YVR PARKADE
Vancouver, British Columbia
Days to Produce
Number of Panels
Project Details
200
2190
Days to Erect Shell
Total M3 Concrete
Eagle Builders was chosen to erect this six-level, 2196 stall parkade structure because of our production capacity and production quality which included utilizing high-quality steel forms.
118
13, 000
Footprint
Useable SQ FT
178, 000 sq ft
855, 000
In order to move our product from Red Deer, Alberta to New Westminster, British Columbia, Eagle Builders had to come up with a comprehensive railway logistics plan which included constructing a rail siding in Red Deer, complete with two 20 ton overhead cranes, implemented impact testing and securement designs for safe transport. In total 525 rail cars of precast were transported to site. The project was installed in 111 days on site, and was a total of XXXX pieces.