SWMS C03 - Excavation

Page 1

Excavation

Page 1 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022
Work involving use of heavy machinery to conduct excavation. Organisational Details Company Name: Approval Date: Company Address: Next Review Date: Director / Manager Name: Contact Number: Type of SWMS: Generic (multiple projects, jobs, or work requests) ☐ Site specific (complete section below) ☐ Site Specific Details Principle Contractor: n/a ☐ Contact Number: n/a ☐ Site Manager or Supervisor Name: n/a ☐ Other PCBU’s: n/a ☐ Site Address: n/a ☐ n/a ☐ SWMS Details What high risk work activities are covered by this SWMS? Work on,
or
to
traffic corridor
use
traffic
pedestrians Work
powered
Work
electrical
or services. What
works? Scope
work
work
installing, maintaining, repairing, altering, removing, or
construction painting services. Who else was consulted/involved in preparing this SWMS? Workers / employees  Principle Contractor  WHS Team ☐ Additional compliance measures: Pre-start Hazard Risk Assessment  Toolbox Talk  Workplace Safety Inspection ☐
SWMS
in
adjacent
a
in
by
other than
in an area with movement of
mobile plant.
on or near energised
installations
is the scope of the
of
includes the physical
of
adding to
Page 2 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022 Sign off Person responsible for ensuring compliance with SWMS: Responsible persons signature: B Hmayed Contact Number: Date: Training / Licencing Requirements Construction industry general induction (White Card)  Senior First Aid Training ☐ Forklift Licence ☐ Traffic Control Ticket ☐ Asbestos Awareness ☐ Working with Asbestos of a Minor nature ☐ (Other): ☐ (Other): ☐ (Other): ☐ Personal Protective Equipment Safety boots  Eye protection  Respiratory equipment  Safety Helmet  Hearing protection ☐ Barricading and signage  Communication equipment  Long sleeve long pants  White night suits required on night shift ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ (Other): ☐ Chemicals PVC Cement ☐ Diesel Fuel ☐ Petrol Fuel ☐ Silicone Spray ☐ Multi-Purpose Grease ☐ Silicone ☐ MAPP Gas / LPG ☐ Oxygen / Acetylene ☐ Multi-Use Lubricant Spray (WD-40) ☐ Nitrogen ☐ Refrigerants ☐ (Other): ☐

Legislation

Jurisdictions Safety Legislation Regulator and Contact Number

Act: Work Health and Safety Act 2011 (NSW)

Regulation: Work Health and Safety Regulation 2017 (NSW)

Regulator: SafeWork NSW Number: 13 10 50

•Managing Risks of Hazardous Chemicals in the Workplace

•First Aid in the Workplace

COP NSW 

•Managing the Risk of Falls at Workplaces

•Confined Spaces

•Construction Work

•Managing Noise and Preventing Hearing Loss at Work

Standards

AS/NZS 1067: Sunglasses and fashion spectacles, AS/NZS 1270: Acoustics - Hearing protectors, AS/NZS 1337.4-6 Series: Personal eye-protection, AS/NZS 1715: Selection use and maintenance of respiratory protection devices, AS/NZS 2161.1-10: Occupational protective gloves, AS/NZS 2210.1-9 Series: Occupational protective footwear, AS/NZS 1800: Occupational protective helmets - Selection, care and use, AS/NZS 4501.1: Occupational protective clothing – General recommendations on selection, care, use and maintenance of protective clothing

Hierarchy of Controls Definitions

Elimination

Substitution

This control measure involves eliminating or removing the risk in its entirety

This form of control involves substituting a safer process or material for the hazardous process/material found.

Isolation

Engineering

This control involves separating the hazard or hazardous work practice from employee’s other work areas. This may involve sectioning off the area by erecting barriers or by moving either the hazardous work practice or the „other‟ employees and their work practices.

This method of control involves designing and/or adding physical safety features to plant or equipment.

Admin

PPE

This type of control is most effective when used in conjunction with measures mentioned above or as an interim control whilst more effective control measures are developed and implemented.

PPE is not a particularly effective control method and should only be used:

• When all other control measures are impractical; or

• In conjunction with other more effective, control measures.

Page 3
SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022

from populated areas, schools and high traffic areas. • Exclusion zone set up around the site set up area. • Traffic control conducted by ticketed traffic controllers. Refer to Traffic and Pedestrian Management SWMS-008). • Ensure all vehicles are parked legally (not in No Stopping and not over driveways or in a location which is obstructing traffic. • All staff are to wear PPE (hard hat,

Page 4 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022 Risk Level Matrix Risk Analysis Consequence Likelihood Consequence C1 C2 C3 C4 Likelihood L1 1 1 2 3 L1 Highly Likely C1 Catastrophic L2 1 2 3 3 L2 Likely C2 Major L3 2 3 4 4 L3 Unlikely C3 Moderate L4 3 4 4 4 L4 Rare C4 Minor EXTREME RISK HIGH RISK MEDIUM RISK LOW RISK Excavation # Job Step / Process / Activity Identify Hazards Risk Level (R) and the Residual Rating (RR) Identify Controls / Action Required Person Responsible L C R RR 1 Establishment of Site and Amenities • Non-Compliance with site safety rules L2 C2 HR LR
Use this Safe Work Method Statement in conjunction with any other relevant Safe Work Method Statement.
and
• Location of Amenities are to be pre-determined
setup away
visibility vest and safety boots, safety glasses and gloves). Workers

2

Plant Set Up

• Mechanical Issues with Machine.

• Machine Operator Inexperience.

• Overhead Power Cables.

• Loading and Unloading of Machine from Truck L2 C2 HR LR

• No person is to ever work alone on an excavation job if the job is ranked as a medium or high risk.

• Machine Operator to conduct daily visual prestart inspection of machine and report any issues.

• Plant is to be maintained in accordance with manufacturer's specification and all records kept for verification if requested.

• Only Operators that hold a verification of competency can excavate.

• Workers to be made aware of overhead clearance heights and requirements.

• Tiger tails and a spotter to be in place when work activity is being undertaken in close proximity to overhead powerlines.

• Trucks parked in areas where no cables are above whilst machines are being unloaded.

• Ensure ramps are placed in correct positions and locking pins correctly used.

• Traffic Controllers to control vehicles movements in the area, especially when loading or unloading machines.

• Pre-determined unloading / loading zone

• Pre-start toolbox talk/risk assessment completed covering site evacuation, excavation emergency response and any other site-specific hazards. Be aware of prevailing weather conditions. Implement measures to prevent polluted water runoff entering watercourses.

• B Type first aid kit present

Workers

Page 5 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022

3

Check for presence of existing services.

• Electrocution, building / environmental damage Adjacent exposed live terminals.

• Electrical shock/Burns

• Falls

• Exposure to work site danger Serious impact injuries

• Cuts & abrasions

• Harm to others

L2 C2 HR LR

• Conduct ground search before breaking any ground. Use ground search contractor or Dial 1100 for dial before you dig.

• Site familiarisation. Know nearest live points at all times. Where necessary, either place barricades between personnel and live terminals or cover with appropriate plastic sheeting.

• Precautions are to be taken by operators when moving plant to avoid contact with any overhead conductors. Tiger Tails and a spotter to be in place when work activity is being undertaken in close proximity to overhead power lines.

• Work area to be clearly defined using barriers and signs.

• Access to work area only via specified route.

• Spotter to be used where necessary to ensure Limits of Approach is maintained.

• If asbestos is found, work is to cease and the asbestos management plan (AMP) must be followed. All personnel working in excavation are trained in identifying asbestos prior to work.

Workers

4

Fall Prevention

• Falls L2 C2 HR LR

• All excavations are to be protected in such a manner so as to prevent any person falling into the excavation.

• In addition to the primary 2-metre-high site fence where the potential to fall greater than 1.5 metres exists, in this case Para webbing / Bunting or similar should be positioned at least 2 metres from the edge of the hazard and be adequately supported. Hazard tape is not acceptable.

• Provide alternate pathway for public to access their route safely.

Workers

5

Back Filling Excavation/Trench

• Collapse of Excavation / Trench

• Underground Services

• Manual Handling

L2 C2 HR LR

• All workers to be out of excavation / trench prior to back filling.

• Plant operator to approach excavation / trench at 90 to the side.

• Plant operator to back fill in layers so as shoring can be gradually lifted if applicable.

• Exclusion zone to be set up around the works area for the safety of motorists and pedestrians prior to commencement

Workers

Page 6 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022

SWMS Employee Sign off

Page 7 SWMS C03 – Excavation SWMS | Revision: 01 | Issue date: 21/10/2022
This SWMS has been developed in consultation and has been read, understood, and signed by all workers undertaking the scope of works: Print Names: Signatures: Dates:

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.