BRID CANAL BRIDGE

Next Article
YVR PARKADE

YVR PARKADE

Taber, Alberta

3 days to install 24 girders

Advertisement

8 days precast production

4145 sq ft

SL510 type bridge

148 m3 of concrete used 14 and 12 meter long girders

The Bow River Irrigation District Canal Bridge was constructed to meet rigorous timeline requirements in 2021. Despite a challenging installation process, Eagle was able to convert the 5 span bridge to a 3 span bridge with no topping required.

Foothills Medical Center Parkade

Calgary, Alberta

Project Details

The Parkade was awarded to Eagle Builders at the end of 2016 by a general contractor on behalf of Alberta Health Services.

The project consists of 2034 parking stalls in 4 levels with 7 months of dedicated production and 8 months of on-site precast concrete installation.

The parkade is comprised of a variety precast concrete components including: inverted tees, double tees, columns, spandrel panels, and wall panels.