Work involving maintenance and minor repairs of domestic and commercial premises. Organisational Details Company Name: Approval Date: Company Address: Next Review Date: Director / Manager Name: Contact Number: Type of SWMS: Generic (multiple projects, jobs, or work requests) ☐ Site specific (complete section below) ☐ Site Specific Details Principle Contractor: n/a ☐ Contact Number: n/a ☐ Site Manager or Supervisor Name: n/a ☐ Other
n/a ☐ Site Address: n/a ☐ n/a ☐ SWMS Details
risk work activities
this
Who
Workers
 Principle
 WHS
☐ Additional compliance measures: Pre-start Hazard Risk Assessment  Toolbox Talk  Workplace Safety Inspection ☐
Building Maintenance
Minor Repairs SWMS
PCBU’s:
What high
are covered by
SWMS? A risk of a person falling more than 2 metres The disturbance of or likely disturbance of asbestos Work on or near energised electrical installations or services Work on, in or adjacent to a road, railway, shipping lane or other traffic corridor used by traffic other than pedestrians What is the scope of the works? The Building Maintenance (Minor Repairs) Safe Work Method Statement (SWMS) outlines the main hazards and risks associated with maintenance and minor repairs of domestic and commercial premises including hazardous manual tasks, electric shock, exposure to hazardous substances, risks of falls, and working in residential premises and public areas. The SWMS provides details of the health and safety precautions (including protective equipment) necessary for minor building maintenance and repair work.
else was consulted/involved in preparing this SWMS?
/ employees
Contractor
Team
Page 2 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022 Sign off Person responsible for ensuring compliance with SWMS: Responsible persons signature: BHmayed Contact Number: Date: Training / Licencing Requirements Construction industry general induction (White Card)  Senior First Aid Training  Forklift Licence ☐ Traffic Control Ticket ☐ Asbestos Awareness ☐ Working with Asbestos of a Minor nature ☐ (Other): ☐ (Other): ☐ (Other): ☐ Personal Protective Equipment Safety boots  Eye protection  Respiratory equipment  Safety Helmet  Hearing protection ☐ Barricading and signage  Communication equipment  Long sleeve long pants  White night suits required on night shift ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ Chemicals PVC Cement ☐ Diesel Fuel ☐ Petrol Fuel ☐ Silicone Spray ☐ Multi-Purpose Grease ☐ Silicone ☐ MAPP Gas / LPG ☐ Oxygen / Acetylene ☐ Multi-Use Lubricant Spray (WD-40) ☐ Nitrogen ☐ Refrigerants ☐ (Other): ☐

Jurisdictions Safety Legislation

Act: Work Health and Safety Act 2011 (NSW)

Regulation: Work Health and Safety Regulation 2017 (NSW)

Legislation

Regulator

and Contact Number COP

Regulator: SafeWork NSW Number: 13 10 50

NSW 

Standards

•Managing Risks of Hazardous Chemicals in the Workplace

•First Aid in the Workplace

•Managing the Risk of Falls at Workplaces

•Confined Spaces

•Construction Work

•Managing Noise and Preventing Hearing Loss at Work

AS/NZS 1067: Sunglasses and fashion spectacles, AS/NZS 1270: Acoustics - Hearing protectors, AS/NZS 1337.4-6 Series: Personal eye-protection, AS/NZS 1715: Selection use and maintenance of respiratory protection devices, AS/NZS 2161.1-10: Occupational protective gloves, AS/NZS 2210.1-9 Series: Occupational protective footwear, AS/NZS 1800: Occupational protective helmets - Selection, care and use, AS/NZS 4501.1: Occupational protective clothing – General recommendations on selection, care, use and maintenance of protective clothing

Hierarchy of Controls Definitions

Elimination

Substitution

Isolation

This control measure involves eliminating or removing the risk in its entirety

This form of control involves substituting a safer process or material for the hazardous process/material found.

This control involves separating the hazard or hazardous work practice from employee’s other work areas. This may involve sectioning off the area by erecting barriers or by moving either the hazardous work practice or the „other‟ employees and their work practices.

Engineering

Admin

PPE

This method of control involves designing and/or adding physical safety features to plant or equipment.

This type of control is most effective when used in conjunction with measures mentioned above or as an interim control whilst more effective control measures are developed and implemented.

PPE is not a particularly effective control method and should only be used:

• When all other control measures are impractical; or

• In conjunction with other more effective, control measures.

Page 3
SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022

Determine, document and mark EXCLUSION ZONES

commencing. ● No-one is to stand directly in the drop zone of a load.

to

No-one is to be in an excavation whilst the plant is operating. ● Ensure that Safety Pins are in place before commencing any work. ● Ensure that plant is positioned in a manner that provides safe access/ egress and does not pose risk of collision. ● Ensure plant is operated on surfaces free from risk of rollover

Ensure that any additional equipment, (e.g. buckets, ramps, trailers, etc.) associated with plant are adequately stored or barricaded.

Workers

Page 4 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022 Risk Level Matrix Risk Analysis Consequence Likelihood Consequence C1 C2 C3 C4 Likelihood L1 1 1 2 3 L1 Highly Likely C1 Catastrophic L2 1 2 3 3 L2 Likely C2 Major L3 2 3 4 4 L3 Unlikely C3 Moderate L4 3 4 4 4 L4 Rare C4 Minor EXTREME RISK HIGH RISK MEDIUM RISK LOW RISK Building Maintenance # Job Step / Process / Activity Identify Hazards Risk Level (R) and the Residual Rating (RR) Identify Controls / Action Required Person Responsible L C R RR 1 Establishment of Site and Amenities • Non-Compliance with site safety rules L2 C2 HR LR ●
prior
work

6

Mobile plant

• Untrained workers

L2 C2 HR LR

• Only persons who are competent to do so are to operate mobile plant.

• Plant that does not require a person to hold a licence for high risk work to operate must only be operated by persons who have successfully completed a recognised training course provided by a RTO and have been assessed as competent in the operation of the plant.

Electricity Electrocution

Isolation procedures

7

L3 C2 HR LR

• All electrical work will be carried out only by licensed or registered electrical workers.

• Ensure that safety switch is provided on switchboard, and check operation before connecting leads to board. Provide portable safety switch if RCD is not supplied on switchboard.

• All electrical installations must be treated as “live” until isolation of the installation or circuit is tested and verified as “dead” by a licensed electrician.

• Note: closure of main switch will not be effective in cases where an addition supply of power may be present (e.g., supply from and adjoining property, solar panels, etc.)

• Do not attempt to carry out work involving electrical fittings or installations until specific circuit is verified as de-energised.

Workers

8

Electrical tools and equipment

• Electric shock

• Personal injury

L3 C2 HR LR

• All electric tools and equipment will be inspected, tested and tagged every 3 months. Inspect tools and check operation of controls daily before use. Faulty electric tools will not be used.

• Keep electric leads off ground to protect from damage.

• Visually inspect tools and cutters, drill bits, grinding discs, etc. for wear or damage before use. Do not use faulty or damaged tools.

• Wear eye protection when using power tools. Wear hearing protection id harmful noise levels will be generated. Wear respiratory protection (e.g., P1 particulate dust mask) when sanding or grinding.

Page 5 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022
Workers

9

Hazardous manual tasks

• Strains, personal injury

• Provide sufficient personnel or mechanical aids to handle and move large, heavy or awkward loads.

L2 C2 HR LR

Working at heights

• Risks of falls

• Falls of persons from ladders

• Use of portable work platforms

10

L3 C2 HR LR

• Provide safe means of transporting and moving loads on site to minimise manual movement of heavy items

• Provide safe means of access to and for working at heights and where a person may fall from one level to another.

• Ladders are to be an industrial type with a 120kg rating. Domestic ladders must not be use in a workplace.

• Single and extension ladders should be used for access only except for light work which can be carried out with one hand. Ladders should extend 1 metre above level being accessed and be secured against movement.

• Stepladders must be opened fully and braces locked in position before use. All feet must be in contact with a firm, stable surface. All tread surfaces must be clean and dry. Do not work from the top two steps of a stepladder.

• Folding portable work platforms must be opened fully and braces locked in position before use. All feet must be in contact with a firm, stable surface. All treads and platform surfaces must be clean and dry.

Workers

11

Use of hand tools

• Personal injury

• Inspect hand tools before use – ensure that handles are not loose or damaged, and that tool is in good condition for use.

• Do not use hand tools for any purpose other than that for which they were designed.

Page 6 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022
Workers

Painting work

Hazardous materials

• Lead-based paint

• Preparation of work areas

• Application of paints

L3 C2 HR LR

• Inspect surfaces to be painted to determine if asbestos products or lead-based paint may be present. Do not disturb the material until the presence or otherwise of the suspected substance is verified.

• Check for presence of lead-based paint in older premises. Have sample tested if in doubt.

• Avoid breathing dust when removing old paint from surfaces. Use sanding equipment fitted with dust collectors to reduce spread of dust. Wear eye and hearing protection when using powered sanders.

• Wear P1 particulate dust mask when sanding non-hazardous materials, or P2 particulate dust mask if hazardous materials are being disturbed or released.

• Prevent spread of dust generated during sanding to adjoining areas or neighbouring premises.

• Ensure adequate ventilation when applying all types of paints and coatings. Provide good ventilation to remove solvent vapours from area when applying solvent-based paints. Avoid spread of vapours to other areas.

• Avoid contact with skin and eyes when applying paints and coatings. Wash hands before eating, drinking or using the toilet.

Workers

Page 7 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022
14

Protection of persons and property

• Dust

• Noise

• Use of chemicals

• Hazardous materials

• Slips, trips and falls

• Unattended work areas

• Vehicles and plant

• Materials storage

L3 C2 HR LR

• Provide dust control where dust generated during work could spread to adjoining areas. Sweep up dust and vacuum area to remove dust. Wipe down wails and surfaces with damp cloth before vacating area.

• Limit use of noise generating tools where possible. Advice occupants of level of noise and estimated duration prior to commencing. Provide hearing protection to occupants and instruct in use if hazardous noise will be generated while premises are occupied.

• Use non-hazardous chemicals where practicable.

• Ensure good ventilation in areas where volatile chemicals are used. Minimise spread of vapours to adjoining areas. Eliminate ignition sources where flammable vapours may be present. Do not allow smoking or ignition sources while chemicals are being used.

• Prevent access into areas where hazardous materials (e.g., asbestos, synthetic mineral fibres, etc.) may be present.

• Ensure that areas are decontaminated and cleaned thoroughly before allowing re-entry or re-occupancy of the area.

• Ensure that any trip hazards are removed before allowing re-entry into work areas. Do not run power leads across floors, and tape down or place covers over leads if unavoidable.

• Do not leave tools, materials or equipment in areas where they could be accessed by persons at risk. Secure area where risks are present when area is unattended. Return all areas where occupation will occur to a safe condition at completion of work.

• Keep vehicles locked to prevent access by children or other at-risk persons.

• Remove keys from plant and ensure that it cannot be moved if left unattended. Ensure that buckets, etc., are on ground and crowded to minimise contact.

• Ensure that all materials are stored in a manner to prevent access to hazardous substances, rough or sharp edges, or falling objects. Securely cover materials where practicable.

Page 8 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022
15
Workers

16

Site clean-up and waste disposal Slips, trips and falls of persons L3 C3 MR LR

• Ensure that all scrap and waste material is removed and that area is clear of obstacles.

• Check safety of area before removing barricading.

Workers

Page 9 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022

SWMS Employee Sign off

Page 10 SWMS C05 - Building Maintenance – Minor Repairs SWMS | Revision: 01 | Issue date: 21/10/2022
This SWMS has been developed in consultation and has been read, understood, and signed by all workers undertaking the scope of works: Print Names: Signatures: Dates: