited as part of snagging.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Active water ingress reaching Level 5 mezzanine slab. Water is moving through the building.
Active water ingress through ramp corbels at Level 5
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Active water ingress at level 5 spine
Voiding within open cores to be made good to protect the rebar in the PCC planks
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Water ingress in stair core to Level 5 mezzanine
Active water ingress to Level 5 ramp soffit
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Staircase landing slab step to be made good to prevent trips. Step is approx. 5mm
Unacceptable staining and laitance at Level L04
Active water ingress in Level 4 staircores
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Untidy joint in PCC and visible twist in bearing. Damaged concrete at corner of PCC. To be revisited in snagging.
Staircase landing slab step to be made good to prevent trips. Step is approx. 5mm
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Water ingress through joint in staircase at L04 ā appears historic but laitance must be removed.
Severe trip hazard at level L02 ā circa 25mm. Architect to review and comment but this does not appear to be acceptable and the floor must be made good to avoid trips and ankle twists.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
8. Lower Level Car Park Uses
Water-staining at level L01 is not damp to touch. Clean off laitance.
Blockwork and insulation installations are still in progress
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Rough finished concrete to be revisited as part of snagging.
Trip hazard at entry to staircase cores to be made good.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Water entry from roof down M&E shafts. Are the openings to be covered? Water ingress to dry staircases is not acceptable.
Rough finish surface to staircase fire escape to be improved to avoid trips.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Water penetration through external blockwork to be resolved.
Statement required from Superstructure and Substructure Engineers to confirm misalignment of systems can be accommodated by the designed systems.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Vehicle damage to two perimeter blockwork panels. Wall panels to be reconstructed. End panel has slipped its bearing, and a second panel has an impact strike crack pattern.
Temporary bund to prevent water ingress to lift pit to be made good. Concrete repair required to damaged corner PCC panel.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Exposed rebar in top of L00 corridor ramp to be repaired to ensure required cover is maintained.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Finishing works to be completed at front elevation ā PCC holes to be infilled. External skin to be added to wall.
Cut rebar in face of wall to be protected by render repair product to prevent corrosion
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23 17th May 2024
Blockwork point to be completed
Rear elevation progress
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Front elevation progress
2 General Progress of the Works: Design Submissions
The following packages have been reviewed, blue items within this period. Refer to Appendix B: Technical Submission Tracker.
⢠Attenuation product data sheet (ahead of final design information)
⢠Piling Specification ā RBG
⢠Piling Package ā Van Elle
⢠RBG Loading Plans
⢠RBG Building A Superstructure GAs (design still in progress)
⢠RBG Building B Superstructure GAs (design still in progress)
⢠RBG Building C Substructure (in progress)
⢠RBG Drainage
⢠RBG Building A and B Pile-caps
⢠RBG Building C Piling
⢠RBG Block B revised loading plans
⢠RBG Block B Foundation Revision
⢠RBG Block B L10 Revision
⢠McL&H Benchmark Columns
⢠RBG Block A Core Plans
⢠RBG Block B Core Plans
⢠RBG Block C Drainage
⢠RBG Block A Townhall Steelwork
⢠RBG Block C Drainage
⢠RBG Blocks B and C Cores
⢠RBG Block A L06 amendment
⢠RBG Block A,B,C concrete cube report
3 Contractorās Quality Control
Implementation of the Contractorās Quality Control Systems in relation to ERs and Building Contract We can confirm that the design development and/or construction work carried out to date has been regularly inspected/reviewed by the Contractor in this period of reporting
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
We list any suspected defective work and recommend procedures for remedial action including, where necessary, a regime of testing or exposure. Refer to Appendix A: Site observations tracker.
4 Statutory Approval Status
Report on current status of local authority and other statutory approvals relating to Civil and Structural Engineering. Discharge of reserved planning matters or conditions. We report in reference to Eden Campus Conditions Matrix (Chartplan) tracker dated 23/08/2023 Refer to Appendix C: Planning conditions tracker. There has been no change to status of conditions since this date.
Approval of Building Regulations submissions and discharge of any conditions hereto.
⢠All building control approvals are recorded in the McL&H monthly contractorās report.
Comment on satisfaction of Building Inspectorās routine inspections.
⢠No Building Regulation Inspection Reports are known to have been submitted.
5 Prohibited Materials
MNP has not become aware in carrying out its duties under the Appointment and/or this deed that any of the materials or substances referred to in clause 6 of this agreement (Prohibited Materials) are being or has been used in the Development.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Appendix A ā Site Observation Tracker
1 22.07.22
Demolition of the NCP car park is approaching the shared foundation with Lever House. Discussions with the demolition contractor on site indicated that the presence of the shared foundation may not be well understood
2 24.08.22 Demolition of the NCP car park is approaching the shared foundation with Lever House. McL&H and RGB attending site to monitor demo works in vicinity of shared foundation.
The demolition contractor is to demonstrate by RAMS how the works in the vicinity of the shared foundations are to be controlled and the main contractor team is to put in place controls to ensure that the Lever House foundation is protected.
3 20.10.22 No additional comments to make No additional comments to make
4 28.11.22
Rebar cage in Block B central core pile has displaced
5 28.11.22 Rebar to top of Block A pile cap appears to be set lower than the cover zone.
6 11.01.23
Check the cover on the pile is as required to ensure durability meets the ERs (Reviewed May 2024) - McL&H and Van Elle to comment.
Check the cover over the rebar cage is as expected and that it complies with the design intent, and controls cracking.
Excavation close to Brook St bus stops. MNP discuss temporary stability of berm on site with McL&H who confirm temporary stability has been discussed with RBG and earth is stable No additional comments to make
7 11.01.23 MNP / McL&H review Field View Quality system in site office.
8 21.02.23 Column rebar arrangement in a Block A column. Lower start bars set inboard of cranked bar..
9 24.02.23
Block A L01 slab soffit ā rebar marking and grout leakage at day joints.
10 24.02.23 Block A L01,L02 slab soffit ā Most of the soffit is very good but some areas of poorer finish are emerging.
Good QA/QC systems in place. No additional comments to make.
McL&H asked to check rebar arrangement is as required and log via field view.
McL&H to check rebar pattern is not associated with low cover (it looks like staining only from rebar stored on the shutter). McL&H to comment as to whether the staining will be removed and to review shutter cleaning near rebar stock pile locations. (Reviewed May 2024) - McL&H to comment.
McL&H to comment on how marking can be avoided by the subcontractor in the future. Check ply liners are not damaged and are cleaned. 11 24.02.23 Block A L02 Column ā Grout leakage from slab at head and blow holes require repair.
To be addressed prior to offering for inspection. Agree repair with client by establishing benchmark for repaired column. We recommend grout at head of column is removed by slab follow up team after shutters are removed to limit staining potential.
24.02.23 Block A L02 lift lobby. Grout
To be addressed prior to offering for inspection. Recommend establishing a benchmark area at an earlier stage to set expectations for exposed concrete finish.
To be reviewed and discussed with concrete contractor to ensure quality of finishes can be achieved by the follow up team
Site Visit Date Observations Recommendation
Ditto
leakage
soffit staining.
12
and
13 25.05.23 Block A L01 slab soffit ā grout loss at day joint and rebar rust staining
14 25.05.23 Block A L02 soffit ā marks on soffit from damaged shutters To
concrete contractor
up team 15 25.05.23 Block A Lift Lobby ā marks on soffit from water staining and laitance, grout runs on walls To be reviewed and discussed with concrete contractor to ensure quality of finishes can be achieved by the follow up team.
benchmark
after preparation. 16 25.05.23 Block B L01 corbel slab drops ā crack in column head (possibly ā viewed from afar)
17 14.07.23 Block A slab soffit ā rust staining at tie wire debris To be reviewed
discussed with concrete contractor to ensure quality of finishes can be achieved. Can tie wires can be swept away earlier? 18 30.08.23 Block B back propping.
flat
limited
levels.
be reviewed and discussed with
to ensure quality of finishes can be achieved by the follow
Recommend offering for
inspection
To be reviewed by the SE (Reviewed May 2024)McL&H to ask RBG to comment.
and
On review of site photographs we can see that three levels of back propping is in place in block A and part block B, but over half of the block B footprint, back-props to the
slab are
to two
McL&H to please confirm this sequence is as used in the temporary loading calculations and long-term creep calcs. (Reviewed on site May 2024) - McL&H / CCL to comment.
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
19 30.08.23
20 30.08.23
21 03.10.23
22 03.10.23
23 03.10.23
24 03.10.23
Plywood closures have been fitted to the flood void entry points to prevent vermin entering the voids. The flood void is therefore closed.
Block C Ramp Tie pars have been cold worked and do not align with topping / tie slots in PCC
Block C ā Overspill concrete in flood void to be removed
Block C ā Use of PT tendon as tie bar through Delta Beams
Block C ā Damage to PCC elements to be repairs prior to handover to McL&H for snagging
Block B ā L09 slab construction joint ā remove laitance form shutter prior to pour
25 03.10.23 Block B ā Core door enlargement ā cover protection to be added
26 23.10.23 Block A ā Steel beams in Town Hall are propped with two floors of RC cast above
27 23.10.23 Block A ā L6 slab soffit appears to be very wet so looks highly variable
A Town Hall steel
Does this affect the flood performance of the site during the works? Could there be adverse comment from the EA?
Post 3/10/23 visit ā suggest McL&H simply have a policy to remove covers in the case that the site is shut down through a flood event.
McL&H to review and advise how the tie bars will be resolved. (Reviewed on site May 2024) - McL&H to comment
McL&H confirmed this has been completed (May 2024) āSV meeting on site.
McL&H to review and confirm this is as the required tie detail (Reviewed on site May 2024) - McL&H to comment
McL&H confirmed on site that this will happen. Snagging will on be when the PCC formally offers the system. (Reviewed on site May 2024) - McL&H to comment
McL&H confirmed on site that this in on their snagging schedule
McL&H confirmed on site that this in on their snagging schedule (Reviewed on site May 2024) - McL&H to comment
McL&H to confirm TW release strategy to avoid āshockingā the concrete structure above when steel deflects.
Assumed to be storm related ā MNP to inspect when dry
to confirm they have primed site welding prior to over coating and site welds have test certifications. 29 06.12.23
A Roof ā Poorly formed column
Block
head
marks to column shaft McL&H to remediate prior to handover
06.12.23 Block
roof slab soffit
very poor finish McL&H
satisfactory. 31 06.12.23 Block B ā Cast in steels in soffits of slabs McL&H to remediate prior to handover FP McCann Action. 32 06.12.23 Block C ā Defects at Delta Beam bearings and corbels McL&H to remediate prior to handover FP McCann Action. 33 07.02.24 Block A ā temporary bracket within galvanised steel plant frame MNP note that this was resolved on 20.3.24 visit 34 07.02.24 Block C Roof Access Staircase - staining FHPM to confirm if this finish requires enhancement 35 07.02.24 Block C ā Cracking to column corbel McL&H to ask FC McCann Engineer to review (Reviewed on site May 2024) ā Partial repair instigated āno confirmation from Engineer as yet. 36 07.02.24 Block C ā Cracking to beam corbel McL&H to ask FC McCann Engineer to review (Reviewed on site May 2024) ā Partial repair instigated ā no confirmation from Engineer as yet. 37 07.02.24 Block C ā Delta Beam Corrosion where supporting PCC McL&H to confirm how steel paint will be made good to offer required protection 38 07.02.24 Block C ā Steel tendon within PCC joint McL&H to confirm how this will be treated to avoid future corrosion / spalling 39 20.03.24 Block C ā Vehicle impact damage to L00 blockwork McL&H to rebuild blockwork / repair as required 40 15.05.24 Block C ā Water ingress throughout building despite waterproofing appearing to be complete. McL&H to confirm how this will be resolved ahead of landscape installation. 41 15.05.24 Block C ā Upper level roof parapets are not protected and water runs off down wall. RWP / hopper required. McL&H to confirm how this will be resolved with the architect. 42 15.05.24 Block C ā Trip hazards between main car parks and staircase access routes up to 25mm deep ārequired resolution to avoid trip hazard. McL&H to confirm how this will be resolved with the architect.
28 06.12.23
McL&H
Block
and
30
A
ā
to confirm if this is to be treated (Reviewed on site May 2024) - McL&H show photographs of repairs which looked to be
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
43 15.05.24 Block C ā Widespread construction defects to be made good as part of final follow up snagging / clearing operations including;
⢠Water staining to concrete (laitance / stains)
⢠Damaged PCC with exposed rebar
⢠Misaligned PCC units
⢠Untidy concrete repairs
⢠Making good to joints required
⢠Steel delta beams corroded and wet
⢠Steel ledger angled to L08 roof paint required update ā rust appearing
⢠Permanent edge protection to be installed
⢠Debris in PCC joints
⢠Voiding in cored concrete to be made good
⢠Exposed rebar in top of L00 ramp slab
⢠Block work pointing incomplete
⢠Temporary bunds to lifts to be removed
⢠Uneven surface in fire escapes
44 15.05.24
Appendix B ā Technical Submission Tracker
McL&H to resolve all to final snagged state prior to final inspection. There is work to do.
McL&H
rebuilt
damaged walls.
Damaged masonry walls ā vehicle strikes. Rebuilt damaged walls.
to arrange
of
Technical Submission Planned Received Progress CMR Comments Status (No.) A B C Piling Design (Van Elle) 29.07.22 15.08.22 Issued 19.08.22 UXO risk expected in RAMS Pile design Cu max commented on Pile design eccentricity commented on Preliminary pile test results requested Piling near to Lever House pending existing foundation survey 5 1 0 Piling Design Intent (RBG) 29.07.22 09.08.22 Issued 19.08.22 Block B piles close to Lever House. Advisory comment on proximity and centres. 1 0 0 Attenuation Tanks 29.07.22 26.07.22 Issued 04.08.22 Product data sheet only reviewed. No design intent received. No comments on data sheet 1 0 0 Building C - Substructure - 15.08.22 26.09.22 Design in progress and requires coordination. General comments made. 0 5 0 RBG Loading Plans āBuildings A and B - 25.08.22 26.09.22 Loading Plans all as ERs 20 0 0 RBG Constraints Drawings - 01.09.22 26.09.22 Site constraints and Lever House Interface. Comments made on drainage and site risks 0 2 0 RBG Superstructure GAs Buildings A and B - 02.09.22 26.09.22 Design in progress and requires coordination. General comments made. 0 20 0 RBG Substructure Building Bā Layouts - 02.09.22 26.09.22 Design in progress and requires coordination. General comments made. 1 0 0 RBG Drainage ā Layouts and scheduled - 05.09.22 05.10.22 General comments on design principles and details to be addressed 0 6 0 Van Elle Pile Tests - 08.09.22 13.10.22 No comments 5 0 0 RBG Building A and B Pile caps - 04 10.22 19.10.22 Comments on GA plans relating to inline pile caps and restraint of ecc moment, as well as concrete grade interactions. 23 3 0 RBG Basement Waterproofing 01/12/22 13/10/22 Comments on drawings uploaded to VP 0 1 0 RBG Block A L00 06/12/22 13/10/22 Comments on drawings uploaded to VP 4 2 0 RBG Block B L00 06/12/22 13/10/22 Comments on drawings uploaded to VP 1 2 0 RBG Block C Piles 08/12/22 13/10/22 No comments 2 0 0 RBG Block B LoadplansL10 06/02/23 07/02/23 No comments 1 0 0 VanElle Pile design Block C 02/02/23 07/02/23 No comments 1 0 0 RBG Block C Foundation 14/02/23 14/03/23 Comments but drawing superseded on VP 0 1 0
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering Monthly Progress Report ā Report 23 17th May 2024
RBG Block B Founds Rev 23/02/23 14/03/23 Comments on drawing uploaded to VP 0 1 0 RBG Block B L10 Revision 24/02/23 14/03/23 No comments 1 0 0 McL&H Benchmark Cols 24/02/23 14/03/23 Comments on benchmark column 0 1 0 RBG Block A Core Plans 28/02/23 12/05/23 No comments 7 0 0 RBG Block B Core Plans 28/02/23 12/05/23 No comments 7 0 0 RBG Block C Drainage 07/03/23 10/03/23 Comments made 0 3 0 RBG Block C Loading Plan 23/03/23 12/05/23 No comments 1 0 0 Block A Townhall Steelwork 23/03/23 12/05/23 No comments 13 0 0 RBG Block C Drainage 17/04/23 17/04/23 Comments made 0 3 0 RBG Blocks B and C Cores 25/04/23 12/05/23 No comments 8 0 0 RBG Block A L06 Plans 26/06/23 30/08/23 No comments 1 0 0 RBG Block A L08,9,10 03/08/23 24/08/23 No comment 3 0 0 RBG Block A B C concrete cube test report on low results 28/03/24 In progress MNP have reviewed and will release report on findings shortly
220051 Eden Campus Kingston
Client Monitoring Report Civil & Structural Engineering
Monthly Progress Report ā Report 23
17th May 2024
Appendix C - Planning Condition Tracker
Pending release of final tracker by FHPM/DAA
8. All works on site shall take place in accordance withā¦details which shall haveā¦been submittedā¦in the form of a Demolition and Construction Environmental Management Plan.
9. The levels of buildings, roads, parking areas and pathways within the site shall⦠have previously been submitted to and approved in writing by the LPA before development is commenced.
10. Prior to the commencement⦠a Site Waste Management Plan/Circular Economy Statement shall be submittedā¦and approved in writing by the LPA.
14. Hard surfaces ⦠shall be made of porous materials and ⦠retained thereafter to direct run-off water ⦠to a permeable or porous area or surface within the curtilage of the property.
19. The development shall be carried out in accordance with the details approved on 25.02.2022 Reference 21/04117/CLC (Written Scheme of Investigation WSI - Archaeology).
23. The development ⦠shall not be commenced until a detailed Ecological Management Plan has been submitted ā¦and agreed in writing by the LPA.
34. Should remedial works be required in relation to contaminated land, the remedial strategy shall be submitted to and agreed in writing by the LPA, prior to the commencement of the development works and remedial works. On completion of the agreed remedial works, a closure report and certificate of compliance endorsed by the interested party/parties, shall be submitted to and agreed in writing by the LPA, prior to occupation.
35. If during implementation, contamination is encountered, it shall be fully assessed and a contaminated land assessment and remedial strategy shall be agreed by the LPA before the additional remediation works are carried out. The strategy shall be implemented prior to completion of the development.
36. Prior to commencement of groundworks (excluding SI and demo), a final detailed drainage design, including drawings, calculations, SuDS Statement and Drainage Assessment Form shall be submitted to and approved by the LPA. A detailed management plan must also be submitted for the lifetime of the development.
37. No building shall be occupied until evidence is submitted to demonstrate that the SuDS scheme has been completed in accordance with the submitted details. The SuDS scheme shall be managed and maintained in accordance with the agreed management and maintenance plan
41 The development shall be carried out in accordance with the submitted FRA by Cole Easdon (ref: 7378, issue no.5; dated November 2020) and the following mitigation measures:
FFL no lower than 8.8mAOD for more vulnerable residential uses
FFL no lower than 8.4mAOD for less vulnerable commercial uses
FFL no lower than 7.9mAOD for the commercial reception area
Flood storage mitigation shall be provided Flood voids shall be installed
42 The development shall be carried out in accordance with the submitted Interim Flood Storage Scheme detailed within the letter from MNP to the Environment Agency (SV/ib/220051-04; dated 15 February 2021). The car park ramp tank will be implemented at the trigger points specified and remain in perpetuity until the demolition of Lever House is complete.
43 Prior to occupation, a maintenance plan to manage the flood voids and grilles over the lifetime of the development will be submitted to, and approved in writing by, the LPA in consultation with the EA.
44 Prior to occupation, a scheme detailing the flood resistance measures must be submitted to, and approved in writing by, the LPA with guidance from the EA. The scheme should include passive flood barriers up to 8.31 mAOD to protect the shared reception of the Hive and Honey Buildings and the car park basement access ramp, stairwell and lift lobbies.
45 Surface water draining from areas of car park hardstanding shall be passed through an oil separator or series of oil separators, prior to being discharged into any watercourse, soakaway or surface water sewer.
53 The development shall be implemented in accordance with the details approved on 07.03.2022 under reference 22/00292/CLC (Water re-use/harvesting).
59 No piling shall take place until a piling method statement (detailing the depth and type of piling to be undertaken and the methodology by which such piling will be carried out, including measures to prevent and minimise the potential for damage to subsurface water infrastructure, and the programme for the works) has been submitted to and approved in writing by the LPA in consultation with TW.
64 Prior to the occupation of each building the post-construction tab of the GLAās whole life carbon assessment template should be completed accurately and in its entirety in line with the GLAās Whole Life Carbon Assessment Guidance.
No
No No
Yes Yes
Yes Yes
No No
Ref Planning Condition (Civil and Structural Only) Submitted? Approved?
Yes Yes
Yes Yes
Yes
Yes
Yes Yes
Yes Yes
Yes Yes
Informative Informative
Informative Informative
Yes
Yes
No
Informative Informative
Informative Informative
No No
Informative Informative
Monthly
Appendix D ā Building Control Submission and Approval Tracker Ref Building Control Submission Submitted? Approved? 1 REFER TO McL&H MONTHLY REPORT FOR A FULL UPDATE 2 3 4 5 6 Ref Building Control Inspection Report Submitted? Approved? 1 REFER TO McL&H MONTHLY REPORT FOR A FULL UPDATE 2 3 4 5 6
220051 Eden Campus Kingston Client Monitoring Report Civil & Structural Engineering
Progress Report ā Report 23 17th May 2024
ORSA monthly CDM report
FH090-151015 appendix j
Site Inspection
Eden Street Kingston Upon Thames KT1 1ER Globe Kingston Ltd 24 May 2024
Eden Campus
0.0 Document Verification
Job Number 2800 Job Eden Campus
Document Title Site Inspection File Reference SI1 ORSA_H&S Site Inspection February 2024.docx
Document Information
Revision Issue Date Filename 2800_Eden Campus_ORSA Site Inspection_FJMK240524
A 26/05/24 Description Site Inspection
Prepared By Checked By Approved By Name Francis J M Kenny James Bucknall James Bucknall
Signature Date 24/05/24 dd/mm/yy dd/mm/yy
Revision Issue Date Filename Description
Name
Prepared By Checked By Approved By
Signature Date dd/mm/yy dd/mm/yy dd/mm/yy
Revision Issue Date Filename
dd/mm/yy Description
Name
Prepared By Checked By Approved By
Signature Date dd/mm/yy dd/mm/yy dd/mm/yy
1 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
1.0 Key Project Details
Client Globe Kingston Ltd
Site Eden Campus, Eden Street, Kingston Upon Thames KT1 1ER.
Principal Contractor McLaughlin & Harvey Ltd
Inspected by Francis J M Kenny
Date 24 May 2024
Programme Completion due Sept 2024
2.0 Site Inspection
A site inspection of the Eden Campus Project was undertaken on the 24th May 2024 in the company of Jack Monaghan, Assistant Site Manager for Principal Contractor McLaughlin & Harvey Ltd.
The Project comprises the erection of 3 blocks. An 11-storey office block, a 9-storey office and retail block and a multi storey car park with 354 spaces.
The car park will contain ground floor changing area with showers and lockers. The office block will be occupied by Unilever when completed.
The purpose of the site inspection was to highlight any Health, Safety and Environmental observations and undertake a review of the on-site documentation in relation to the work activities that were being carried out.
3.0 Work activities ongoing at time of inspection
§ Roofing.
§ Glazing.
§ Metsec Partitioning.
§ Plaster Boarding.
§ Cladding.
§ M&E
§ Cable containment.
§ Rebar Installation.
§ Containment.
§ Waste removal.
§ Lifting operations.
§ Traffic management
§ Deliveries.
4.0 Site Attendance
The current average daily site attendance is approximately 240 including operatives and site management.
5.0 Accidents, Incidents & Near Misses
It was confirmed by Jack Monaghan that there have been no recorded accidents, incidents or near misses or Enforcing Authority visits since our last inspection.
6.0 Compliance Actions that the contractor needs to implement
Concluding this visit there were no issue or action raised, and all issues or actions raised last month have been addressed by McLaughlin & Harvey Ltd.
7.0 Comments
I conducted a thorough safety inspection of the project site, aiming to assess overall safety performance and ensure compliance with health and safety regulations and best practices.
Operatives continue to diligently following safety protocols with evident supervision, reflecting the management team's active engagement in promoting and enforcing safety measures, setting a commendable example for the project.
Biometric turnstiles effectively control site access, enhancing security and safety by permitting only authorized personnel entry.
The high-quality hoarding and fencing are regularly maintained, while up-to-date health and safety noticeboards ensure operatives are well-informed about safety requirements and legal obligations.
Daily hazard and briefing boards provide essential safety updates, enhancing operatives' awareness of potential hazards and safety precautions.
Adequate PPE usage was observed among all operatives, ensuring their safety during tasks.
While work areas, walkways, and routes were well-organised and maintained, dust management standards have been improved
Certified portable fire extinguishers and visible fire exit signage are crucial for emergency protection, while exclusion zones with effective barriers and signage minimize risks.
Method statements and risk assessments were deemed suitable, considering project-related health and safety risks.
Access to suitable first aid equipment and competent first aiders on-site ensure prompt medical attention.
The site offers adequate toilet and washing facilities, drinking water, and a well-maintained canteen area, with designated spaces for changing and storing clothing and PPE, prioritising workforce well-being and comfort.
Daily coordination briefings, while held, could be utilised more effectively to address safety improvement areas, thereby enhancing project standards and contributing to a wellcoordinated and safe work environment.
Documents observed while on site included:
§ Safety posters
§ Safety notice and hazard boards.
§ Permits.
2 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
8.0 Temporary Works Design & Coordination
McLaughlin & Harvey Ltd. has established a robust system to ensure that any temporary works installed on-site are appropriately designed and approved by competent engineers.
This measure is crucial to mitigate potential risks associated with temporary structures and ensure their stability throughout their intended use.
A comprehensive temporary works register is in place on the project. The register provides detailed information about all temporary works on-site, including their design specifications, installation dates, responsible personnel, and approval status, and the register is updated regularly to reflect any changes or new installations.
Andy Finnigan has been formally appointed as the responsible person for overseeing temporary works at the project site.
This appointment demonstrates a clear commitment to ensuring that temporary works are managed by a competent individual with the necessary expertise to assess and oversee their design, installation, and maintenance.
In line with best practices, McLaughlin & Harvey Ltd. has ensured that engineers responsible for designing and approving temporary works possess the required competencies and qualifications. This approach guarantees that temporary structures are designed and executed by individuals with the appropriate expertise.
9.0 Site Inspection Assessment Criteria below
The scoring criteria adopted for our site inspection is given as
3 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Exemplar Acceptable Improvement Needed Critical
10.0 Site Inspection Checklist & Actions
Observation
Project H&S Organisation
Project Arrangements
Project Risk Register
Project Methodology Statements
Inductions
Register/Notices/Forms
Permits to Work
Construction Phase Health & Safety Plan
Information
Communications/Consultation/Training
Site Establishment
Welfare-General
Canteen
Rest/Drying/Changing Room
First Aid
Sanitary/Washing Facilities
Walkways/safe routes
Fire escape routes
Access and Egress on site
Offices
Storage
Segregation of substances
Access / Egress
Site Boundary
Hoarding/Fence/Other
Security
Signage
Traffic Management
Status Comments
Acceptable Contained within the CPP.
Acceptable Project risk register available.
Acceptable In place for live works.
Acceptable Inductions carried out and recorded.
Acceptable Displayed.
Acceptable Issued and controlled.
Acceptable In place.
Acceptable Displayed on notice boards.
Acceptable Briefings undertaken daily.
Acceptable Good standard, clean and tidy. -
Acceptable Good standard, clean and tidy.
Acceptable Good standard, clean and tidy.
Acceptable First aid equipment available on site.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable Access and egress sufficient and not obstructed.
Acceptable Weil controlled
Acceptable Clean and tidy.
Acceptable Stored in line with COSHH assessment.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable Good standard and well maintained
Acceptable No issues identified.
Acceptable Good signage in place.
Acceptable Managed well.
4 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Action Date
- -
- -
- -
-
-
- -
- -
- -
-
-
- -
-
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Observation Status
One Way System?
Site internal turning
Banks man supervision
Vehicle/Pedestrian Segregation
Wheel wash
Site Access-General
Operations - Safety Management ā Planning
Risk Assessment-General
Method Statement-General
Roles and Responsibilities-General
Scaffold/Register
Plant/Register
False work
Temporary Works Design Brief
Temporary Works Appointments
Temporary Works Register
Operations - Safe Methods of Work
Compliance with method statement
Method Statement-General
Signature/Documentation
Risk Assessments
Permit system responsible person
Internal site safety tours
Documentation Acceptable
Considerate Constructors Registered
Water Management Plan
Emergency Fire evacuation Plan
Use of Scaff-inspection tags
Slips/`Trips /Falls
RPE - Face Fit testing
Acceptable Site has two gates, and a one-way system is used as required.
Acceptable Traffic marshals in place.
Acceptable In place.
Acceptable Good segregation is in place.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable RAMS are in place.
Acceptable Suitable and sufficient.
Acceptable In place and listed within CPP.
Acceptable Suitable and sufficient.
Acceptable Completed.
Acceptable. No issues raised.
Acceptable In place.
Acceptable In place for Andy Finnigan
Acceptable In place and up to date.
Acceptable No issues raised.
Acceptable Suitable and sufficient.
Acceptable In place within the site files.
Acceptable In place.
Acceptable In place and up to date.
Acceptable Regular tours undertaken.
Acceptable In place and relevant.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable In place.
Acceptable In place.
Acceptable No issues raised.
Acceptable No issues raised.
5 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Comments Action Date
- -
-
-
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Observation Status
Asbestos Register and Awareness Training
Good Practice - Safe Working
Work areas tidy
Walkways/safe routes clear of obstruction
Tools & Equipment suitable for the task
Safe manual handling
Signage
Storage of materials
Compliance with method statement
Personnel Protective Equipment PPE
Operations - Activity Set Up
Resources
Operatives Certification
Plant Certification
PUWER Register
Hoist Register
Crane Register
Lifting Equipment Register
Induction Register
Tool box talks
Contractor's team briefings
Operations - Activities -Safe Working
Site tidiness-Housekeeping
Fire Precautions
Fire safety route
Fire Fighting Equipment [Site]
Fire Signage
Fire Escape route
Fire Assembly
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable In place and sufficient.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable Clear and un-obstructed.
Acceptable Suitable for current activities.
Acceptable No issues raised.
Acceptable Plant registers maintained
Acceptable Records in place and up to date.
Acceptable Records in place and up to date.
Acceptable Four cranes in place, and rescue team trained.
Acceptable In place.
Acceptable In place and signed by site operatives.
Acceptable No issues raised.
Acceptable In place and completed.
Acceptable Good standard
Acceptable No issues raised.
Acceptable Clear and unobstructed.
Acceptable Suitable and sufficient.
Acceptable Displayed.
Acceptable Clear and unobstructed.
Acceptable In place.
6 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Comments Action Date
- -
- -
- -
- -
- -
- -
- -
-
-
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
-
-
- -
- -
- -
- -
- -
- -
Observation
Fire register [Site]
COSHH
Safe Storage
Hazardous Substance Register
MSDS Sheets Documented
Hand Tools/Plant/Transport
Hand Tools [PAT]
Plant
Transport Equipment
Excavation
Electricity
Acceptable In place.
Acceptable Assessments in place.
Acceptable No issues raised.
Acceptable In place and sufficient.
Acceptable Attached to assessments.
Acceptable No defects noted.
Acceptable PAT tested and in date.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable Good practice
Acceptable No issues raised.
Overhead Power Lines Not Applicable Not Applicable.
Underground Services
Acceptable No issues raised.
HV Electrical installation Not Applicable Not Applicable.
Working at Height
Ladders
Step Ladders
Mobile Scaffold Towers
Roof work
Mobile Elevated Working Platforms [MEWP]
Hoists
Mechanical Lifting
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable Clear and unobstructed.
Confined Space Not Applicable. Not Applicable.
Permit
Floor openings
Edge Protection
Signage
Safe working practices
Protective clothing /equipment
PPE-General
Acceptable No issues raised.
Acceptable No issues raised.
Acceptable in place where required.
Acceptable Relevant safety signage is in place.
Acceptable No issues raised.
Acceptable 5 points of PPE as per site rules.
Acceptable No issues raised.
7 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Action Date
Status Comments
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
-
-
- -
Observation Status
Manual handling
Environmental
Air Pollution
Water Pollution
Land Pollution
Noise Pollution
Dust Pollution
Acceptable No issues raised.
Acceptable No activities causing concern. - -
Acceptable No activities causing concern.
Acceptable No activities causing concern.
Acceptable No activities causing concern.
Acceptable No activities causing concern. - -
Acceptable Dust management throughout the project has improved, but will need to be monitored McLaughlin & Harvey Ltd Ongoing
Working over /adjacent to water Not Applicable. Not Applicable. - -
Roadwork's Not Applicable. Not Applicable.
Working over/adjacent to railways Not applicable Not Applicable.
8 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
Comments Action Date
- -
- -
-
-
-
-
- -
- -
Appendix 1 Photographs
9 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
10 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
11 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
12 2800_Eden Campus_ORSA Site Inspection_FJMK240524.docx
FH090-151015 appendix k
DAA CMT report
Architectural Progress Report _ 28th May 2024
Project UL Campus, Kingston Created By Alexander Cook
Job No 19064
Date 28/05/2023
Revision 01
1.0 Project Overview
Date 28/05/2023
Approved By Alastair Roberts
Date 28/05/2023
ļ§ DAA continue to develop & coordinate the Stage 5 detailed design of buildings A + B + C with McLH in line with the construction programme.
ļ§ DAA have started Snagging process to ensure De-snag condition in line with Program - Refer to the McLH Snagging Tracker for further details.
ļ§ R emaining planning conditions such as Bridge Link, Condition 03 & External Louvre ( NMA ) have been consented by RBKT.
2.0 Key Design Development/Deliverables
ļ§ DAA are attending project DTMās with McLH & the design team as well as organising specific design workshops with Structures, M+E, Facades, Building Control, Fire & BREEAM when required
ļ§ A s lead design DAA continue the coordination of BIM models & have begun circulat ing our Revit models on a bi-weekly basis following all BIM protocol to ensure the design team is fully informed & coordinated
ļ§ DAA issued architectural information that targets all pre-above ground planning conditions & continue to work with both McLH + FH to unlock the conditions. The CMT team continue to chase the progress of Condition 3 & associated comments
ļ§ DAA are attending detailed design workshops on the proposed External Works, landscaping, Internal walls , waterproofing, roofing , external f acades to ensure further coordination between consultants, the occupier team & funders.
ļ§ DAA continue to manage & present E xternal + Internal finishes samples to both the Unilever design team & RBKT for formal sign off. The design team are continuing to develop the faƧade detailed proposals with Clarkes & McLH through dedicated faƧade workshops & a re actively responding to RFIās to ensure the faƧades retains the original design intent + quality.
ļ§ DAA have attended site meetings + visits + snagging when required to review benchmark works on site, samples & detailed coordination issues.
3.0 Next Period / Key Decisions and Instructions Required
ļ§ Instruction required on all occupier variations + associated DAA fees on the following:
- Signage planning application.
Any Additional Occupier Variations
Architectural Progress Report _28th May 2024 ā Revision 01 UL Campus, Kingston 19064 Page 1 of 3
ļ§ Full understanding of any other new UL variations which could potentially affect the S tage 5 design programme is critical for avoiding redundant work.
4.0 Issued Documentation + Information.
ļ§ DAA have issued design sketches + Updated Stage 5 Design Packs for the following :
ļ§ MSCP Wayfinding
ļ§ MSCP Roller Shutter Proposals
ļ§ Entrance Link + BL Coordination
ļ§ External Lighting + CCTV TVR
ļ§ Blind Box design updates + coordination
ļ§ External Works + Site coordination ā Ramps / Stairs / Flood Voids / Railings ā A + B + C
ļ§ Fire Curtains + interface detailing ā Bridge Link
ļ§ RCPās + MEP coordination/Set out
ļ§ Service Yard elevations ā External Lourves
ļ§ Drylining Workshops + BWH coordination
ļ§ RAF construction detailing
ļ§ Area Drawings
ļ§ Roller Shutter Construction Issue
ļ§ Reception Screed Drawings + associated details
ļ§ Roof Package Updates
ļ§ Firestopping details ā A + B + C
ļ§ MSCP External Wall / Flood void / Blockwork
ļ§ BC Tracker Development
ļ§ FaƧade Coordination + Comments ā A + B
ļ§ Access + Security Strategy
ļ§ DAA have fully updated their Architectural folder on Viewpoint + associated TIDP which now contains all issued drawings / specifications / reports / design options / sketches through to end of February
ļ§ DAA have continued to attend BIM clash detection workshops when required & have always ensured that design development of Revit models are frequently issued following coordination workshops & key design changes/variations.
ļ§ DAA have responded to all required RFIās & provided comments via Viewpoint on all consultant drawings & design information.
Latest Stage 5 Car Park Architectural Information Issued within this period [Buildings C] :
ļ§ 13000 ā Floorbeds - A5
ļ§ 21000 ā External Walls + FaƧade Packages - A5
ļ§ 22000 ā Internal Walls ā A5
ļ§ 24000 ā Stairs - A5
ļ§ 25000 ā Cores - A5
ļ§ 2 7 000 ā Roof Package - A5
ļ§ 30000 ā GA Drawings - A5
ļ§ 34000 ā Metalwork - A5
ļ§ 35000 ā RCPs - A5
ļ§ 42000 ā Wall Finishes - A5
ļ§ 43000 ā Floor Finishes - A5
ļ§ 68000 ā Fire Strategy - A5
ļ§ 44000 ā Skirtings - A5
ļ§ 74000 ā Sanitaryware Package - A5
ļ§ Outline Finishes Specification
ļ§ External Door Schedule - A5
ļ§ Internal Door Schedule - A5
ļ§ NBS Specifications - A5
Architectural Progress Report _28th May 2024 ā Revision 01 UL Campus, Kingston 19064 Page 2 of 3
ļ§ External Roller Shutter Proposal - A5
ļ§ Floor beds + Gullies Changing village - A5
Latest Stage 5 Architectural Information Issued within this period [Buildings A + B] :
ļ§ 03000 ā GAās - A5 ā CAT A Omissions
ļ§ 04000 ā Ground Floor Setting Out + Slab Edge Set Out + Builders Works Penetrations - A5
ļ§ 13000 ā Floorbeds - A5
ļ§ 23000 - Thermal Zones - A5
ļ§ 21000 ā External Walls + FaƧade Packages - A5
ļ§ 22000 ā Internal Walls - A5
ļ§ 23000 ā Building Links ā Reception + Bridge - A5
ļ§ 24000 ā Stairs + Feature Stair Building B - A5
ļ§ 25000 ā Core Package - A5
ļ§ 27000 ā Roof Package - A5
ļ§ 31000 - External Door Schedule - A5
ļ§ 32000 ā Internal Door Schedule - A5
ļ§ 33000 ā RAF - A5
ļ§ 34000 ā Metalwork - A5
ļ§ 35000 ā RCPās - A5 ā CAT A Omissions
ļ§ 42000 ā Wall Finishes - A5 ā CAT A Omissions
ļ§ 43000 ā Floor Finishes ā A5 ā CAT A Omissions
ļ§ 44000 ā Skirtings ā A5 ā CAT A Omissions
ļ§ 68000 ā Fire Strategy - A5
ļ§ 74000 ā Sanitaryware Package - A5
ļ§ 80000 ā Areas - A5
ļ§ 90000 ā External Works - A5
ļ§ External Door Schedule ā A5
ļ§ Internal Door Schedule ā A5
ļ§ NBS Specifications ā A5
ļ§ External Shutter ā A5
ļ§ Lift Finishes + Lobby - A5
ļ§ Fire Stop Details + Fire Curtains - A5
Latest Contractors Instruction Issued within this period:
ļ§ CI 014 - CIRCLESLIDE DOORS
ļ§ CI 015 - BUILDING B FEATURE STAIR GLAZING INFILL
ļ§ CI 028 - CAT A Temp Measures
ļ§ CI 029 - Internal + External Doors
ļ§ CI 030 - Changing Places
ļ§ CI 031 - External Louvres
ļ§ CI 032 - Facade Lighting ā In progress
ļ§ CI 033 - GF Screed and Omission of RAF
ļ§ CI 034 - Blind Boxes
ļ§ CI 035 - Car Park Additional Work
ļ§ CI 036 - WC Grilles
ļ§ CI 037 - RAF Omission
ļ§ CI 038 - Building A Baby Change
ļ§ CI 039 - Car Park - Shower shelf
ļ§ CI 040 - Blind box
ļ§ CI 041 ā Doors ( CI 029 amendment s + CCTV ) In progress
ļ§ CI 042 - Lift Floor
ļ§ EAI 71 - Omission of Soap Dispenser
Architectural Progress Report _28th May 2024 ā Revision 01 UL Campus, Kingston 19064 Page 3 of 3
FH090-151015 appendix l
package review schedule
Architectural
Architectural Lifts (Internal finish) Lifts (Internal finish) RIBA 4
Architectural M10 Cement Base Levelling Wearing Screeds Technical Submittal RIBA 4 N/A
Architectural M60 Painting / Clear Finishing Technical Submittal RIBA 4 N/A
Architectural NIA Plans - Areas Building A & B RIBA 4 22/12/2022 24/01/2023 17 days 24/01/2023
Architectural Circleslide Curved Sliding Door Technical Submittal RIBA 5 N/A 13/10/2023 N/A 13/10/2023 02/11/2023
02/10/2023 B 02/10/2023 B 02/10/2023 B
package review schedule Project Honey 05/06/2024 issue date discipline package description design stage planned release date (programme dated xxxx) actual release date delta all developer occupier/ fund date received status given date received status given date received status given comments Architectural Ceilings Building C RIBA 4 N/A 26/11/2022 N/A 26/11/2022 15/12/2022 13/12/2022 23/12/2022 A 23/12/2022 A 23/12/2022 A All plans received 26/11/2022. Architectural Circulation Stairs Circulation Stairs Building A RIBA 4 25/08/2022 02/09/2022 6 days 02/09/2022 22/09/2022 20/09/2022 29/09/2022 B 29/09/2022 B 29/09/2022 B All plans received on 02/09/2022 Architectural External Door Schedule & Plans Building C RIBA 5 N/A 02/08/2023 N/A 02/08/2023 22/08/2023 18/08/2023 17/08/2023 B 17/08/2023 B 17/08/2023 B Architectural External Doors (tbc with Clarkes) External Doors (tbc with Clarkes) RIBA 4 06/10/2022 15/11/2022 28 days 15/11/2022 05/12/2022 01/12/2022 01/12/2022 B 29/11/2022 A/B 29/11/2022 B All plans received 15/11/2022 Architectural External Doors Plan Building C RIBA 5 N/A 07/11/2023 N/A 07/11/2023 27/11/2023 23/11/2023 01/12/2023 B 01/12/2023 B 01/12/2023 B Architectural External works External works RIBA 4 15/08/2022 16/08/2022 1 day 16/08/2022 05/09/2022 01/09/2022 14/09/2022 A 14/09/2022 A 14/09/2022 A Woodland ramp building B external works received 23/08/2022 Architectural FaƧade FaƧade RIBA 4 N/A 02/12/2022 N/A 02/12/2022 22/12/2022 20/12/2022 Not issued for CMT review. Architectural Feature Stair Feature Stair - Building B RIBA 4 N/A 26/09/2022 N/A 26/09/2022 14/10/2022 12/10/2022 09/11/2022 B 09/11/2022 B 09/11/2022 B All plans received 26/09/2022 Architectural Feature Stair Feature Stair Building A RIBA 4 08/12/2022 15/12/2022 5 days 15/12/2022 13/01/2023 11/01/2023 12/01/2023 B 12/01/2023 B 12/01/2023 B Architectural Fire Strategy Fire Strategy Building A + B RIBA 4 03/10/2022 11/10/2022 6 days 11/10/2022 31/10/2022 27/10/2022 14/11/2022 B 14/11/2022 B 14/11/2022 B p Mace agreed to downgrade HL status C to Status B on 21/11/2022 Architectural Floor Finishes Floor Finishes RIBA 4 05/09/2022 20/09/2022 11 days 20/09/2022 10/10/2022 06/10/2022 11/10/2022 B 11/10/2022 B 11/10/2022 B All plans received on 20/09/2022 Architectural Floor finishes Building C RIBA 4 N/A 26/11/2022 26/11/2022 15/12/2022 13/12/2022 03/01/2023 A 03/01/2023 A 03/01/2023 A
Floor
Door Stop
16/10/2023 N/A 16/10/2023 03/11/2023 01/11/2023 31/10/2023 A 31/10/2023 A 31/10/2023 A Architectural Green Wall Design Drawings RIBA 5 N/A 01/11/2023 N/A 01/11/2023 21/11/2023 17/11/2023 21/11/2023 A 21/11/2023 A 21/11/2023 A All plans received 20/11/2023. Architectural Internal lighting Block A + B calculations RIBA 4 N/A 08/09/2022 N/A 08/09/2022 28/09/2022 26/09/2022 13/10/2022 B 13/10/2022 B 13/10/2022 B All plans received on 08/09/2022
Architectural
Mounted
Sample Submittal RIBA 5 N/A
20/10/2022 13/12/2022 13/12/2022 11/01/2023 09/01/2023 22/12/2022 B 22/12/2022 B 22/12/2022 B
Internal Walls and ironmongery Internal Walls and ironmongery RIBA 4
RIBA 4 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 06/02/2023 A/B 06/02/2023 A/B 06/02/2023
Architectural K41 Raised Access Floors Technical Submittal
A/B
28/11/2022 28/11/2022 16/12/2022 14/12/2022 19/12/2022
19/12/2022
19/12/2022
A
A
A
25/01/2023 14/02/2023 10/02/2023 21/02/2023 A/B 21/02/2023 A/B 21/02/2023 A/B Received comments from Perkins and Will on 21/02/2023
25/01/2023 N/A
25/01/2023
25/01/2023 14/02/2023 10/02/2023 21/02/2023 A/B 21/02/2023 A/B 21/02/2023
Received comments from Perkins and Will on 21/02/2023
26/11/2022
26/11/2022 15/12/2022 13/12/2022 23/12/2022
23/12/2022
23/12/2022
N/A
A/B
Architectural Metalwork Building C RIBA 4 N/A
N/A
A
A
A
02/11/2022 31/10/2022 14/11/2022 B 14/11/2022 B 14/11/2022 B All plans received 13/10/2022
Architectural Metalwork (Plantroom steel) (tbs with Clarkes) Metalwork (Plantroom steel?) (tbs with Clarkes) RIBA 4 13/10/2022 13/10/2022 0 days 13/10/2022
Architectural Metalworks Design Building A & B Stairs RIBA 5 N/A 16/11/2023 N/A 16/11/2023 06/12/2023 04/12/2023
13/02/2023 09/02/2023 16/03/2023 A 16/03/2023 A 16/03/2023 A
Raised Access Floor Raised Access Floor RIBA 4 13/10/2022 14/10/2022 1 day 14/10/2022 03/11/2022 01/11/2022 07/11/2022 B 07/11/2022 B 07/11/2022 B All plans received 14/10/2022 Architectural Roof Roof RIBA 4 06/10/2022 07/10/2022 1 day 07/10/2022 27/10/2022 25/10/2022 09/11/2022 A 09/11/2022 A 09/11/2022 A All plans received 07/10/2022 Architectural Roof Completions Roof Details RIBA 4 06/10/2022 07/10/2022 1 day 07/10/2022 27/10/2022 25/10/2022 09/11/2022 A 09/11/2022 A 09/11/2022 A All plans received 07/10/2022 Architectural Sanitary Building C RIBA 4 13/10/2022 30/11/2022 34 days 30/11/2022 20/12/2022 16/12/2022 03/01/2023 B 03/01/2023 B 03/01/2023 B Architectural sanitary Building A + B RIBA 4 N/A 24/11/2022 N/A 09/01/2023 27/01/2023 25/01/2023 09/01/2023 B 09/01/2023 B 09/01/2023 B All plans received 24/11/2022 Architectural Site layout and landscape plan Site layout and landscape plan RIBA 4 N/A 22/11/2022 N/A 22/11/2022 12/12/2022 08/12/2022 22/12/2022 B 22/12/2022 B 22/12/2022 B All plans received 21/10/2022 Architectural Skirting Skirting RIBA 4 08/08/2022 09/08/2022 1 day 09/08/2022 30/08/2022 25/08/2022 30/08/2022 A 30/08/2022 A 25/08/2022 A 11th floor skirting plan received on 10th August Architectural Stairs Building C RIBA 4 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 12/01/2023 B 12/01/2023 B 12/01/2023 B Architectural Sub Floors Sub Floors RIBA 4 15/09/2022 31/08/2022 -11 days 31/08/2022 06/10/2022 04/10/2022 11/10/2022 B 11/10/2022 B 11/10/2022 B All plans received on 31/08/2022 Architectural Subfloors Building C RIBA 4 N/A 26/11/2022 N/A 26/11/2022 15/12/2022 13/12/2022 23/12/2022 A 23/12/2022 A 23/12/2022 A Architectural Wall Finishes Wall Finishes RIBA 4 08/08/2022 09/08/2022 1 day 09/08/2022 30/08/2022 25/08/2022 30/08/2022 A 30/08/2022 A 25/08/2022 A All plans received on 09/08/2022 Architectural Wall finishes Building C RIBA 4 N/A 26/11/2022 N/A 26/11/2022 15/12/2022 13/12/2022 14/01/2023 B 14/01/2023 B 14/01/2023 B Architectural Way finding strategy Ground Floor C RIBA 4 N/A 12/11/2022 N/A 12/11/2022 01/12/2022 29/11/2022 09/12/2022 B 09/12/2022 B 09/12/2022 B All plans received 12/11/2022 Architectural Woodland walk- GA Woodland walk- GA RIBA 4 N/A 22/11/2022 N/A 22/11/2022 12/12/2022 08/12/2022 03/01/2023 B 03/01/2023 B 03/01/2023 B All plans received 21/10/2022
Soffit Building A Details & Sections RIBA 5
05/02/2024 N/A 05/02/2024 23/02/2024 21/02/2024 21/02/2024 B 21/02/2024 B 21/02/2024 B Architectural Building A FaƧade Plan Details FaƧade details RIBA 5 N/A 16/09/2023 N/A 16/09/2023 05/10/2023 03/10/2023
Architectural
Architectural
N/A
20/11/2023 A 20/11/2023 A
A
01/12/2023 08/01/2024 A 08/01/2024 A 08/01/2024 A Architectural
Fire Strategy Report Report RIBA
13/12/2023 11/12/2023 18/12/2023 B 18/12/2023 B 18/12/2023 B Architectural Fire Strategy Report RIBA 4 N/A 24/01/2023 N/A 24/01/2023 13/02/2023 09/02/2023 08/02/2023 A/B 08/02/2023 A/B 08/02/2023 A/B Architectural Fire Strategy Site Wide Plan RIBA 4 N/A 14/02/2023 N/A 14/02/2023 06/03/2023 02/03/2023 21/02/2023 B 21/02/2023 B 21/02/2023 B Architectural yp y g Ceilings Architectural Technical Submittal RIBA 4 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2023 B 12/01/2023 B 31/01/2023 B Closed out on 31/01/2023 Architectural K20 Timber Board Flooring Architectural Technical Submittal RIBA 5 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 14/03/2023 B 14/03/2023 B 14/03/2023 B Awaiting comments. comments received/ status given developer occupier fund response required by https://francishunter-my.sharepoint.com/personal/kyra_bosompem_francishunter_co_uk/Documents/Documents/Project Honey/Package Review Schedule/Project Honey Package Review Schedule 231120
31/10/2023
20/11/2023
Architectural External Works Site Wide Woodland Walk Path RIBA 5 N/A 15/11/2023 N/A 15/11/2023 05/12/2023
FaƧade
4 23/11/2023 23/11/2023 23/11/2023
MEP
MEP
MEP
MEP
MEP
MEP
MEP Below ground drainage Below ground drainage RIBA 3 N/A 13/09/2022 N/A 13/09/2022 03/10/2022 29/09/2022 05/10/2022
MEP Below ground drainage Construction details RIBA 3 N/A 13/09/2022 N/A 13/09/2022 03/10/2022 29/09/2022
MEP BMS description of operations BMS description of operations RIBA 3 14/10/2022
MEP
N/A 11/04/2024 N/A 11/04/2024 01/05/2024 29/04/2024 18/04/2024 A 18/04/2024 A 18/04/2024 A All plans received 03/10/2022
MEP Containment Specification RIBA 3 N/A 10/10/2022 N/A 10/10/2022 28/10/2022 26/10/2022 20/10/2022 B 20/10/2022 B 20/10/2022 B All plans received 10/10/2022
MEP Containment Layouts (Building A) RIBA 3 21/11/2022 11/11/2022 -6 days 11/11/2022 01/12/2022 29/11/2022 12/12/2022 B 12/12/2022 B 12/12/2022 B All plans received 11/11/2022.
MEP Containment Layouts (Building C) RIBA 4 N/A 09/03/2023 N/A 31/07/2023 18/08/2023 16/08/2023 29/08/2023 B 29/08/2023 B 29/08/2023 B
MEP Containment Layouts Building A & B RIBA 5 N/A 23/04/2024 N/A 23/04/2024 13/05/2024 09/05/2024 07/05/2024 A/B 07/05/2024 A/B 07/05/2024 A/B Status C given on theM5 Floor.
MEP Containment Layouts Building C RIBA 3 05/12/2022 05/12/2022 0 days 05/12/2022 23/12/2022 21/12/2022
MEP Controls (BMS) Description of operations RIBA 3 18/07/2022 14/10/2022 88 days 14/10/2022 03/11/2022 01/11/2022 04/11/2022 B 02/11/2022 B 04/11/2022 B All plans received 14/10/2022
MEP Cooling (CHW) system Building A schematic RIBA 5
MEP Disabled Refuge Alarm System Alarm System RIBA 4 N/A 30/05/2023 N/A 30/05/2023 19/06/2023 15/06/2023 08/06/2023 A
MEP Disabled refuge schematic Building
05/04/2023 C
package review schedule Project Honey 05/06/2024 issue date discipline package description design stage planned release date (programme dated xxxx) actual release date delta all developer occupier/ fund date received status given date received status given date received status given comments comments received/ status given developer occupier fund response required by Architectural Lift Finishes Schedule Building C RIBA 4 N/A 13/04/2023 N/A 13/04/2023 03/05/2023 01/05/2023 Architectural Link Bridge Elevations, Sections and Details RIBA 4 N/A 14/05/2024 N/A 14/05/2024 03/06/2024 30/05/2024 04/06/2024 B 04/06/2024 B 04/06/2024 B Architectural Balustrade Calculations Technical Submittal RIBA 5 N/A 20/01/2024 N/A 20/01/2024 08/02/2024 06/02/2024 05/02/2024 C 05/02/2024 C 05/02/2024 C Architectural Section details Underside Building B RIBA 4 N/A 18/01/2024 N/A 18/01/2024 07/02/2024 05/02/2024 05/02/2024 B 05/02/2024 B 05/02/2024 B Architectural M40 stone /concrete/quarry/ ceramic tiling / Architectural Technical Submittal RIBA 4 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2023 B 12/01/2023 B 31/01/2023 B Closed out on 31/01/2023 Architectural Maple Drawings Building C RIBA 4 N/A 10/05/2023 N/A 10/05/2023 30/05/2023 26/05/2023 02/05/2023 A/B 02/05/2023 A/B 02/05/2023 A/B Received all plans on the 10/05/2023. Architectural Panel Setting Out Plans Building A & B RIBA 4 N/A 24/01/2023 N/A 24/01/2023 13/02/2023 09/02/2023 14/02/2023 B 14/02/2023 B 14/02/2023 B All plans received. Architectural Sample Sheets Building C RIBA 5 N/A 24/11/2023 N/A 24/11/2023 14/12/2023 12/12/2023 05/02/2024 A/B 05/02/2024 A/B 05/02/2024 A/B Awaiting comments on sample approval form 26, 27 and 49. Architectural Stick Curtain Wall Building A & B RIBA 4 N/A 29/06/2023 N/A 29/06/2023 19/07/2023 17/07/2023 21/07/2023 B 21/07/2023 B 21/07/2023 B All plans received. Architectural U- Value and Condensation Risk Assessment Building B Level 02 Unitised Facade Technical Submittal RIBA 5 N/A 19/06/2023 N/A 19/06/2023 07/07/2023 05/07/2023 13/07/2023 C 13/07/2023 C 13/07/2023 C Architectural Z20 Fixings and Adhesives Architectural Technical Submittal RIBA 5 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2022 B 12/01/2023 A 31/01/2022 B Closed out on 31/01/2023 Architectural Z22 Sealants Architectural Technical Submittal RIBA 4 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2022 B 12/01/2023 B 31/01/2023 B Closed out on 31/01/2023 Architectural Z31 Powder Coatings Architectural Technical Submittal RIBA 4 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2023 B 31/01/2023 B 31/01/2023 B Closed out on 31/01/2023 Architectural Z33 Anodizing Architectural Technical Submittal RIBA 5 N/A 11/01/2023 N/A 11/01/2023 31/01/2023 27/01/2023 31/01/2023 B 12/01/2023 B 31/01/2023 B Closed out on 31/01/2023 Architectural Floor finishes Building C RIBA 5 N/A 15/12/2023 N/A 15/12/2023 12/01/2024 10/01/2024 Removed from CMT Workflow. Architecture Thermal Zones Thermal Zone package for Buildings A and B RIBA 4 07/07/2022 08/07/2022 1 day 08/07/2022 27/07/2022 26/07/2022 27/07/2022 B 27/07/2022 B 27/07/2022 B All plans received on 08/07/2022
Above Ground Drainage Building C RIBA 3 N/A 27/01/2023 N/A 27/01/2023 16/02/2023 14/02/2023 15th floor rejected. MCLH & Delivery team review status B given. MEP Above Ground Drainage Building B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 18/01/2023 B Awaiting comments from developer and fund.
MEP
13/01/2023 18/01/2023 B Awaiting comments from developer and fund.
Above Ground Drainage Building A RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023
Above ground drainage stack positions Building C RIBA 3 N/A 20/12/2022 N/A 20/12/2022 19/01/2023 17/01/2023 17/01/2023 B 17/01/2023
B 17/01/2023 B
A 18/03/2024 A
Above ground drainage stack positions Building C RIBA 5 N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 15/03/2024 A 18/03/2024
ABS Pipe and Fittings for Condensate Drainage Technical Submittal RIBA 5 N/A 12/03/2024 N/A 12/03/2024 01/04/2024 28/03/2024 20/03/2024 A/B 20/03/2024 A/B 20/03/2024 A/B
17/04/2023
17/04/2023 05/05/2023 03/05/2023 24/04/2023 B 24/04/2023 B 24/04/2023 B
MEP Alarm Gong Technical Submittal RIBA 4 N/A
N/A
44945 17/01/2023 16/01/2023 B 16/01/2023 B 16/01/2023 B
Ancillary ventilation schematic Building B RIBA 3 N/A 44915 N/A 44915
20/10/2022 B 20/10/2022 B 20/10/2022
ASHRAE Modelling ASHRAE Modelling RIBA 3 N/A 25/09/2022 N/A 25/09/2022 13/10/2022 11/10/2022
B All plans received 25/09/2022
B
05/10/2022 B 05/10/2022 B All plans received on 31/08/2022
B
B
05/10/2022
05/10/2022
05/10/2022 B All plans received on 13/09/2022
14/10/2022 0 days 14/10/2022 03/11/2022 01/11/2022 04/11/2022 B 04/11/2022 B 04/11/2022 B All plans received on 14/10/2023
Cable connections Cable connections
3
03/10/2022
03/10/2022 21/10/2022 19/10/2022 19/10/2022 B 19/10/2022 B 19/10/2022 B All plans received 03/10/2022
RIBA
N/A
N/A
Water Pump Technical Submittal RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 21/11/2023 B
Building A & B RIBA 3
20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 20/01/2023 B 20/01/2023 B 20/01/2023 B
Building B RIBA 3 N/A 05/12/2022 05/12/2022 23/12/2022 21/12/2022 04/01/2023 B 04/01/2023 B 04/01/2023 B
Containment
calculations RIBA 5
MEP Chilled
MEP Chilled water schematic
N/A
MEP Cold Water Booster Tank Room
MEP
Sizing
B
B
08/12/2022
13/02/2023
08/12/2022 B
days
29/03/2024
A 08/04/2024 B MEP
Building
calculationsBuilding A, B & C
5
29/04/2024
29/04/2024 17/05/2024
02/05/2024 A 02/05/2024 A
N/A 13/03/2024 -43
13/03/2024 02/04/2024
14/03/2024
Cooling load calculations -
A, B & C Cooling load and heat loss
RIBA
N/A
N/A
15/05/2024
02/05/2024 A All plans received 29/04/2024 MEP Design report Design report RIBA 3 23/11/2022 20/02/2023 60 days 21/02/2023 13/03/2023 09/03/2023 05/04/2023 C 05/04/2023 C
C
3
22/03/2023 C 22/03/2023 C 22/03/2023 C MEP Disabled
schematic Building
B
B
B
B MEP Domestic
Building
B
https://francishunter-my.sharepoint.com/personal/kyra_bosompem_francishunter_co_uk/Documents/Documents/Project Honey/Package Review Schedule/Project Honey Package Review Schedule 231120
RIBA
N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023
refuge
A & B RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 08/12/2022
MEP Disabled Toilet Alarm System Alarm System RIBA 4 N/A 30/05/2023 N/A 30/05/2023 19/06/2023 15/06/2023 02/06/2023
01/08/2023
01/08/2023
schematics
A &
RIBA 4 N/A 15/03/2023 N/A 15/03/2023 04/04/2023 31/03/2023 06/06/2023 C 06/06/2023 C 06/06/2023 C
MEP Domestic Services Building B RIBA 5 N/A 28/08/2023 N/A 28/08/2023 15/09/2023 13/09/2023 22/09/2023
MEP Drainage Layout Building B & C RIBA 4 N/A 14/04/2023 N/A 14/04/2023 04/05/2023 02/05/2023 12/05/2023 B 02/05/2023 B 12/05/2023 B
MEP Drainage Layout Building C RIBA 5 N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 15/03/02024 A/B 18/03/2024 A/B 18/03/2024 A/B Status B given on the following floors - 7th floor
MEP Dry Riser Building A RIBA 4 N/A 23/05/2023 N/A 23/05/2023 12/06/2023 08/06/2023 20/06/2023 A/B 07/06/2023 A/B 20/06/2023 A/B
MEP Dry Riser Building A + B RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 10/01/2023 B 10/01/2023 B 10/01/2023 B
MEP Dry Riser Building A & B RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 01/12/2023 A/B 14/12/2023 A/B 14/12/2023 A/B
MEP Dry Riser Building C RIBA 4 N/A 12/06/2023 N/A 12/06/2023 30/06/2023 28/06/2023 20/06/2023 B 20/06/2023 B 20/06/2023 B
MEP Dry Riser Building C RIBA 3 N/A 14/02/2022 N/A 14/02/2022 04/03/2022 02/03/2022 17/03/2023 B 13/03/2023 B 13/03/2023 B
MEP Electrical riser Drawings Building A + B RIBA 3 N/A 11/11/2022 N/A 11/11/2022 01/12/2022 29/11/2022 11/11/2022 C C C All plans received 11/11/2022. Reason rejected: Provide LV schematics.
MEP Electrical riser Drawings Building A + B+C RIBA 4 N/A 15/03/2023 N/A 15/03/2023 04/04/2023 31/03/2023 30/05/2023 C 30/05/2023 C 30/05/2023 C
MEP Electrical Vehicle charging Electrical Vehicle charging RIBA 3 N/A 27/03/2023 N/A 27/03/2023 14/04/2023 12/04/2023 31/05/2023 C 31/05/2023 C 31/05/2023 C
MEP Emergency Exit Light Fitting Light Fitting RIBA 4 N/A 30/05/2023 N/A 30/05/2023 19/06/2023 15/06/2023 02/06/2023 A 02/06/2023 A 02/06/2023 A
MEP Energy statement Energy statement RIBA 3 N/A 12/09/2022 N/A 12/09/2022 30/09/2022 28/09/2022 20/10/2022 B 20/10/2022 B 20/10/2022 B All plans received on 12/09/2023
MEP Exterior Lighting Design Site Wide RIBA 4 N/A 15/05/2023 N/A 15/05/2023 02/06/2023 31/05/2023 01/06/2023 B 01/06/2023 B 01/06/2023 B
MEP Fire Alarm Building A Layout RIBA 5 N/A 04/12/2023 N/A 04/12/2023 22/12/2023 20/12/2023 21/12/2023
MEP Fire Alarm and Security Building A Layouts RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 22/05/2023 B 09/06/2023 B 22/05/2023 B
MEP Fire Alarm and Security Building B RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 22/05/2023 B 09/06/2023 B 22/05/2023 B
MEP Fire Alarm and Security Building A, B & C Layouts RIBA 5 N/A 04/12/2023 N/A 04/12/2023 22/12/2023 20/12/2023 06/12/2023 A/B 21/12/2023 A/B 21/12/2023 A/B
MEP Fire alarm schematic Building B RIBA 5 N/A 17/10/2023 N/A 17/10/2023 06/11/2023 02/11/2023 08/11/2023 B 08/11/2023 B 08/11/2023 B
MEP Fire alarm schematic Building C RIBA 5 N/A 17/10/2023 N/A 17/10/2023 06/11/2023 02/11/2023 08/11/2023 B 16/11/2023 B 16/11/2023 Awaiting Occupier and Fund comments.
MEP Light Fittings Site wide RIBA 5 N/A 14/05/2024 N/A 14/05/2024 03/06/2024 30/05/2024 05/06/2024 A/B 05/06/2024 A/B 05/06/2024 A/B
MEP Flow Meter Technical Submittal RIBA 4 N/A 17/04/2023 N/A 17/04/2023 05/05/2023 03/05/2023 24/04/2023 B 24/04/2023 B 24/04/2023
MEP
MEP
MEP
0 days 20/12/2022 09/01/2023 05/01/2023 All plans received 03/11/2022 MEP Lighting and emergency lighting Building B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 09/01/2023 05/01/2023 18/01/2023 B 18/01/2023 B 18/01/2023 B All plans received.
MEP Lighting Layout Building A RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 02/06/2023 A/B 02/06/2023 A/B 02/06/2023 A/B
MEP Lighting Layout Building B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 18/01/2023 B 18/01/2023 B 18/01/2023 B All packages received.
MEP Lighting Layout Building A, B, & C RIBA 5 N/A 15/01/2024 N/A 15/01/2024 02/02/2024 31/01/2024 02/02/2024 B
MEP Lightning protection Layouts Building C RIBA 4 N/A 02/05/2023 N/A 02/05/2023 22/05/2023 18/05/2023 31/05/2023 B 31/05/2023 B 31/05/2023 B Status C received on 13/12/2022. Revision plans uploaded on 16/02/2023.
MEP Lightning protection Layouts Building C RIBA 5 N/A 12/03/2024 N/A 12/03/2024 01/04/2024 28/03/2024 20/03/2024 B 20/03/2024 B 20/03/2024 B
MEP Lightning protection Drawings (Building A + B GF and roof) RIBA 3 N/A 16/02/2023 N/A 16/02/2023 08/03/2023 06/03/2023 All plans received 11/11/2022. Previous Plans were given status C on 21/11/2022. Revisions received 16/02/2022.
MEP
package review schedule Project Honey 05/06/2024 issue date discipline package description design stage planned release date (programme dated xxxx) actual release date delta all developer occupier/ fund date received status given date received status given date received status given comments comments received/ status given developer occupier fund response required by MEP Domestic schematics Building A & B RIBA 3 05/11/2022 03/11/2022 - 2 days 03/11/2022 23/11/2022 21/11/2022 18/11/2022 C 18/11/2022 C 18/11/2022 C Status C received. MEP Domestic schematics Building C RIBA 3 05/11/2022 05/12/2022 0 days 05/12/2022 23/12/2022 21/12/2022 16/01/2023 C 16/01/2023 C 16/01/2023 C Status C received MEP Domestic Schematics Building C RIBA 5 N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 21/03/2024 C 21/03/2024 C 21/03/2024 C MEP Domestic Services Layouts Building A & B RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 02/06/2023 C 22/06/2023 C 22/06/2023 C
Domestic services Layouts - Building A + B
3
C
MEP
RIBA
N/A 17/11/2022 N/A 17/11/2022 07/12/2022 05/12/2022
C C Status C received
MEP Domestic Services Building A & B Layout RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 20/06/2023 C 20/06/2023 C 20/06/2023 C
B
B
B
22/09/2023
22/09/2023
B 18/01/2023 B
B
MEP Domestic tank schematic Building A & B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 02/02/2023
02/02/2023
All plans received 03/11/2022
Domestic water
systems
3
days 03/11/2022 23/11/2022 21/11/2022 All plans received
MEP Domestic water (H&C) systems Schedules RIBA 3 26/10/2022 03/11/2022 6 days 03/11/2022 23/11/2022 21/11/2022
MEP
(H&C)
Drawings RIBA
05/11/2022 03/11/2022 0
03/11/2022
B 20/10/2022 B 20/10/2022 B All plans received 25/09/2022
MEP Domestic water (H&C) systems Design and Calculations RIBA 3 26/09/2022 25/09/2022 -1 day 25/09/2022 13/10/2022 11/10/2022 20/10/2022
MEP Drainage Layout Building A RIBA 4 N/A 14/04/2023 N/A 23/05/2023 23/05/2023 08/06/2023 12/06/2023 B 07/06/2023 B 20/06/2023 B
B
Foul Drainage Diagrammatic Building C RIBA 4 N/A 02/05/2023 N/A 02/05/2023 22/05/2023 18/05/2023 12/05/2023 A 19/05/2023 B 19/05/2023 B
B
Foul Drainage Schematic Building A RIBA 4 N/A 03/04/2023 N/A 03/04/2023 21/04/2023 19/04/2023 11/04/2023
02/05/2023 B 02/05/2023 B
B
B
Generator Technical Submittal RIBA 5 N/A 12/03/2024 N/A 12/03/2024 01/04/2024 28/03/2024 20/03/2024
20/03/2024 B 20/03/2024
schematic Site wide
3
05/12/2022
05/12/2022 23/12/2022 21/12/2022 08/12/2022 B 08/12/2022 B 08/12/2022 B
Generator Exhaust Flue Systems Technical Submittal RIBA 5 N/A 15/12/2023 N/A 15/12/2023 04/01/2024 02/01/2024 21/03/2024 A 21/01/2024 A 21/01/2024 A
Grooved NRV Technical Submittal RIBA 4 N/A 17/04/2023 N/A 17/04/2023 05/05/2023 03/05/2023 24/04/2023 B 01/05/2023 A 24/04/2023 B
system Building A schematic
3
days
20/01/2023 B Awaiting comments from developer and fund. MEP Lighting and emergency lighting Building A, B & C Layouts RIBA 3 02/11/2022 20/12/2022 0 days 25/11/2022 15/12/2022 13/12/2022 08/12/2022 B 08/12/2022 B 08/12/2022 B Awaiting comments from all parties for Building C - GF Lighting Layout and Building C - M0 Lighting Layout. MEP Lighting and emergency lighting Drawings building B RIBA 3 05/11/2022 20/12/2022
MEP Generator controls
RIBA
N/A
N/A
MEP
MEP
MEP Heating (LTHW)
RIBA
22/10/2022 20/12/2022 0
20/12/2022 19/01/2023 17/01/2023
Building
31/05/2023 B 31/05/2023 B
MEP Lightning protection
B RIBA 3 N/A 20/02/2023 N/A 20/02/2023 10/03/2023 08/03/2023
31/05/2023 B
Lightning protection
design
3
10/10/2022 21 days 10/10/2022 28/10/2022 26/10/2022 21/10/2022 B 20/10/2022 B
All plans received 10/10/2022. Roof and GF drawings received 11/11/2022 MEP Low temperature hot water schematic Building A + B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 18/01/2023 B Awaiting comments. MEP Low temperature hot water schematic Building A RIBA 5 N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 14/03/2024 A/B 08/04/2024 A/B 08/04/2024 A/B MEP LTHW Pump Technical Submittal RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 22/11/2023 B MEP Luminaire Specification Initial load assessment calculations RIBA 5 N/A 09/12/2022 09/12/2022 06/01/2023 04/01/2023 13/12/2022 B MEP LV & LV life Safety Schematic Building A RIBA 5 N/A 15/01/2024 N/A 15/01/2024 02/02/2024 31/01/2024 19/02/2024 C 19/02/2024 C 19/02/2024 C MEP LV & LV life Safety Schematic Building C RIBA 3 04/11/2022 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 07/02/2023 B 07/02/2023 B 07/02/2023 B MEP LV Power Switch Room Schematics RIBA 3 02/11/2022 03/11/2022 0 days 03/11/2022 23/11/2022 21/11/2022 All plans received 03/11/2022 MEP LV Power Switch Room Schematics (Building C) RIBA 3 04/11/2022 19/01/2023 10 days 19/01/2023 08/02/2023 06/02/2023 14/02/2023 C 14/02/2023 C 14/02/2023 C All plans received 18/11/2022 MEP LV Switchboard SB-OC Building C RIBA 5 N/A 12/03/2024 N/A 12/03/2024 01/04/2024 28/03/2024 20/03/2024 B 20/03/2024 B 20/03/2024 B https://francishunter-my.sharepoint.com/personal/kyra_bosompem_francishunter_co_uk/Documents/Documents/Project Honey/Package Review Schedule/Project Honey Package Review Schedule 231120
Drawings and
RIBA
08/09/2022
21/10/2022 B
MEP Potable Cold Water Storage Building A,B & C RIBA 4 N/A 17/07/2023 N/A 17/07/2023 04/08/2023 02/08/2023
MEP Pump House Building B - Level 00 RIBA 4 N/A 31/08/2023 N/A 31/08/2023 20/09/2023 18/09/2023 27/11/2023 A 27/11/2023 A 27/11/2023 A
MEP Pump House Building B - Level 00 RIBA 3 N/A 19/01/2023 N/A 19/01/2023 08/02/2023 06/02/2023 06/02/2023 B
MEP PV PV RIBA 3 N/A 25/09/2022 N/A 25/09/2022 13/10/2022 11/10/2022 25/09/2022 C 25/09/2022 C 25/09/2022 C All plans received 25/09/2022. Status C was received
MEP QAHV Sanitary Hot Water Pump Building C RIBA 5 N/A 17/07/2023 N/A 17/07/2023 04/08/2023 02/08/2023 14/08/2023 C 16/08/2023
MEP Rainwater diagrammatic Building C RIBA 4 N/A 02/05/2023 N/A 02/05/2023 22/05/2023 18/05/2023 12/05/2023 A 19/05/2023 B 19/05/2023 B
MEP Rainwater drainage schematic Building A & B RIBA 4 N/A 03/04/2023 N/A 03/04/2023 21/04/2023 19/04/2023 11/04/2023 B 02/05/2023 B 02/05/2023 B
MEP RD102 Sprinkler Specification RIBA 4 N/A 31/03/2023 N/A 31/03/2023 20/04/2023 18/04/2023 11/04/2023 A 20/06/2023 A 20/06/2023 A
MEP Sanitaryware Technical submittal RIBA 5 N/A 12/01/2024 N/A 12/01/2024 01/02/2024 30/01/2024 13/02/2024 B 22/02/2024 B 22/02/2024 B
MEP Shower Channel Gullies Technical Submittal RIBA 4 N/A 14/06/2023 N/A 14/06/2023 04/07/2023 30/06/2023 30/06/2023 B
MEP Site Utilities Incoming Services Plans RIBA 4 N/A 11/09/2023 N/A 11/09/2023 29/09/2023 27/09/2023 02/10/2023 C 02/10/2023 C 02/10/2023 C Status B given by MCLH and closed out on 22/02/2023.
MEP Site Wide Generator Controls Schematic RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 19/12/2023 B 19/12/2023 B 19/12/2023 B
MEP Small Power and Data Layouts (Building C) RIBA 4 N/A 12/06/2023 N/A 12/06/2023 30/06/2023 28/06/2023 29/08/2023 B 29/08/2023 B 29/08/2023 B All plans received 12/06/2023.
MEP Small power and data Layouts (building C) RIBA 3 N/A 18/11/2022 N/A 18/11/2022 08/12/2022 06/12/2022 08/12/2022 B 13/02/2023 B 08/12/2022 B All plans received 18/11/2022.
MEP Small power and data Layouts (building A + B) RIBA 3 N/A 25/11/2022 N/A 25/11/2022 15/12/2022 13/12/2022 15/12/2022 B 15/12/2022 B 15/12/2022 B All plans received 25/11/2022
MEP Small power layout Building A & B RIBA 4 N/A 23/03/2023 N/A 23/03/2023 12/04/2023 10/04/2023 08/06/2023 B 07/06/2023 B 08/06/2023 B
MEP Small power layout Building B RIBA 5 N/A 23/04/2024 N/A 04/12/2023 22/12/2023 20/12/2023 06/12/2023 B 20/12/2023 B 20/12/2023 B Statuc C given on reuploaded ground floor drawing on 07/05/2024.
MEP Small power layout Building A RIBA 5 N/A 04/03/2024 N/A 04/03/2024 22/03/2024 20/03/2024
MEP Smoke Ventilation System Design RIBA 4 N/A 24/08/2023 N/A 24/08/2023 13/09/2023 11/09/2023 28/11/2023 C 28/11/2023 C 28/11/2023 C Status C given to allow Halsion to reupload updated drawings.
MEP Smoke Ventilation System Wiring Schematic Building A, B & C RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 22/11/2023 C 22/11/2023 C 22/11/2023 C Status C given to allow Halsion to reupload updated drawings.
MEP Sprinkler and Dry Riser Mains Layout Building A +B RIBA 4 N/A 19/07/2023 NA 19/07/2023 08/08/2023 04/08/2023 24/07/2023 A 16/08/2023 A 16/08/2023 A
MEP Sprinkler Block Plan Building A & B RIBA 4 N/A 06/04/2023 N/A 06/04/2023 26/04/2023 24/04/2023 24/04/2023 B 02/05/2023 B 02/05/2023 B awaiting UL response.
MEP Sprinkler Protection Building A & B RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 21/12/2023 A/B 21/12/2023 A/B 21/12/2023 A/B
MEP Sprinkler protection Building B RIBA 3 N/A 25/11/2022 N/A 25/11/2022 15/12/2022 13/12/2022 03/01/2023 A/B 03/01/2023 A/B 03/01/2023 A/B
MEP Sprinkler protection Layouts Building A RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 14/12/2022 C 14/12/2022 C 14/12/2022 C Status C received
MEP Sprinkler protection RCP Layouts Building A RIBA 3 N/A 03/11/2022 N/A 03/11/2022 23/11/2022 21/11/2022 10/01/2023 B 10/01/2023 B 10/01/2023 B Awaiting comment from occupier for Level 01 Sprinkler Protection Layout.
MEP Sprinkler Protection Pipework Layout Building B RIBA 4 N/A 07/08/2023 NA 07/08/2023 25/08/2023 23/08/2023 14/08/2023 B 29/08/2023 B 29/08/2023 B Status C given to Level 1 on 28/11/2023.
MEP Sprinkler protection RCP layout Building B RIBA 5 N/A 23/04/2024 N/A 23/04/2024 13/05/2024 09/05/2024 30/04/2024 A 30/04/2024 A 30/04/2024 A
MEP Sprinkler protection RCP layout Building A RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 06/12/2022 A Revisions uploaded on 27/01/2023, awaiting comments.
MEP Sprinkler protection RCP layout Building A & B RIBA 4 N/A 15/05/2023 N/A 15/05/2023 02/06/2023 31/05/2023 30/05/2023 B 02/06/2023 B 02/06/2023 B
MEP Sprinkler protection RCP layout Building B RIBA 3 N/A 06/12/2022 N/A 06/12/2022 26/12/2022 22/12/2022 16/01/2023 A/B 16/01/2023 A/B 16/01/2023 A/B All plans received 06/12/2022
MEP Sprinkler riser Building A + B RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 06/01/2023 B 04/01/2023 B 04/01/2023 B
MEP Sprinkler riser Building A +B RIBA 4 N/A 12/06/2023 N/A 12/06/2023 30/06/2023 28/06/2023 20/06/2023 A 16/08/2023 A 16/08/2023 A
MEP Sprinkler Riser Building A & B RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 21/12/2023 A 21/12/2023 A 21/12/2023 A
MEP Sprinkler Schematic Layout RIBA 3 N/A 20/02/2023 N/A 21/02/2023 13/03/2023 09/03/2023 29/06/2023 B 29/06/2023 B 29/06/2023 B
MEP Sprinkler Schematic Layout Site Wide RIBA 4 N/A 06/04/2023 N/A 06/04/2023 26/04/2023 24/04/2023 24/04/2023 B 02/05/2023 B 02/05/2023 B
MEP Sprinkler system System Design RIBA 3 02/11/2022 03/11/2022 0 days 03/11/2022 23/11/2022 21/11/2022 All plans received 03/11/2022
MEP Sprinkler Tanks Technical Submittal RIBA 4 N/A 14/06/2023 N/A 14/06/2023 04/07/2023 30/06/2023 30/06/2023 A/B 30/06/2023 A/B 30/06/2023 A/B
MEP Stage 4 Design Report MEP Stage 4 Report RIBA 4 N/A 15/03/2023 N/A 15/03/2023 04/04/2023 31/03/2023 29/08/2023 C 29/08/2023 C 29/08/2023 C
MEP Substation Earthing RAMS RIBA 3 N/A 03/11/2022 N/A 03/11/2022 23/11/2022 21/11/2022 30/01/2023 B Removed from CMT Workflow.
MEP Tech subs MEP Tech Subs RIBA 4 N/A 01/08/2023 N/A 01/08/2023 21/08/2023 17/08/2023 20/09/2023 B 20/09/2023 B 20/09/2023 B
MEP Underground GRP Storage Tank With Granula Infill/TF4 Filter RIBA 3 N/A 15/12/2022 N/A 15/12/2022 12/01/2023 10/01/2023 Given status A by MCLH on 22/02/2023.
MEP Valves Site wide RIBA 4 N/A 28/03/2023 N/A 28/03/2023 17/04/2023 13/04/2023 20/06/2023 A/B 06/06/2023 A/B 20/06/2023 A/B
MEP Ventilation Building A & B RIBA 5 N/A 14/11/2023 N/A 23/04/2024 13/05/2024 09/05/2024
29/04/2024
package review schedule Project Honey 05/06/2024 issue date discipline package description design stage planned release date (programme dated xxxx) actual release date delta all developer occupier/ fund date received status given date received status given date received status given comments comments received/ status given developer occupier fund response required by MEP Mechanical plantroom schematic Building B RIBA 3 18/11/2022 05/12/2022 -11 days 05/12/2022 23/12/2022 21/12/2022 05/12/2022 B Awaiting comments from occupier and fund. MEP Mechanical riser Building B RIBA 3 N/A 18/11/2022 N/A 18/11/2022 08/12/2022 06/12/2022 Awaiting comments. MEP Mechanical riser Building A RIBA 3 N/A 03/11/2022 N/A 03/11/2022 23/11/2022 21/11/2022 24/11/2022 B 24/11/2022 B 24/11/2022 B All plans received 03/11/2022 MEP Network schematic Building A, B & C RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 19/12/2023 C 19/12/2023 C 19/12/2023 C Status C received. MEP Network schematic Building A + B RIBA 3 N/A 05/12/2022 N/A 05/12/2022 23/12/2022 21/12/2022 08/12/2022 C C C Status C received. MEP Network schematic Building A, B & C RIBA 4 N/A 02/05/2023 N/A 02/05/2023 22/05/2023 18/05/2023 24/05/2023 B 19/05/2023 B 19/05/2023 B MEP Office and ancillary ventilation schematics Building A + B RIBA 3 01/11/2022 03/11/2022 0 days 03/11/2022 23/11/2022 21/11/2022 21/11/2022 B 21/11/2022 B 21/11/2022 B All plans received 03/11/2022
Office WC Ventilation Schematic Building B RIBA 3
05/12/2022 B awaiting response from occupier and fund.
Office WC Ventilation Schematic Building A + B RIBA 4
31/08/2023
18/09/2023 27/09/2023 C 24/09/2023 C 24/09/2023
awaiting response from occupier and fund.
MEP
N/A 11/11/2022 N/A 11/11/2022 01/12/2022 29/11/2022
MEP
N/A
N/A 31/08/2023 20/09/2023
C
technical
14/12/2022 19/12/2022 A/B 19/12/2022 A/B 19/12/2022 A/B
Piped services layouts Building A
B
5
MEP OTIS
drawings Building A RIBA 3 N/A 28/11/2022 N/A 28/11/2022 16/12/2022
MEP
&
RIBA
N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 14/03/2024 B 08/04/2024 B 08/04/2024 B Status C given on Building A 6th,8th floor layouts.
C
C
C
B 24/04/2023 B
B
24/07/2023
16/08/2023
16/08/2023
MEP Pressure Switch Technical Submittal RIBA 4 N/A 17/04/2023 N/A 17/04/2023 05/05/2023 03/05/2023 24/04/2023
24/04/2023
B
B
B
MEP Project Honey MEP Spec Specification RIBA 4 N/A 03/11/2023 N/A 03/11/2023 23/11/2023 21/11/2023 26/01/2024
26/01/2024
26/01/2024
06/01/2023 B
MEP
06/01/2023 B 06/01/2023 B
24/10/2022 B
https://francishunter-my.sharepoint.com/personal/kyra_bosompem_francishunter_co_uk/Documents/Documents/Project Honey/Package Review Schedule/Project Honey Package Review Schedule 231120
29/04/2024 A
A 29/04/2024 A Received all plans. MEP Ventilation Building C RIBA 5 N/A 15/01/2024 N/A 15/01/2024 02/02/2024 31/01/2024 15/02/2024 A 15/02/2024 A 15/02/2024 A MEP Ventilation Layout Building A RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023
06/01/2023 B 06/01/2023 B Received all plans.
Ventilation Layout Building B RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023
06/01/2023 B Awaiting Occupier and Fund comments. MEP Ventilation systems Calculations RIBA 3 10/10/2022 25/09/2022 -10 days 25/09/2022 13/10/2022 11/10/2022
24/10/2022 B 24/10/2022 B All plans received 25/09/2022
MEP
MEP Site Utilities Incoming Services Plans RIBA 4 N/A 14/04/2023 N/A 14/04/2023 04/05/2023 02/05/2023 23/05/2023 C 23/05/2023 C 23/05/2023 C
Structural Basement waterproofing system Basement waterproofing system RIBA 4 N/A 30/11/2022 N/A 05/12/2022 23/12/2022 21/12/2022 Not issued for review.
Structural Car park GA's and sections Car park GA's and sections RIBA 4 N/A 10/11/2022 N/A 10/11/2022 30/11/2022 28/11/2022 All plans received 10/11/2022
Structural Cast - In Channel Technical Submittal RIBA 3 N/A Not issued for review.
Structural Civils (tbc) Attenuation (CPD) RIBA 4 21/12/2022
Structural Core Plans Building A & B RIBA 4 N/A 27/02/2023 N/A 27/02/2023 17/03/2023 15/03/2023 12/05/2023 A 12/05/2023 A 12/05/2023 A
Structural First Floor GA Building B RIBA 4 N/A 16/12/2022 N/A 16/12/2022 13/01/2023 11/01/2023 MCLH closed out as status A ON 03/02/2023.
Structural GA's Building A & B RIBA 4 N/A 30/11/2022 N/A 30/11/2022 20/12/2022 16/12/2022
Structural GA's Building C RIBA 3 N/A 07/12/2022 N/A 07/12/2022 04/01/2023 23/12/2022 15/12/2022 A/B 15/12/2022 A/B 15/12/2022 A/B
Structural General Arrangement Plan Foundations RIBA 4 N/A 13/02/2023 N/A 13/02/2023 03/03/2023 01/03/2023
Structural General arrangements Building A+ B RIBA 4 N/A 26/09/2022 N/A 26/09/2022 14/10/2022 12/10/2022 13/01/2023 A 13/01/2023 A 13/01/2023 A All plans received. Awaiting comments for building B - first floor GA.
Structural Glass Balustrade Technical Submittal RIBA 4 N/A 11/04/2023 N/A 11/04/2023 01/05/2023 27/04/2023 11/05/2023 B 11/05/2023 B 11/05/2023 B
Structural Glass Technical Report Technical Submittal RIBA 4 N/A 06/04/2023 N/A 06/04/2023 26/04/2023 24/04/2023 25/04/2023 C 25/04/2023 C 25/04/2023 C MCLH delivery team and review - status C given.
Structural Grd Floor and L06 Link Bridge Grd Floor and L06 Link Bridge RIBA 4 29/11/2022 14/01/2023 N/A 14/01/2023
Structural Ground Floor Building B RIBA 4 04/11/2022 Not issued for review.
Structural Loading plans Loading plans RIBA 4 02/11/2022 02/11/2022 0 days 02/11/2022 22/11/2022 18/11/2022 31/10/2022 B 31/10/2022 B 31/10/2022 B All plans received 02/11/2022
Structural Pile caps Pile Caps C RIBA 4 23/09/2022 Not issued for review.
Structural Piling Piling A + B RIBA 4 11/08/2022 09/08/2022 -2 days 09/08/2022 30/08/2022 25/08/2022 25/08/2022 A/B 25/08/2022 A/B 25/08/2022 A/B All plans received on 09/08/2022
Structural Piling Concrete mix design RIBA 4 N/A 09/09/2022 N/A 09/09/2022 29/09/2022
Structural Piling Piling C RIBA 4 27/09/2022 07/12/2022 51 days 07/12/2022 05/01/2023 03/01/2023 16/12/2022 A 16/12/2022 A 16/12/2022 A
Structural Plant Steel frame Building A RIBA 4 15/03/2023
Structural Siderise CW-FS120 Technical Submittal RIBA 4 N/A 27/02/2023 N/A
Structural Specialist CDP Design (FP McCann) Specialist CDP Design (FP McCann) RIBA 4 13/10/2022
Structural Superstructure PT Floors (CPD) Building A RIBA 4 09/11/2022
Structural Superstructure PT Floors (CPD) Building B RIBA 4 09/11/2022
Structural Test piling Results and proposal RIBA 4 N/A 25/09/2022 N/A 25/09/2022 13/10/2022 11/10/2022 13/10/2022 A 13/10/2022 A 13/10/2022 A All plans received 25/09/2022
Structural Town Hall Building A RIBA 4 N/A 03/04/2023 N/A 03/04/2023 21/04/2023 19/04/2023 05/04/2023 A 05/04/2023 A 05/04/2023 A
Structural Walls and Columns inc Stairs Building A RIBA 4 20/10/2022
Structural Walls and Columns inc Stairs Building B RIBA 4 21/10/2022
Structural Wicona EL Evo Technical Submittal RIBA 4 N/A 23/01/2023 N/A 23/01/2023 10/02/2023 08/02/2023 01/02/2023 B Received EOC comments on 01/02/2023.
Structural Wind calculations Wind calculations RIBA 4 TBC 01/02/2023 N/A 01/02/2023 21/02/2023 17/02/2023
Structural Ash and Lacy Mechslip Brickslip Technical Submittal RIBA 4 N/A 09/03/2023 N/A 09/03/2023 29/03/2023 27/03/2023 24/05/2023 B 24/05/2023 B 24/05/2023 B
Structural Benchmark Approval Form Rectangular Columns RIBA 5 N/A 08/02/2023 N/A 08/02/2023 28/02/2023 24/02/2023 17/03/2023 B 20/03/2023 B 20/03/2023 B
Structural Kilsaran Inspection and Test Plan Test Plan RIBA 4 N/A 20/02/2023 N/A 20/02/2023 10/03/2023 08/03/2023 Not issued for review.
Structural Loading Plan Building C level 00 RIBA 4 N/A 22/03/2023 N/A 22/03/2023 11/04/2023 07/04/2023 24/04/2023 A 24/04/2023 A 24/04/2023 A
Structural Performance mark ups Building A & B RIBA 5 N/A 14/05/2024 N/A 14/05/2024 03/06/2024 30/05/2024 04/06/2024 B 04/06/2024 B 04/06/2024 B Received comments from EOC on 04/06/2024
Structural FaƧade Tech subs Technical Submittals RIBA 5 N/A 14/05/2024 N/A 14/05/2024 03/06/2024 30/05/2024 04/06/2024 B 04/06/2024 B 04/06/2024 B
package review schedule Project Honey 05/06/2024 issue date discipline package description design stage planned release date (programme dated xxxx) actual release date delta all developer occupier/ fund date received status given date received status given date received status given comments comments received/ status given developer occupier fund response required by MEP Wet Alarm Valve Set Technical Submittal RIBA 4 N/A 17/04/2023 N/A 17/04/2023 05/05/2023 03/05/2023 24/04/2023 B 24/04/2023 B 24/04/2023 B MEP Zonecheck Technical Submittal RIBA 4 N/A 04/04/2023 N/A 04/04/2023 24/04/2023 20/04/2023 11/04/2023 A 02/05/2023 A 02/05/2023 A MEP Electrical riser Building A RIBA 5 N/A 04/03/2024 N/A 04/03/2024 22/03/2024 20/03/2024 20/03/2024 B 13/03/2024 B 20/03/2024 B MEP Office Floor Ventilation Distribution Schematic Building A RIBA 5 N/A 06/02/2024 N/A 06/02/2024 26/02/2024 22/02/2024 12/02/2024 B 05/03/2024 B 05/03/2024 B MEP Containment Layouts Building C RIBA 5 N/A 05/12/2023 N/A 05/12/2023 25/12/2023 21/12/2023 19/12/2023 B 21/12/2023 B 21/12/2023 B MEP External Louvres Schedule RIBA 5 N/A 15/01/2024 N/A 15/01/2024 02/02/2024 31/01/2024
Tech subs MEP Tech Subs RIBA 5 N/A 13/05/2024 N/A 13/05/2024 31/05/2024 29/05/2024 03/06/2024 B 03/06/2024 B 03/06/2024 B MEP Domestic Services Building A &B RIBA 5 N/A 15/01/2024 N/A 15/01/2024 02/02/2024 31/01/2024 21/02/2024 B 21/02/2024 B 21/02/2024 B MEP
Layout Building A
A
A
A Status B given on Building A 7th floor drainage layout.
Dry Riser Schematic Layout Building C RIBA 4 N/A 12/06/2023 N/A 12/06/2023 30/06/2023 28/06/2023 20/06/2023 B 16/08/2023
MEP
Drainage
& B RIBA 5 N/A 13/03/2024 N/A 13/03/2024 02/04/2024 29/03/2024 19/03/2024
19/03/2024
19/03/2024
MEP
A/B
Building
C
C
C
MEP Earthing Schematic
A, B & C RIBA 5 N/A 14/11/2023 N/A 14/11/2023 04/12/2023 30/11/2023 19/12/2023
19/12/2023
19/12/2023
Board Technical
A
MEP Initiation
Submittal RIBA 4 N/A 14/08/2023 N/A 14/08/2023 01/09/2023 30/08/2023 30/08/2023
30/08/2023 A 30/08/2023 A
Plantroom Schematic Building C RIBA 3 N/A 20/12/2022 N/A 20/12/2022 17/01/2023 13/01/2023 07/02/2023 B 10/02/2023 B 07/02/2023 B
02/02/2023 31/01/2023 06/02/2023 B 06/02/2023 B 06/02/2023 B
Structural Lower Ground floor Lower Ground Floor C RIBA 4 20/10/2022 Structural Pile and core Caps Pile and core - caps A + B RIBA 4 23/09/2022 30/09/2022 7 days 30/09/2022 20/10/2022 18/10/2022 19/10/2022 A/B 19/10/2022 A/B 19/10/2022
plans received
A/B All
30/09/2022
27/09/2022 24/09/2022 A 24/09/2022 A 24/09/2022 A All plans received on 09/09/2022
27/02/2023 17/03/2023 15/03/2023 Not issued for review.
https://francishunter-my.sharepoint.com/personal/kyra_bosompem_francishunter_co_uk/Documents/Documents/Project Honey/Package Review Schedule/Project Honey Package Review Schedule 231120
McLH procurement schedule
FH090-151015 appendix m
McLaughlin & Harvey Ltd Y Procurement Schedule Doc Ref: BO/3-2940 5412 - Project Honey 03 June 2024 Key: Order Complete Procured By Package Subcontractor / Supplier (Potential) Latest Award Date Lead In Period inc. Design (wks) Start On Site Date LOI Issued (Y/N) Order Placed (Y/N) Order Date Status Monitor (wks) External Works/Landscaping TBC 08/06/2024 6 20/07/24 1 Flood Grilles/Steelwork TBC 23/07/2024 4 20/08/24 7 Final Clean Serna 25/04/2024 4 23/05/24 Y ISSUED Decoration (excluding WC's) AC Beck 22/05/2024 2 05/06/24 Y ISSUED Glazed Doors/Screens OWS 23/01/2024 12 16/04/24 Y ISSUED Service Yard Gte TBC 14/02/2024 12 08/05/24 Y ISSUED O & M Manuals Riddell 02/02/2024 4 01/03/24 Y ISSUED Air Test Air Leakage Testing 16/03/2024 4 13/04/24 Y ISSUED Raised Access Floors Kingspan 29/11/2023 10 07/02/24 Y ISSUED Lift Lobby Fire Curtains A1S Shutters 04/12/2023 8 29/01/24 Y ISSUED Feature Stair Fire Curtains Coopers 04/12/2023 8 29/01/24 Y ISSUED Commissioning Manager Ashford 27/10/2023 1 03/11/23 Y ISSUED Green Roof AYM 12/09/2023 12 05/12/23 Y ISSUED Roofing & Waterproofing AYM 12/09/2023 12 05/12/23 Y ISSUED Firestopping Middlesex 25/09/2023 6 06/11/23 Y ISSUED Fit-Out including WC's Swift Crafted 12/08/2023 21 06/01/24 Y ISSUED Partitions & Ceilings AT Jones 02/08/2023 5 06/09/23 Y ISSUED Structural Steel CMF Limited 24/08/2023 8 19/10/23 Y ISSUED Feature stair/Architectural Metalwork CMF Limited 22/07/2023 12 14/10/23 Y ISSUED Screeds UK Subfloors 27/07/2023 6 07/09/23 Y ISSUED Secondary Steel CMF Limited 19/08/2023 8 14/10/23 Y ISSUED Scaffolding Kitts 01/11/2023 4 26/06/23 Y ISSUED Sewer Connection Riney 10/07/2023 12 02/10/23 Y ISSUED Plant Screens Clarke Facades 12/06/2023 8 07/08/23 Y ISSUED Blockwork Swift 19/06/2023 8 14/08/23 Y ISSUED Facade Clarke Facades 17/10/2022 48 18/09/23 Y Y ISSUED Mansafe System PTSG 23/05/2023 15 05/09/23 Y Y ISSUED Roof Access Strategy PTSG 08/08/2023 4 05/09/23 Y Y ISSUED Temporary Electrics Trident 11/01/2023 15 26/04/23 Y ISSUED Sanitary Appliances Halsion 13/03/2023 15 26/06/23 Y ISSUED Lifts Otis 05/01/2023 35 07/09/23 Y ISSUED Hoists Reco 16/01/2023 16 08/05/23 Y ISSUED BREEAM Consultant Armila 06/11/2022 2 20/11/22 Y Y ISSUED Site Temps (Enabling) Wysepower 07/11/2022 1 14/11/22 Y ISSUED Building Control Sweco 13/11/2022 1 20/11/22 Y ISSUED Principal Designer Orsa/Ridge 06/11/2022 2 20/11/22 Y ISSUED Logistic Management & Security Avondale 24/10/2022 2 07/11/22 Y ISSUED Car Park - Structure FP McCann 28/11/2022 12 20/02/23 Y Y ISSUED Temporary Works AWD 26/09/2022 2 10/10/22 Y Y ISSUED Landscape Architect McIlwaine 03/10/2022 2 17/10/22 Y Y ISSUED Precast Stairs Mitchellson 04/01/2023 8 01/03/23 Y Y ISSUED GRP Grating Mitchellson 06/04/2023 21 31/08/23 Y ISSUED Ground Investigation Survey Geotech 12/09/2022 0 12/09/22 Y ISSUED M&E Installations Halsion 15/08/2022 45 26/06/23 Y Y ISSUED Acoustic Consultant Hann Tucker 05/09/2022 1 12/09/22 Y ISSUED Fire Consultant Marshall Fire 05/09/2022 1 12/09/22 Y ISSUED Groundworker & Frame Mitchellson 26/08/2022 6 07/10/22 Y ISSUED Biometrics M Site 29/08/2022 2 12/09/22 Y ISSUED Piling Van Elle 22/08/2022 3 12/09/22 Y ISSUED Surveys SES 29/08/2022 2 12/09/22 Y ISSUED Architect Darlings 11/02/2022 2 25/02/22 Y ISSUED Structural & Civil Consultant Robert Bird 11/02/2022 2 25/02/22 Y ISSUED Hoarding (Alterations) Shorts 18/07/2022 3 08/08/22 Y ISSUED Site Accomodation; including Electrics Avondale 18/07/2022 3 08/08/22 Y ISSUED Hoarding License Council 12/09/2022 0 12/09/22 Y ISSUED Buildings A and B Page 1 of 1 03/06/2024
5412 - Project Honey 03 June 2024 Key: Order Complete Package Subcontractor Supplier (Potential) Design Responsibility (Y/N) Go To Tender Tender Period (wks) Latest Award Date Lead In Period inc. Design (wks) Start On Site Date LOI Issued (Y/N) Order Placed (Y/N) Order Date Status Monitor (wks) Comments / Status Final Clean TBC N 23/05/2024 6 04/07/2024 4 01/08/24 4 Waterproofing - Above Changing Village 4M Floors N 22/03/2024 6 03/05/2024 8 28/06/24 Y ISSUED Resin Flooring & Line Marking 4M Floors N 22/03/2024 6 03/05/2024 8 28/06/24 Y ISSUED Cycle Storage Turvec Y 08/04/2024 6 20/05/2024 12 12/08/24 Y ISSUED External Doors/Louvres Clarke Facades Y 26/02/2024 6 08/04/2024 12 01/07/24 Y ISSUED Roof Landscaping Frost Landscapes Y 10/12/2023 8 04/02/2024 14 12/05/24 Y ISSUED Fit Out (including Changing Rooms ) Original Joinery Y 03/10/2023 6 14/11/2023 8 09/01/24 Y ISSUED Architectural Metalwork CMF Y 19/10/2023 6 30/11/2023 8 25/01/24 Y ISSUED Brickwork Swift N 02/10/2023 6 13/11/2023 20 01/04/24 Y ISSUED GRP Grating Dura N 06/09/2023 6 18/10/2023 6 29/11/23 Y ISSUED Firestopping Middlesex N 03/10/2023 6 14/11/2023 8 09/01/24 Y ISSUED Roofing & Waterproofing AYM Y 10/08/2023 8 05/10/2023 12 28/12/23 Y ISSUED Blockwork Swift Block N 03/08/2023 4 31/08/2023 4 28/09/23 Y ISSUED Screeds TBC N 09/08/2023 6 20/09/2023 10 29/11/23 Y ISSUED Perforated FaƧade Envelope Maple Y 30/05/2023 6 11/07/2023 20 28/11/23 Y Y ISSUED MEP Halsion Y 01/06/2023 6 13/07/2023 15 26/10/23 Y ISSUED Lifts Otis Y 19/09/2023 6 31/10/2023 35 02/07/24 Y Y ISSUED Car Park - Superstructure FP McCann Y 24/04/2023 6 05/06/2023 6 17/07/23 Y Y ISSUED
MSCP
Procurement
Page 1 of 1 03/06/2024
Contract: Building C -
Schedule Date:
Schedule
FH090-151015 appendix n
McLH programme
Lautus progress report
FH090-151015 appendix
o
Planning Report
Project Honey
1
May 24
Project Honey
This report is based on the construction programme rather than the contract programme.
Summary
Progress
The approach to the installation of Utilised cladding had been to complete two floors of cladding before finishes commence on the floor. Due to the poor performance this has been relaxed to complete a floor of cladding and then start finishes on that floor. This again was changed to carry out finishes to a floor independent to cladding installation leaving just the perimeter fit out works until the cladding is finished. This approach results in a higher risk of water damage but reduces the projection delays in completion.
A key link between the completion of utilised cladding on a floor and commencing the perimeter floor plate fit out is missing.
Total number of weeks Week Number Section Block Completion 109 88 1 B 5 August 24 2 A 21 October 24 2 C 21 October 24
2 Block Present position reported Previous position +/A -2W 2D B - 4W 0D C - 1 W
Building A - on site
Envelope
The weekly reports detailing cladding panels manufactured and cladding panels installed has stopped. Reports now only detail units manufactured and not cladding panels fixed split between straight and curve panels.
Due to reported production issues, cladding progress has been poor. There is not one floor that is completed. The lack of curved panels on the lower floors may have an affect on early commissioning.
From the revised construction programme cladding completion is show as 12 August 24
The Contract programme shown completion 22 April 24.
Utilised Cladding now 15 weeks 3 days in delay.
The instruction to install perimeter blind boxes will be carried out once the utilised panels have been fixed. The sequencing of this work may well increase pressure in achieving pc.
There are no links between the end of cladding on each floor and the remaining fit out works that can only be undertaken once the cladding is complete to a floor in particular level 5.
Membranes installed with finishes still to be carried out. Installation dates for the PV panels still to be confirmed. Mechanical works are a principle delay on level 9 and the terrace level 8. Level 6 the delay is now insulation, gutters, roof finishes handrails etc.
3
Roof
Roof delays Building A.
Finishes
Power On is due w/c 28/5/24.
Lift installation ā Work complete lift 07 and 97% complete on L01 & L05. Work progressing on lifts L02 and L06 running approximately -2½ weeks. L03 due to commence 24 June 24.
Lift L07 is planned to be used as the only means of vertical transportation of movement of materials and labour shared with the fit-out contractor once the external hoist has been de commissioned 10 June 24. This could cause delays in moving materials and labour up the building.
Work to risers running -5 weeks in delay.
Cores
The construction programme has split the cores down into
1). WC fit out
2). Lobby and corridors.
4
This will give a clearer picture of progress in the cores.
Work activities to cores are running in parallel on level 1 to 5 which requires high levels of labour with a higher risk in achieving programme dates.
The critical floor is the fifth floor CAT fit out, showing at present completion 30 September 24 with beneficial access of the 23 September 24. Key to achieving this date is the installation of utilised cladding panels and resolving issues around the blind box installation which are still to be confirmed.
Plenums have been ordered with a delivery date of the 14 June 24. This will affect the planned timing of the air balancing.
Building B- on site
Envelope
Original completion of the utilised cladding was the 10 April 24, now projected completion 8 July 24 an improvement from last month.
The weekly reports detailing cladding panels manufactured and cladding panels installed has stopped. Reports now only detail units manufactured and not cladding panels fixed, split between straight and curve panels.
Cladding installation is running approximately 12W2d. Last month 14 weeks late. A betterment of 1W 3d from previous month.
5
Roof
Level 11 roof is complete except for installation of plant screen cladding.
The terrace at level 10 roof finishes still to be carried out beyond the laying of the completed membrane. Projected completion is the 1 August 24.
Finishes
Power On due 24 May 24.
Lift installation.
Lift 03 is complete L02 is 90% complete. Lift L04, L05 are underway and L01 installation is still to commence.
It is reported that beneficial access will be provided via a shared lift L03. This will be the only means of vertical transportation or movement of materials and labour, shared with the fit-out contractor once the external hoist has been decommissioned. This could cause delays in moving materials and labour up the building.
Finishes to Stairs 01 and 02 now running together rather than one at a time. This may cause access restrictions for labour and materials.
Building C- on site
Roof landscaping 34% complete.
The final cladding panels to be installed on the South elevation, the projected completion now 4 June 24.
Work progressing with fit out on the ground floor a critical area which is now projected to complete 28 October 24.
6
External Works Access
Gate 2 will be closed 3 June 24.
The haulage road is then due to be broken up. This will effect site logistics at a time when there is a high demand for materials for fit out works. This may have an effect on site progress. The water connection at the site boundary will also increase congested on the movement of materials.
Tower Cranes
TC2 is removed 27/28 July 24. Building B.
TC3 is removed 22/23 June Building A.
Hoist
Hoist is to be removed building A on the 10 June 24.
Critical issues
āą¾ Date required from Thames Water when final connections will be made.
āą¾ Poor performance of installation of unitised cladding panels will affect the final fitting out of upper floors.
āą¾ No weekly reports now being given of unitised straight and curved panels installed per week.
āą¾ Access for materials and labour will be via one lift in each building. Concern that the proposed use of only one lift for both the main works and for client contractors will restrict movement of labour and materials.
āą¾ With the possible introduction of Smart building functionality, it is necessary to know
7
what elements of the build have to be complete for the smart system to commence installation. This will enable the dovetailing of the final stages of the build process with the installation of the smart system.
āą¾ The updated beneficial access dates are to be incorporated onto the construction programme.
āą¾ The effect of the introduction of blind boxes is to be determined on the completion of a floor. Manufacture periods, installation and sequencing details to be confirmed.
āą¾ With the break out of the haulage road this will effect the logistic of movement of materials at a time when the pressure for materials for internal works is increasing. This is likely to effect on site progress.
8
FH090-151015 appendix p
Clarkeās manufacturing update
Block B Straight Panels
Project Honey - Block B
Straight Panels (including linkbridge)
06/05/202413/05/202420/05/202427/05/202403/06/202410/06/202417/06/202424/06/202401/07/2024
Panels Fabrication (Planned) 3320258252524
Panels Fabrication (Actual) 332-26 258131619
Cumulative Fabricated (Planned) 258283308332
Cumulative Fabricated (Actual)258271287306 TotalCheck
Project Honey - Block B Curved Panels
Block B Curved Panels
06/05/202413/05/202420/05/202427/05/202403/06/202410/06/202417/06/202424/06/202401/07/2024
Panels Fabrication (Planned) 82049111111
Panels
Cumulative Fabricated (Planned) 49607182
Cumulative Fabricated (Actual)49596871
Block A Straight Panels
Project Honey - Block A
Straight Panels (including linkbridge)
06/05/202413/05/202420/05/202427/05/202403/06/202410/06/202417/06/202424/06/202401/07/2024
Panels Fabricated (Planned) 478026300058585742
Panels Fabrication (Actual) 478-161 263122418
Cumulative Fabricated (Planned) 263263263263321379436478478
Cumulative Fabricated (Actual)263275299317
Block A Curved Panels
Project Honey - Block A Curved Panels
06/05/202413/05/202420/05/202427/05/202403/06/202410/06/202417/06/202424/06/2024
Note: From WC 13/05/24 we will be fabricating Block A 'Z' Panels for 4 weeks
01/07/2024
TotalCheck
Fabrication (Actual) 82-11 491093
TotalCheck
TotalCheck
Panels Fabricated (Planned) 6903600077775 Panels Fabrication (Actual) 69-31 36110 Cumulative Fabricated (Planned) 363636364350576469 Cumulative Fabricated (Actual)36373838
Level 8.5
LFB response
FH090-151015 appendix
q
Private and Confidential
Gregory Kypri
Principal Building Control Surveyor Sweco
T 020 8555 1200
Minicom 020 7960 3629 london-fire.gov.uk
The London Fire Commissioner is the fire and rescue authority for London Date 13 May 2024 Our Ref 23/161090/LR Your Ref 66101102
Dear Sir/Madam,
RECORD
OF CONSULTATION/ADVICE GIVEN
THE BUILDING (APPROVED INSPECTORS ETC.) REGULATIONS 2010 & REGULATORY REFORM (FIRE SAFETY) ORDER 2005 ARTICLE 46
FIRE AND RESCUE SERVICES ACT 2004
SCOPE OF WORKS: new mixed use development PREMISES ADDRESS: Project Honey, Surrey House, Kingston Upon Thames, London KT1 PLAN NUMBER(S) INCLUDING REVISIONS: As per attached PDF. DOCUMENTS REVIEWED:
⢠Fire Strategy Report ā Buildings A & B. EDC-MAR-ZZ-XX-RP-Y-0009-P07-S4. Marshall Fire. Rev 14. 07/08/23
⢠Fire Strategy Report ā Building C. EDC-MAR-CXX001-XX-RP-Y-0002-P05-S4. Marshall Fire. Rev 04. 26/06/23
⢠External Fire Spread Analysis. EDC-MAR-ZZ-XX-RP-Y-0001-P03-S4. Marshall Fire. Rev 01. 06/07/23
⢠CFD Report: Venting of a FF shaft - Building B. EDC-MAR-BXX001-XX-RP-Y-0003-P05-S4. Marshall Fire. Rev 02. 08/02/23
⢠CFD Report: Venting of a FF shaft at reduce height - Building B. EDC-MAR-BXX001-XX-RPY-0002-P02-S4. Marshall Fire. Rev 01. 08/02/23
⢠CFD Report: Venting of Level 8. EDC-MAR-AXX001-XX-RP-Y-0005-P01-S4. Marshall Fire. Rev 00. 27/03/23
⢠CFD Report: Venting of a FF shaft. EDC-MAR-AXX001-XX-RP-Y-0002-P04-S4. Marshall Fire. Rev 02. 08/02/23
⢠3rd Party Review of Fire Strategy. Brigly Fire. BF/FSR/SWE/HONEY. Issue 2. 01/06/23
⢠3rd Party Review of CFD Modelling. Brigly Fire. CFD/REV/SWE/HONEY. Issue 2. 21/05/23
⢠LFB Pro forma. Sweco. 16/08/23
The London Fire Commissioner (the Commissioner) is the fire and rescue authority for London. The Commissioner is responsible for enforcing the Regulatory Reform (Fire Safety) Order 2005 (The Order) in London.
The Commissioner has been consulted with regard to the above-mentioned premises and makes the following comments/observations:
Union Street
169
London SE1 0LL
FS_D_01HUB Rev 0, 05/10/2021 Page 1 of 9
(1) Comments on proposed scheme primarily relating to the Regulatory Reform (Fire Safety) Order 2005 (āThe Orderā)
Note to the building control body (BCB): it is expected that a copy of these comments will be passed to the future responsible person for this scheme.
Project Honey Building A and Building B Fire Strategy Report, EDC-MAR-ZZ-XX-RP-Y-0009P07-S4_Rev 14, dated 07/08/2023
3.1. Means of Warning and Evacuation Regime
1. We note the commentary indicating that an investigation period is not proposed. We assume consideration has been given towards the impact false alarms and unwanted fire alarms signals will have on the buildings occupants and the London Fire Brigade (LFB) given this proposal.
3.2 Horizontal Means of Escape
2. It is unclear from the plans provided how the occupants of the bridge will escape to a storey exit. We assume occupants within the bridge have unrestricted access to a storey exit within the maximum allowable travel distances specified table 11 of BS 9999:2017 and summarised in section 3.2.1 of the fire strategy report. We assume the BCB, as approving authority, are satisfied with the proposed arrangements
3.2.1 Travel Distance
3. We note the travel distance within the mezzanine level exceeds the minimum allowable travel distance for a retail space. As the layout is unknown this distance should not exceed 13.2m. We question how a 32.65m travel distance is considered acceptable and are of the opinion further justification is required for this significant deviation from guidance.
3.2.2 Horizontal Means of Escape ā Door Widths
4. We note a single firefighting core serves the 8th storey of building A which is a clear deviation from guidance. As a single stair office design over 11m (31.7 m in this case) is such a significant departure from fire safety guidance such as ADB and BS 9999, in our opinion a fully fire engineered approach following a framework such as that outlined in BS 7974 and the supporting PD 7974 series should be followed. Included within the BS 7974 framework is the expectation to undertake a qualitative design review (QDR). We would expect the QDR to consider and agree the key considerations relating to a tall single stair, such as:
a) How a potential fire will be controlled and suppressed (such as by compartmentation and a suitable automatic fire suppression system);
b) How the single stair will be fundamentally protected for means of escape, and how provisions for safe working for attending fire crews will be provided. This will require demonstration that the stair and lobby will be protected from the ingress of smoke throughout both the means of escape and firefighting phases, and that the smoke control system proposed will direct the air path direction from the stair to the lobby and from the lobby to the fire compartment. Air paths in the reverse direction are potentially unsafe for attending fire crews.
c) Consider the number of both evacuation lifts (see BS 9999:2017 Annex G) and firefighters lifts to ensure there is sufficient numbers of lifts provided so that if a lift is out of service (e.g. as a result of breakdown or maintenance), there is at least one of each lift type (evacuation and firefighters) that is still available for use from all areas of the building.
d) How it will be demonstrated that all occupants, including any that require assistance from the buildingās fire safety management personnel, can evacuate prior to the arrival of the fire and rescue service.
FS_D_01HUB Rev 0, 05/10/2021 Page 2 of 9
We are also of the opinion that particular aspects in this scheme are not compatible with a single stair approach, for example the dual entry firefighterās lift, fire curtain. These aspects should be addressed as part of the overall fire safety engineering approach.
5. We also highlight the stair arrangements on the seventh and eighth floors of building A are not standard and could cause confusion in both the means of escape and firefighting phases Clear signage may be necessary to reduce any confusion. We assume you the BCB and approving authority will satisfy yourselves regarding the non-standard approach.
3.2.3 Building A ā Eighth Floor Level Shared Lift Lobby
6. All occupants from the Eighth floor of building A must pass through the lift lobby (08-002 Lift Lobby) to reach a place of relative safety This is highlighted in the CFD report which shows the whole lift lobby (08-002) and corridor (08-001) filled with smoke We do not feel it appropriate to consider the storey exit at the lobby door as this is not a place of relative safety. We therefore are of the opinion the travel distances for the 8th storey should be reconsidered and measured to a place of relative safety.
3.3 Vertical means of Escape
7. We note that an L2 fire alarm has been proposed instead of a type M (Manual) alarm system in order to apply a BS 9999 15% reduction/increase where necessary. We disagree that a manual alarm system would be appropriate and would expect that a suitable and sufficient fire risk assessment would include an automatic fire detection and alarm system for this type of building. Therefore, in our opinion the system provided is not enhancement and should not be used to justify the extended travel distances within the premises.
8. We note the total anticipated occupancy on upper floor levels is within the maximum numbers according to the total achievable occupancy load. However, as noted in the comment 7, above we do not feel a 15% reduction in the stair width per person is appropriate. We refer this to you the BCB and approving authority for review. If you do not agree with the 15% reduction in stair width then the maximum allowable occupancy will be reduced and the total anticipated occupancy will exceed this. Therefore, considerations will need to be made as to how the occupancy numbers will not exceed the maximum allowable occupancy
3.5 Open Spatial Void
9. We note that active fire curtain barrier assemblies (hereafter referred to as the āfire curtain(s)ā) are proposed to be used to enclose the open spatial voids created by the feature stair. In our opinion, the use of fire curtains for the proposed application does not provide equivalence to traditional passive fire protection, composed of fire resisting walls and protected openings. This is in part due to the increased maintenance and testing expectations placed upon the responsible person by fire curtains. We recommend that the proposed use of fire curtains for this application be reconsidered. Where it is proposed to continue to use fire curtains, we request that further suitable justification be provided.
10. We note the proposed Townhall (open spatial void) at level six and seven of Building A. It is unclear who will manage this space to ensure the proposed floor capacities and the 2m sterile zone around the feature stair are managed. We assume this space will be occupied by those unfamiliar with the building and expect an appropriate risk profile is applied to this space
3.6 Provision of Refuges
11. Refuge spaces have not been clearly identified on the plans or within the fire strategy. We note the comment āa disabled refuge positioned in a place of safetyā however we question where this may be in each building. The mechanical smoke extraction from the lobbies will cause smoke to enter them eliminating them as an option as a place of safety. This is further demonstrated in the CFD reports. We therefore assume the only place of safety is considered to be within the staircase however we question how the minimum area (900mm x 1400mm) for the refuge
FS_D_01HUB Rev 0, 05/10/2021 Page 3 of 9
space is satisfied as it appears there is not the space to have the refuge space without impeding on the stair width
12. A sufficient number of lifts should be available at all times for both firefighters use and occupant evacuation. This number should also include a redundancy to ensure that there is at least one lift still available for use from all areas of the building, in the event of the lift being out of service (e.g., as a result of breakdown or maintenance). We assume that you as the approving authority will ensure that an acceptable number of lifts are provided, for both firefighters use and occupant evacuation.
5.2.2 Compartmentation
13. We feel there are significant increased risks with the proposed arrangements for the glazing on the stair core 2 in building B We refer you to our commentary in comment 9 above.
Building B Ground Floor Escape Stair Glazed Screen
14. Glass poses two problems in the event of a fire - excessive thermal radiation passing through the glass and cracking and falling out of the glass once a critical temperature difference has been reached. Compartmentation requires that areas are independent from each other and so the effects of fire on glass leads to situations where compartmentation breaks down.
A study investigating the effect of water film, or drencher systems, on glass, exposed to fire, suggests that crazing and falling out of the glass has a tendency to occur during cooling of the glass. The implication being that the thermal shock from water spray causes crack formation which subsequently propagates through the glass. This occurs due to a temperature difference across the thickness of the glass. In the case of impact of water, this may be characterised by a certain temperature on the exposed side.
Failure of the window leads to loss of integrity leading to potential increased smoke exposure nevertheless the use of water film does decrease the transmission of heat radiation decreasing the thermal exposure. Assessment of these scenarios and the hazards they present is needed to ensure that the building operates as intended, in the event of a fire. Avoidance of these glass failures requires assurances of certain temperatures on the exposed side of the glass. Principally because it is not possible to restrict water impact on glass as this would incur restrictions of fire fighter tactics.
General
Fire curtain assemblies
15. We note that active fire curtain barrier assemblies (hereafter referred to as āfire curtainsā) are proposed to be provided. It is our expectation that that the fire curtain(s) will be specified to conform to the requirements of BS 8524 parts 1 and 2 and that consideration should be given to performance requirements such as:
⢠Suitable insulation and radiation performance in accordance with Clauses 5.6.3 and 5.6.4 of BS 8524-1:2013, where the fire curtain is proposed to be in proximity to an escape route or combustible materials;
⢠A reliability and durability Class suitable for the proposed frequency of testing of the assembly, in accordance with Clause 5.3 of BS 8524-1:2013: in our opinion, this is especially important where the fire curtain is proposed to compensate for the omission of passive fire protection in critical areas and it would be appropriate to test the fire curtain more frequently and in excess of the manufacturerās recommended maintenance schedule;
⢠An emergency egress control, in accordance with Clause 5.4.3 of BS 8524-1:2013, for example where a fire curtain(s) is proposed to be located on means of escape routes;
⢠An emergency access control, in accordance with Clause 5.4.4 of BS 8524-1:2013, for example where a fire curtain(s) is proposed be located on fire and rescue service access routes;
FS_D_01HUB Rev 0, 05/10/2021 Page 4 of 9
⢠Sensory equipment for obstruction warning in accordance with Clause 5.8.5 of BS 8524-1:2013: in our opinion, this equipment should be considered whenever fire curtains are proposed to be provided in areas where it is reasonably foreseeable that obstructions such as furniture or luggage could be located.
For additional guidance, we refer to the ASFP published Black Book: Active Fire Curtains: Compartmentation and Protected Routes, 1st Edition: Guidance on specification, use and application of product.
CFD
16. We note that the modelling on this project has been demonstrated to meet the design objectives to the satisfaction of the Approving Authority (or in conjunction with their third-party reviewer). As such for this project LFB have only reviewed the accompanying report and not the modelling data itself.
(2) Observations on proposed scheme primarily relating to the Building Regulations
Project Honey Building A and Building B Fire Strategy Report, EDC-MAR-ZZ-XX-RP-Y-0009P07-S4_Rev 14, dated 07/08/2023
7.1 Access to the Building for Firefighting
17. Table 13 of the fire strategy indicates a minimum carrying capacity of 12.5(t). Please note LFB pumping appliances require a minimum carrying capacity of 14 tonnes. (See Fire Safety Guidance Note .29 attached).
18. We note the commentary proposing the omission of the dry riser outlet between levels seven and eight of stair 1A. It should be noted that hose distances are not the sole criteria for the recommendation of a second Firefighting shaft. We refer you to comment number 21 below. The omission of the dry riser outlet limits, firefighting tactical options, as attending fire crews will run two jets, one from the floor of origin (which is typically the back-up jet) and one (the primary jet) from the floor below, therefore, we do not concur with the justification as detailed and are of the opinion that the dry riser should be provided in accordance with clause 22.1 of BS 9999:2017.
19. We note the dry riser inlet for stair 2 of building A is located in a position that is not intuitive for firefighter access. It is our expectation the dry riser inlet is located on the external wall next to the access point for a firefighting shaft. With the current arrangements there may be confusion with the dry riser inlet for stair 1. Clear signage should be considered to ensure this confusion is restricted.
7.2 Temporary Firefighting Vehicle Access for Building B
20. We note the temporary firefighting arrangements which do not meet the recommendations of guidance. It is essential the time period for temporary arrangements is minimised Considerations should be made as to how the temporary arrangements will affect the firefighting operations and captured within the fire risk assessment. It should be ensured the continued safe operation for firefighters as well any additional provisions that can be implemented to reduce the additional demand on firefighting operations are provided.
7.3 Firefighting Shaft
21. We disagree with the inappropriate method undertaken to measure the floor plate of building B. The firefighting facilities clearly form part of the floor plate and are intended to be low risk in order to provide protection to firefighters and in our opinion must part of the calculated floor size. Further, it is our expectation and that of guidance such as Approved Document B and BS 9999 that building B should be served by two firefighting shafts. as the stated floor area is >900m2. It should be noted that hose coverage is not the sole determinant of the number of
FS_D_01HUB Rev 0, 05/10/2021 Page 5 of 9
firefighting shafts but just one factor. Consideration also needs to be given to aspects such as the impact of tenancy splits, the ability for firefighters to approach the fire from a different direction, carrying out firefighting and search and rescue activities simultaneously, and the ability to switch to another firefighting shaft if one is compromised. It is our view that the benefits of two firefighting shafts and the options these give attending fire crews are not met in this instance.
22. We note commentary in section 5.2.2 of the fire strategy proposing the dual-entry firefighter lift will meet the recommendations given in clause 20.4.3 of BS 9999:2017. However, we refer to clause 20.4.3 (d) where it states that āany storey served by a single firefighters lift should not be served by a dual-entry firefighters liftā. Therefore, we do not consider that the proposed design is suitable. It is our opinion that the dual-entry provision for the firefighters lift should be removed and the lift should open into the firefighting lobby only. The firefighting lift should also not be used as a goods lift.
23. We note commentary stating āthe mezzanine floor is served solely by stair 1 and is not provided with a firefighting lift due to building constraintsā however we do not feel justification has been made for the deviation from clause 20.1.3 of BS 9999:2017
7.5 Fire Control Centre
24. The fire control centre for building B is located through a back of house corridor which has an unventilated bin store connected to it. It is our expectations that 0.2m2 of permanent ventilation or a suitable mechanical alternative is provided as per clause 15.10 of BS 9999:2017. We question how the proposed arrangements can be considered acceptable and assume you, the BCB and approving authority will ensure the proposed arrangements do not negatively impact the access to the fire control centre.
7.7 Smoke ventilation
25. It is unclear from the documents provided whether ventilation is provided to the lobby of the firefighting shaft at the mezzanine level of building A. It is our expectation all levels accessed from the firefighting shaft should have the necessary provisions outlined in clause 20 and 27 of BS 9999:2017. Please provide further justification as to the ventilation provisions for the mezzanine level.
(3) Additional observations and recommendations relating to proposed scheme
Project Honey MSCP Building C Fire Strategy Report, EDC-MAR-CXX001-XX-RP-Y-0002-P05S4_Rev 04, dated 26/06/2023
7.6 Car Park Electric Charging Points
26. We note that the proposals include enclosed car parking areas and recommend that consideration is given in relation to electric vehicle (EV) charging units, together with the potential fire risk posed by their battery systems. The following should be considered, preferably as part of a Qualitative Design Review (QDR) and, following the recommendations given in BS 7974. This is not intended to be an exhaustive list of considerations:
⢠Whether the smoke ventilation provisions for car parks are sufficient to manage the products of combustion from a fire involving one or more EVs
⢠Whether AWFSS require enhancements beyond the minimum recommendations of the relevant standards
⢠Whether the fire resistance of elements of structure should be increased beyond the minimum recommendations of this code of practice
FS_D_01HUB Rev 0, 05/10/2021 Page 6 of 9
⢠Whether car parking spaces served by EVCUs should be located closer to the access points to the car park for the fire and rescue services and to any fire main outlets in order to assist firefighters in applying extinguishing media to the fire
⢠Whether there should be provision for the safe removal of any EV car that has been involved in a fire and may still pose a risk of reignition. If access to the space is only via a car lift, for example, this may not provide such suitable provision
⢠Whether the water supplies provided for the fire and rescue services should be enhanced beyond the minimum requirements of BS 9990 and other relevant standards, in particular with regard to the duration of water supply available
⢠Suitable protection to car park internal surfaces and drainage systems to facilitate post-fire clean-up and environmental protection
This list is not intended to be exhaustive. However, it covers some of the areas of consideration that we would expect to be addressed by the project design team. We would also recommend liaising with the relevant insurance provider as they may have their own requirements.
A means of isolating the power supply to EVCUs should be provided for the fire and rescue services in a suitable location associated with, but outside of, the fire resisting enclosure to any car park containing EVCUs. This should be at the main designated access point to the building or car park for the fire and rescue services. Signage should be provided to identify the power supply isolation controls and this should state:
āFIREFIGHTERS ELECTRICAL ISOLATION SWITCH FOR CAR PARK ELECTRIC VEHICLE CHARGING UNITSā
The signage should be conform to BS 5499-1.
The location(s) of power supply isolation controls serving EVCUs should be indicated on premises information provided for firefighters.
The power supply to all EVCUs should also be automatically isolated upon actuation of the fire warning and detection system or sprinkler system serving the car park in which they are located.
EVCUs should be provided with a suitable level of water resistance to ensure that they do not pose a hazard to firefighters should they become immersed in water, either as a result of the activation of the sprinkler system or firefighting operations.
It is our strong recommendation that car parks containing EVCUs should be provided with sprinkler coverage in accordance with BS 9251:2021 or BS EN 12845:2015+A1, irrespective of whether a building is otherwise provided with a sprinkler system.
General
Cycle storage areas
27. The proposals include a cycle storage area. It is our opinion that consideration is given to the storage (and potential charging) of electric bikes and electric scooters and the potential fire risk posed by these electric powered personal vehicles (EPPV)s which may be located within these areas. There is increasing evidence showing that EPPVs can spontaneously ignite and burn for long periods so there is an increased potential for toxic gases/smoke/fire spread. It is therefore our recommendation that adequate automatic fire suppression and smoke control systems for the area are necessary. As such storage would be deemed an ancillary area, we are of the view that it should be provided with a ventilated lobby in accordance with the recommendations given in clause 32 of BS 9991:2015. If EPPVs are to be stored in this location, then a fire risk assessment may identify this room as a place of special fire hazard and appropriate fire safety measures should be provided, taking into account the guidance provided in RC59 Recommendations for fire safety when charging electric vehicles.
FS_D_01HUB Rev 0, 05/10/2021 Page 7 of 9
28. We note that a significant number of photovoltaic cells are to be installed. Care should be taken to ensure that these are installed correctly to the manufacturerās recommendations due to concerns that have become known in regards to the fire hazards associated with poorly fitted installations. We recommend that āarc-faultā protection is fitted if possible, and also request that it is clarified whether there is any access (e.g. for maintenance) to the areas where the cells are situated.
It is our expectation that suitable isolation controls will be provided for use by firefighters. These controls should be accessible to firefighters and provided with suitable local signage to identify their location. The location of isolation controls should also be shown on premises information plans provided in a Secure Information Box or equivalent operational/emergency information pack provided for fire and rescue service use, as appropriate.
29. We note that the design includes proposals for green/living building envelope elements. We presume that you, as the approving authority, are satisfied that the proposed green/living building elements do not conflict with functional requirement B4 of the Building Regulations or Greater London Authority Town and Country Planning policy with regard to combustible elements external wall and roof construction.
It is our expectation that the fire performance and fire safety of green/living building envelope elements will be considered as part of the fire safety strategy for the proposed development. We refer you to guidance such as that given in the Green Roof Organisation (GRO) Green Roof Code (2014) and the Department for Communities and Local Government (DCLG) guidance on Fire Performance of Green Roofs and Walls (August 2013), referenced in Approved Document B.
Regulation 38 (Building Regulations)
30. Where applicable, we presume that you, as the BCB and approving authority, will check to ensure that adequate fire safety information (as detailed in Section 17 of Approved Document B, Volume 1/Section 19 of Approved Document B, Volume 2) will be issued to the responsible person for the premises at the completion of the project, or when the building or extension is first occupied.
(4) Expected outcome of consultation
Based on the nature of the items raised above in sections 1 to 3:
ā We would expect to be consulted further to this letter due to the significant issues raised in relation to matters under The Order and/or Building Regulations. In our view further information should be provided in regard to the following:
Comments numbered 3, 4, 6, 8, 9, 11, 13, 19, 21, 23, 24, 25
Notwithstanding the above, we presume that all comments/observations raised in this consultation letter will be forwarded to the client/project design team for consideration.
The above observations are in relation to the current proposal and may not be relevant to any future proposal.
Any queries regarding this letter should be addressed to FSR-AdminSupport@london-fire.gov.uk. If you are dissatisfied in any way with the response given, please ask to speak to the Team Leader quoting our reference.
FS_D_01HUB Rev 0, 05/10/2021 Page 8 of 9
Yours faithfully,
Assistant Commissioner (Prevention & Protection)
Reply To: Building Design Consultation Hub (via FSR-AdminSupport@london-fire.gov.uk)
There is clear evidence that Automatic Water Fire Suppression Systems (AWFSS) can reduce the number of deaths and injuries from fire, as well as reducing the risk to firefighters.
The London Fire Brigade strongly encourages those who design, construct and approve residential and commercial buildings, to go beyond the minimum expectation of compliance and include AWFSS in a wider variety of buildings. There are also additional benefits to the inclusion of AWFSS in terms of property protection, environmental protection and business continuity.
Further guidance can be found on the Brigadeās website.
FS_D_01HUB Rev 0, 05/10/2021 Page 9 of 9
FH090-151015 appendix
latest
r
Buildzone tracker/report
TECHNICAL AUDIT
SITE INSPECTION REPORT
Approved Consultant Services Limited
Tel: 020 7079 1028
Buildzone Ref Number: BZ9084931
Address: Project Honey Eden Street Kingston KT1 1ER
Description: NewDevelopmentof2xOfficeBlocksand1 x Car Parking Block
Surveyor: Ahmet Ozcagli
Developer / Contractor Details:
Summary of Visit:
Developer Name: Globe Kingston Ltd
Contractor Name: McLaughlin & Harvey Ltd
Project ManagementName: Francis Hunter
Inspections Required: 27 (Twenty Seven)
Inspection No: 14 of 27
Date: Updated: 03.05.2024
Time on site: 11:00hrs
Surveyor Email: technical@approvedconsultant.co.uk aozcagli@approvedconsultant.co.uk
Photographs: Yes
Inspection Madewith Contractor / Developer: Yes
David Luntā 07885959943 ā David.lunt@francishunter.co.uk
Luke Nurserā 07568188829 ā luke.nurser@francishunter.co.uk
Farid Safavi ā 07843368758 ā farid.safavi@francishunter.co.uk
Joe Gooden - joe.gooden@build-zone.com
Nick Sullivan ā nick.sullivan@towergate.co.uk
General Site Layout:
Approved ConsultantServices Ltd Page 1 of 5
Inspection Type: Commencement ā Substructure ā Drainage ā Damp proofing ā Superstructure ā Fire ā Services ā Intermediate ā Stage ā Completion ā Weather: Overcast 12°C
Site visit carried out in company of contractor site manager.
Block A:
Drylining fire stopping progressed up to 9th floor.
MEP works ongoing at all floors.
Prefabricated faƧade panel installations commenced at 2nd floor progressed partially up to 6th floor.
East elevation CP panel installations over SFS and steel has progressed up to roof level.
Roof heat insulation works 90% completed. Roof floor cladding works 80% completed.
FaƧade heat insulation installations at roof levelongoing with render.
Ground and 1st floor curtain wall installations ongoing.
Block B:
Drylining works mostly complete.
Drylining fire stopping progressed up to 8th floor.
MEP works ongoing at all floors.
Prefabricated panel installation progressed partially up to 8th floor.
Ground and 1st floor curtain wall profile and glazing installations ongoing.
Roof level heat insulation and raised floor installations ongoing.
Raised access floor installations progressed up to 6th floor.
Suspended ceiling panel installations commenced and ongoing at several levels.
Block C:
FaƧade panel installations ongoing at several elevations.
Concrete floor works completed from ground to top floor.
Roof waterproofing works completed.
Approved ConsultantServices Ltd Page 2 of 5
.11 For Block B, provide structuralengineerās written approval of fire door opening core wall cutting works.
.13 ProviderepairmethodstatementandimagesofrepairsatBlockCprecastelements.
.17 Clientis advisedto provide repair methodology and images ofrepair applications to floor concrete at Block C roof level.
.18 Clientis advisedto provide repair methodology and images ofrepair applications to floor concrete at Block C 1st level.
.26 Notable images from visit on 03.05.2024
Information required
Information required
Information required
Information required
Observations
Approved ConsultantServices Ltd Page 3 of 5 1.00
Current Status
Observations / Remediation / Comments
Approved ConsultantServices Ltd Page 4 of 5
2.00 Technical Submissions
.01
Provide pre-pour QA inspection records for slab and columns.
.02 Provide Building Control Site inspection reports periodically, throughout the course of construction. (Provided up to 06.2023)
.03
.04
.05
.06
.07
Provide Full Architectural Package (RIBA Stage 5)
Provide Full Structural Package and Calculations (RIBA Stage 5)
Provide pile integrity tests certificates.
Provide Cube test results.
ProvideHeatsoakandimpacttestcertificationforallexternallyglazedunitsthatare not serviceable from eitherground floor or from within
.08 Provide Flat roof and terracewaterproofing IBG
.09 Confirm full list of external cladding materials proposed.
.10 Provide window & external door manufacture guarantee.
.11
Provide QA records for precast elements from manufacturer
3.00 Other matters arising (at time of inspection)
.01 Where applicable, minimum statutory documentation and certification required:
Pre-pour inspection records from site engineer
Building Controlsite inspection reports
Fire consultant QA records
Basement waterproofing QA records
Pile integrity test certs
Bolt checking QA records
Weld test certs
Cube test certs
Static load test certs
Basement waterproofing IBG
Terrace and flat roof IBG
BBA certification for any rainscreen cladding or brick slips
Glazing / curtain walling heat soak and impact testing certs
Building ControlCompletion Cert(s)
EPC
As built SAPS
Mechanical Ventilation certification
Chlorination certs
Gas/water/elec certs
Fire doorcompliance commissioning
Fire suppression, alarm commissioning
Sound tests
Air tests
Lift Commissioning
Drainage pressure testing (written confirmation from AI) & orCCTV
NEXT VISIT: 30.05.2024
Provided
Information required (ongoing)
Provided
Provided
Provided
Information required
Information required
Information required
Provided
Provided
Information required
Information required. (At completion of project)
Note
Approved ConsultantServices Ltd Page 5 of 5
TECHNICAL AUDIT REMEDIATION TRACKER
BuildzoneRef Number: BZ9084931
Address: ProjectHoney
InspectionsRequired: 27 (Twentyseven)
InspectionNo: 14 of 27 Eden Street
DateofInspection: 03.05.2024 Kingston KT1 1ER
Surveyor: Ahmet Ozcagli
Key: UrgentRemediation
Client is advised to provide belowinformation for works before site visit:
ā¢Provide images of works before visitincluding pile caps,foundations before concrete pour, floor slab before concrete pour,Core twin wall installations.
ā¢Provide pile integritytests certificates.
ā¢Provide pre-pour QAinspection records for foundations,slabs,columns and core wall installations.
1.02 Provide images of drainage works before backfilling.
Provide structural engineerās solution or approval for the low concrete coverage for steel over precastslab at Block A ground floor.
Provide structural engineerās solution or approval for the low concrete coverage for steel over precastslab at Block B ground floor.
Provide structural engineerās solution or approval for the low concrete coverage for steel over precastslab at Block C ground floor.
For Block B,provide structural engineerās written approval of fire door opening core wall cutting works.
Provide repair method statementand images of repairs at Block C precast elements.
1.14 Provide images of Block C car park floors before concrete pours.
Client is advised to provide repair methodologyand images of repair applications to floor concrete at Block C roof level.
Client is advised to provide repair methodologyand images of repair applications to floor concrete at Block C 1st level.
1.20 Provide waterproofing leak tests for Block A.
1.21 Provide waterproofing leak tests for Block B.
1.23 Provide waterproofing leak tests for Block C. 2.00TechnicalSubmissions
2.01 Pre-pour QA inspection reports
2.02 Ongoing - Building control inspection records Provided & Ongoing
2.03 Full RIBA Stage 5 Architectural Drawings
Informative Remediation Resolved No. 1.00Observations/Remediation/Comments 1.01
1.05 1.07 1.08 1.11 1.13
1.17 1.18
RemediationCurrentStatus
Approved Consultant Services
2.04 Full RIBA Stage 5 Structural Drawings and Calcs
2.05 Pile integritytest results
2.06 Cube testresults
2.07 Heat soak and impacttestglass specifications
2.08 Terrace and flat roof IBG
2.09 List of full cladding materials proposed
2.10 Windows & external door manufacture guarantees
2.11 Provide QA records for precast elements from manufacturer
3.00Othermattersarising(attimeofinspection)
3.01 Provide all statutoryand certification documentation at projectcompletion
inline with technical reporting
Pre-pour inspection records from site engineer
Building Control site inspection reports
Fire consultant QA records
Basementwaterproofing QA records
Pile integritytest certs
Bolt checking QA records
Weld testcerts
Cube testcerts
Static load testcerts
Basementwaterproofing IBG
Terrace and Flat roof IBG
BBA certification for anyrainscreen cladding or brick slips
Glazing / curtain walling heat soak and impacttesting certs
Building Control Completion Cert(s)
EPC
As built SAPS
Mechanical Ventilation certification
Chlorination certs
Gas/water/elec certs
Fire door compliance commissioning
Fire suppression,alarm commissioning
Sound tests
Air tests
Lift Commissioning
Drainage pressure testing (written confirmation from AI) & or CCTV
Approved Consultant Services