Progressive Companies Proposal - City of Pontiac RFP schedule and fee

Page 1


City of Pontiac

Design-Build for Neighborhood Mini Parks

A People-First Approach to Developing Vibrant Communities

Project Schedule

The following represents the anticipated project schedule, assuming that the City of Pontiac and AHJ’s staff can provide feedback and input at the necessary intervals, or within one (1) week from receipt of deliverables:

DESIGN SCHEDULE

Phase 1:

Concept / Program Verification: 2-3 weeks with up to 2 steering committee meetings

Schematic Design: 4-5 weeks with up to 3 steering committee meetings

Phase 2:

Design Development: 4-5 weeks with 1-2 steering committee meetings

Construction Documents: 5-6 weeks with 1-2 steering committee meetings

Bidding, contracts, and submittals: 4-6 weeks

CONSTRUCTION SCHEDULE

See attached Schedule our Team anticipates starting construction after Scopes and Budgets are agreed to by the City of Pontiac. We anticipate work can proceed early March 2026, and the Full Parks will be constructed by the end of July 2026. We presented Option A and Option B for proceeding on the 4 Partial Parks since the exact scope cannot be quantified until final designs are determined based on available funding. Option A would commence immediately after the 4 Full Parks are complete and be finalized by December 2026. Option B shows the anticipated schedule assuming an earlier agreed to Design and Scope with City through an expedited review to finalize the remaining funding for the 4 Partial Parks. This Option shows concurrently working on the last Full Park with the First Partial Park and results in a late Fall 2026 overall completion. Option B may be more advantageous for the City to help mitigate their overhead costs. Our Team plan is to work with the City to accomplish an earlier start on the 4 partial parks.

Approximately 10 months, with each of the eight parks will have individual project specific schedules, and depending on final scopes of work will dictate work duration. As previously, noted above our intent is to complete parks in accordance with priority, but with City approval may work concurrently on multiple parks to meet deadlines. All work to be completed and any ARPA funds will be spent and all parks completed by December 31st, 2026.

Post Construction / Project Closeout: 2-4 weeks

Fredrik Meijer Gardens, Grand Rapids,

Negotiation/Execution

Design Schedule

City of Pontiac Mini Parks RFP (Progressive Companies)

Concept/Program Verification (up to 2 steering committee meetings)

Schematic Design (up to 3 steering committee meetings)

Phase 2:

Design Development (1 or 2 steering committee meetings)

Construction Documents (1-2 steering committee meetings)

Issue for Bidding and Plan Review / Permits

Permit Issued

Bidding Construction

Prepare Work Scopes

Issue for Bids

Bidding

Post Bids and Preparation of Final Bid Tab

Owner Meeting for Approval to Proceed with Subcontracts and Construction

Subcontracts

Submittals Submit/Review/Approval

Construction 4Full Parks - Complete these 4parks 100%. Note: Assumed Scope Final Details Unknown at this time

Art Dunlap Park, Full Scope (Dist 1) (Pull Ahead Status)

Mobilize/Erosion Control/Site Security/Signage/Barricades

4 parking spots, 1HC parking spot

Demo F/R/P/S: concrete curb

Demo/Excavate/Backfill/Asphalt/Striping: parking pavement

Shift the Two Existing Bball Courts to the South

Demo/Excavate/Backfill/Asphalt/Striping

Install 4ea Relocated Hoops

Junior Hoops

Demo/Excavate/Backfill/Asphalt/Striping/Install 1ea Hoop

Install Earth Tone Play Equipment (5-12yr)

Demo/Excavate/Backfill

Install New Play Equipment and Wood Chip Surfacing

56 We Cannot Guarantee Actual Start Dates due to funding determining final scope. For this RFP show Start Date after 4Full Parks are 100% complete. We may be able to start sooner once final details are agreed to.

57 Indian Village Park, Partial Scope

Install Earth Tone Play Equipment (2-5yr)

Demo/Excavate/Backfill

Install New Play Equipment and Wood Chip Surfacing

Remove/Reinstall Reconfigured Asphalt Pathways

New Pavillion (assumed open pre-engineered/readily available open structure, no electrical, plumbing

Install Bleachers

Replace Fencing around Bball Courts

Install Trash Receptacles

Install Bike Rack

Install Basketball Central Sign

Install Grills

Remove Dead Trees (no new Irrigation or Landscaping is included since an agreed to survey will be

Screening landscaping at south edge

Punchlist/Cleanup/Demob

North Kiwanis Park, Full Scope (District 3)

Cherry Lawn Park, Full Scope (District 4)

Richardson Park, Full Scope (District Seven)

A: Construction 4Partial Parks

Village Park, Partial Scope (District 2)

Park, Partial Scope (District Six) Dawson Pond Park, Partial Scope (District Two)

Village Park, Partial Scope (District 2)

Park, Partial Scope (District Six)

Pond Park, Partial Scope (District Two)

Project Fee

Design & Engineering Fees

Art Dunlap Park, Full Scope (District 1) (Pull Ahead Status)

• $40,000 Design / Engineering Fee

• Approximately 265 hours staff time

• Up to 4 visits for Construction Administration

Indian Village Park, Partial Scope (District 2)

• $24,000 Design / Engineering Fee

• Approximately 160 hours staff time

• Up to 2 visits for Construction Administration

North Kiwanis Park, Full Scope (District 3)

• $28,000 Design / Engineering Fee

• Approximately 186 hours

• Up to 3 visits for Construction Administration

Cherrylawn Park, Full Scope (District 4)

• $32,000 Design / Engineering Fee

• Approximately 213 hours

• Up to 4 visits for Construction Administration

Baldwin Park, Partial Scope (District 6)

• $28,000 Design / Engineering Fee

• Approximately 186 hours

• Up to 3 visits for Construction Administration

Richardson Park, Full Scope (District 7)

• $32,000 Design / Engineering Fee

• Approximately 213 hours

• Up to 4 visits for Construction Administration

Dawson Pond Park, Partial Scope (District 2)

• $24,000 Design / Engineering Fee

• Approximately 160 hours staff time

• Up to 2 visits for Construction Administration

Fredrik Meijer Gardens, Grand Rapids, MI

Art Heaton Park, Partial Scope (District 6)

• $36,000 Design / Engineering Fee

• Approximately 240 hours staff time

• Up to 3 visits for Construction Administration

Total Design Fee: $244,000

As requested in the RFP 3.1.1 and 3.2 the following is our final percentage of construction cost for design engineering, construction administration and engineering, and the percentage for construction.

• Design Engineering = 6.5%

• Construction Administration and Engineering = 1%

• Construction Management Fee = 3%

Clarifications/Assumptions:

1. Site surveys will be provided by Owner in digital (AutoCAD) format. This shall include boundaries, topography, trees over 6” caliper at chest height, underground and overhead utilities, easements, vaults, and any existing improvements.

2. Community and stakeholder engagement is completed and has informed the proposed improvements / design concepts. Additional stakeholder engagement is not included in this proposal but can be accommodated as an additional service if needed.

3. A half-day project kick-off meeting will be facilitated by the consultant to visit the park sites and verify the improvement program for each facility. Design coordination meetings will occur virtually via Microsoft Teams on a bi-weekly basis through the completion of construction documents.

4. This proposal is based on the elements included in the preliminary concept plans. If additional improvements are needed, such as electrical service, lighting, water, irrigation, sanitary or storm sewers, restrooms, etc., design for these elements cab be provided for an additional service fee.

5. Construction administration assumes that multiple site visits will happen during the same day, i.e. 2-3 parks per site visit.

6. The Construction Management Fee does not include the required general conditions and general requirement costs of the project including but not limited to on-site part-time supervision, office staff, porta johns, temp power, overhead costs, insurances, bonding, etc. Once the scope of the projects are known, these costs will be included in the cost estimates based on each park.

7. In reference to the City of Pontiac's response to Progressive Companies prebid question related to the future parks, we have only included design and construction fees for the (4) partial parks and (4) full scope parks. Progressive Companies and the City of Pontiac will partner together with an option to extend the contract for future parks with consideration for additional fees and schedule.

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.