1 minute read

Process for Pre-Con, Pre-Drywall, Orientation and Final Signoff

Final Walk Orientation:

• Timing – Between one(1) and two(2) days prior to closing. Sales Advisor to coordinate via Outlook or Google calendar invite.

Advertisement

• Process - the purchaser and Project Manager and Sales Advisor will meet and review all items listed from the First Walk list and sign off that said items are complete to the satisfaction of the purchaser. All items identified by the purchaser and itemized on a punch list must be completed prior to closing.

Should there be any item or items which could not be completed due to something needing back ordered, said items will be added to a list to survive closing so long as all parties agree in writing. Sales Advisor to create an addendum for this when necessary.