Huntsville
20 Decatur
State Supplement sponsored by:
231
65
72 Florence
2
72
565 59
43 231
31
5
ALABAMA STATE EDITION
431
Gadsden
78 59
A Supplement to:
Anniston
20
Birmingham Bessemer
82 Tuscaloosa
65 280
20 82 Auburn
80
85
Selma
Phenix City
Montgomery
82 65
231
43 84 431 331
84
84 52
SHIP WITHIN 48 HOURS
Dothan
31
45 65 98
SAME DAY PARTS AVAILABILITY
Mobile
10
®
December 2 2020
24 HOUR TECHNICAL SUPPORT BACKED BY A 75 YEAR BUSINESS Thousands in Service!
Vol. XXI • No. 25
“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Alabama Connection • Rich Olivier, Atlanta, GA • 1-800-409-1479
Affordable Price. Premium Service.
CALL 800-367-4937 *On approved credit • Financing Available
The majority of the work will be paid for with federal emergency funds because the governor declared a flooding event a disaster and signed a proclamation qualifying it for federal emergency aid.
With the highway now open to motorists, crews are working to complete construction efforts on U.S. 231 near Huntsville, Ala., nine months after a landslide caused major damage. Repairs were made two months ahead of schedule on both roadways of U.S. 231 between Lacey’s Spring and Morgan City, including the twin bridges constructed to safely span the slide on Brindlee Mountain. “It’s extremely satisfying that such a large magnitude of work could be completed so quickly,” said Curtis W. Vincent, north region engineer of the Alabama Department of Transportation (ALDOT). “The contractor, Brasfield and Gorrie, had a great plan, and implemented it by working seven days a week, 24 hours a day. It was quite an accomplishment, and won them a $2.5-million-dollar bonus.” Currently, final grading and work on topsoil of slopes
By Cindy Riley
CEG CORRESPONDENT
beneath the bridges is taking place. Dirt work is almost complete, with the entire project expected to wrap up by the end of December. Vincent explained that Highway 231 was forced to close immediately after the landslide, due to destruction of the asphalt pavement within the roadway. “Major cracks and elevation differentials existed that made the roadway impassable for the traveling public,” he said. “The entire roadway prism seemed to move downslope, as the colluvial material beneath the roadbed moved downward on the mountain.” Detour routes were established for approximately 15,000 vehicles per day that commute along the route to and from Huntsville. Officials let an emergency contract the following morning, to begin removal of the asphalt and base in the area of the slide, so that the geotechnical staff could begin evalu-
ation. “The site was considered dangerous, because movement continued to occur,” said Vincent. “Instrumentation was installed so that the movement could be monitored as workers took precautions as work progressed. Materials and Test Bureau of ALDOT organized and performed testing, along with consultants from Dan Brown and Associates and Auburn University.” During much of the construction, motorists were detoured onto county roadways. Vincent said the traveling public had to adapt to a 16-mi. detour (14-mi. net), but were surprised that crews constructed the two bridges and had the roadway open within four months of beginning construction. The slide was the result of heavy rainfall back in February. Further investigation revealed a slide plane roughly 50 ft. see LANDSLIDE page 6
Page 2 • December 2, 2020 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide
Atlanta, GA 404.469.7210 Birmingham, AL 205.841.6666 Madison, AL 256.350.0006 Mobile, AL 251.633.4020 Montgomery, AL 334.262.6642 Oxford, AL 256.832.5053 Tuscaloosa, AL 205.848.4147 Pensacola, FL 850.479.3004
Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • December 2, 2020 • Page 3
Page 4 • December 2, 2020 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide
Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • December 2, 2020 • Page 5
Page 6 • December 2, 2020 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide
Destruction of Asphalt Pavement Causes Huntsville Highway Closure LANDSLIDE from page 1
underground, affecting roughly 1,000 ft. of the bifurcated highway in each direction. As with all projects, safety was a major concern for crews on the scene. “Highway construction is always dangerous,” said Vincent. “All necessary precautions were taken.” Work on the $22.5 million project has been conducted in phases. During the first stage of repair, Reed Contracting removed approximately 220,000 cu. yds. of dirt and debris from the slide area. Material was taken to a borrow pit approximately 5 mi. away in Huntsville. “Reed Contracting is a local contractor with excellent work history with ALDOT,” said Vincent. “They had manpower and equipment locally that was utilized for the removal of dirt work prior to the bridge project. Brasfield and Gorrie also utilized subcontractors, and their personnel to implement a well thought out plan to construct the bridges. Brasfield and Gorrie was extremely professional to work with, along with construction inspection provided by Volkert and Associates.” A variety of heavy machinery was needed on the project, including equipment to remove earth and construct the foundations for the bridges. Each bridge is approximately 1,000 ft. long and 44 ft. wide, accommodating two 12-ft. lanes with 10-ft. shoulders, and constructed on stable foundations consisting of massive drilled shafts socketed in solid rock beneath the landslide. Vincent noted that the drilled shaft work for the 30-plus columns has been the most challenging part of the job. The extensive drilled shafts were anchored into bedrock 30 to 40 ft. below the surface. The project required 32 drilled shafts, with a 9.5 ft. diameter. The task was considered crucial to the project’s overall success. “The shafts along with the accompanying concrete and steel anchored these structures to solid bedrock to prevent any future movement,” said Vincent. “This project demonstrates the ability to accomplish huge tasks once a good plan
is established, and the contractor supplies the proper equipment and crews to achieve their goals.” More limited cracking actually occurred in February 2019. According to the ALDOT, measures to address the landslide weren’t taken then, because the problem had yet to be completely identified. More in-depth repairs to the damaged pavement weren’t made because, without a solution to correct the underlying issue, the possibility of further subterranean movement meant potential repeat road damage. Recognizing that an underlying geotechnical issue was at work, ALDOT installed instruments to monitor the area and obtain a better understanding of the extent, cause and methods to address the problem. While some additional minor repairs were necessary as the new pavement over the crack settled, the instruments installed on site detected very little movement during the remainder of the year. If ALDOT had more details about the problem in February 2019, the suggested repair then would have been the same as it is today. The majority of the work will be paid for with federal emergency funds because the governor declared a flooding event a disaster and signed a proclamation qualifying it for federal emergency aid. In a statement, Gov. Kay Ivey applauded the September 2020 reopening, which was marked by a ceremony attended by state legislators and other officials. “I am proud that the people of Morgan County and surrounding areas will now be able to enjoy an easier and smoother commute on Highway 231,” said Ivey. “Not only has a repair and improvement been made to the infrastructure, but it was completed more than two months ahead of schedule, thanks to the state working hard with a private sector partner. “We remain committed to enhancing Alabama’s transportation infrastructure to ensure every Alabamian in all parts of the state can reap the benefits. This is certainly exciting and welcome news.” CEG
Work on the $22.5 million project has been conducted in phases. During the first stage of repair, Reed Contracting removed approximately 220,000 cu. yds. of dirt and debris from the slide area.
Each bridge is approximately 1,000 ft. long and 44 ft. wide, accommodating two 12-ft. lanes with 10-ft. shoulders, and constructed on stable foundations consisting of massive drilled shafts socketed in solid rock beneath the landslide.
With the highway now open to motorists, crews are working to complete construction efforts on U.S. 231 near Huntsville, Ala., nine months after a landslide caused major damage.
Long-Awaited Widening of Ala. Highway 157 Begins in Cullman State legislators and community stakeholders joined Cullman city officials and the Alabama Department of Transportation (ALDOT) in October to break ground on the long-awaited Alabama Highway 157 widening project between U.S Highway 31 and Alabama 69 in Cullman, Ala. The kickoff event was held on state rightof-way near Lake Catoma, where a bridge for the future roadway was previously constructed. Chilton Contractors Inc., headquartered in Clanton, Ala., began work on the construction of a two-lane northbound roadway several days later. The general contractor won the $14,895,273 contract in July to build the additional lanes, including drainage, grading, pavement, traffic signals and multi-use paths. The existing two-way road will serve
as the future southbound roadway. The project is funded through a Better Utilizing Investments to Leverage Development (BUILD) grant as well as a combination of state, city and other federal funding. “Teamwork was the key,” said Cullman Mayor Woody Jacobs. “There are so many people involved, and all the stars aligned.” Bridges for the northbound roadway over Lake Catoma and the CSX railroad were completed in 2013. But at that time, the absence of any adjustment to state highway funding was forcing ALDOT to focus increasingly on maintenance of existing infrastructure over costly expansions to Alabama’s transportation network. Only minor traffic impacts to traffic on the existing roadway are anticipated during the
initial stages of construction. Throughout the project, which is anticipated to take about two years, two lanes of AL 157 will remain open whenever possible, but motorists are advised of the possibility of occasional lane closures with traffic directed by flaggers or a pilot car. “This infrastructure project is one of the most highly anticipated in Cullman’s recent history,” said state Sen. Garlan Gudger, who represents District 4, which includes Cullman. “Without adequate funding for transportation projects, such as the federal BUILD grant and Rebuild Alabama, this would not be possible. I am proud to say that because of this funding, what was once a dream is now a reality. The teamwork displayed to
connect this final link of Alabama 157 is not just an achievement for Cullman County, but for all North Alabama.” Gudger was joined at the groundbreaking for the AL 157 project by state representatives Randall Shedd, Corey Harbison and Scott Stadthagen. “This is obviously a major project and it impacts all four counties in my legislative district,” Shedd said. “It’s been my number one legislative priority and working with Sen. Gudger and the legislative delegation has been fruitful. I appreciate Gov. Kay Ivey and ALDOT Director John Cooper’s approval and our congressional delegation for helping to secure this rare and substantial grant. Working together with state, federal and city funding made it a reality.”
Construction Equipment Guide • Alabama State Supplement • www.constructionequipmentguide.com • December 2, 2020 • Page 7
Designed with Maintenance in Min nd You o r ability to effic fficiently process materials on n site dep d end ds on reliable l equipment. KPI-JCI and Astec Mobile Screens design and manufacture a wide selection of mobile crushers, screens and conveyors designed with simplicity for easy operation and maintenance to keep you up and running. For unmatched customer support, our dedicated experts and distribution network will help you find a solution that fits your needs. Learn more at kpijci.com/track-mount
Stone Equipment ent Company, Inc. 210 West Blvd. 1797-A Fulton Spring Rd. Montgomer y, AL 36108 Alabaster, AL 35007 844 -786- 6373 844 -786- 6373 www.stoneeq quipmentco.com q p
Page 8 • December 2, 2020 • www.constructionequipmentguide.com • Alabama State Supplement • Construction Equipment Guide