Schedule
4
Pm clinic Initialization of KOMTRAX Check of cab pressurization
Total work time
Workers
Work time
Wrecker truck
Arrangement of workplace
Delivery
Cleaning and touch-up
Maintenance
· · ·
Installation of blade to chassis Final assembly inspection and supply of oil and grease
Assembly of blade
Installation of ROPS
Interior work and finishing work
Installation of operator's cab
Installation of track
Connection of ripper hoses
Installation of sub-ripper and main ripper
Check of starting operation of engine
Installation of track frame
Unloading · Installation of track · Installation of stand · Installation of chassis · Unloading of other parts
Item
25-ton * 2 trucks 8 4 32H
1st day
25-ton * 1 truck 8H 2 16H
2nd day
0 4H 2 8H
3rd day
Assembly procedure, necessary equipment, and schedule
Assembly procedure, necessary equipment, and schedule A change of the schedule caused by weather is not considered. The special work in the field shall be adjusted separately.