Alabama 25, December 2, 2020

Page 1

Huntsville

20 Decatur

State Supplement sponsored by:

231

65

72 Florence

2

72

565 59

43 231

31

5

ALABAMA STATE EDITION

431

Gadsden

78 59

A Supplement to:

Anniston

20

Birmingham Bessemer

82 Tuscaloosa

65 280

20 82 Auburn

80

85

Selma

Phenix City

Montgomery

82 65

231

43 84 431 331

84

84 52

SHIP WITHIN 48 HOURS

Dothan

31

45 65 98

SAME DAY PARTS AVAILABILITY

Mobile

10

®

December 2 2020

24 HOUR TECHNICAL SUPPORT BACKED BY A 75 YEAR BUSINESS Thousands in Service!

Vol. XXI • No. 25

“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479

Affordable Price. Premium Service.

CALL 800-367-4937 *On approved credit • Financing Available

The majority of the work will be paid for with federal emergency funds because the governor declared a flooding event a disaster and signed a proclamation qualifying it for federal emergency aid.

With the highway now open to motorists, crews are working to complete construction efforts on U.S. 231 near Huntsville, Ala., nine months after a landslide caused major damage. Repairs were made two months ahead of schedule on both roadways of U.S. 231 between Lacey’s Spring and Morgan City, including the twin bridges constructed to safely span the slide on Brindlee Mountain. “It’s extremely satisfying that such a large magnitude of work could be completed so quickly,” said Curtis W. Vincent, north region engineer of the Alabama Department of Transportation (ALDOT). “The contractor, Brasfield and Gorrie, had a great plan, and implemented it by working seven days a week, 24 hours a day. It was quite an accomplishment, and won them a $2.5-million-dollar bonus.” Currently, final grading and work on topsoil of slopes

By Cindy Riley

CEG CORRESPONDENT

beneath the bridges is taking place. Dirt work is almost complete, with the entire project expected to wrap up by the end of December. Vincent explained that Highway 231 was forced to close immediately after the landslide, due to destruction of the asphalt pavement within the roadway. “Major cracks and elevation differentials existed that made the roadway impassable for the traveling public,” he said. “The entire roadway prism seemed to move downslope, as the colluvial material beneath the roadbed moved downward on the mountain.” Detour routes were established for approximately 15,000 vehicles per day that commute along the route to and from Huntsville. Officials let an emergency contract the following morning, to begin removal of the asphalt and base in the area of the slide, so that the geotechnical staff could begin evalu-

ation. “The site was considered dangerous, because movement continued to occur,” said Vincent. “Instrumentation was installed so that the movement could be monitored as workers took precautions as work progressed. Materials and Test Bureau of ALDOT organized and performed testing, along with consultants from Dan Brown and Associates and Auburn University.” During much of the construction, motorists were detoured onto county roadways. Vincent said the traveling public had to adapt to a 16-mi. detour (14-mi. net), but were surprised that crews constructed the two bridges and had the roadway open within four months of beginning construction. The slide was the result of heavy rainfall back in February. Further investigation revealed a slide plane roughly 50 ft. see LANDSLIDE page 6


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.