
1 minute read
Assembly procedure, necessary equipment, and schedule
A change of the schedule caused by weather is not considered. The special work in the field shall be adjusted separately.
1st day 2nd day 3rd day 25-ton * 2 trucks 25-ton * 1 truck 0 8 8H 4H 4 2 2 32H 16H 8H
Schedule
Item
Unloading · Installation of track · Installation of stand · Installation of chassis · Unloading of other parts Installation of track frame
Check of starting operation of engine
Installation of sub-ripper and main ripper Connection of ripper hoses Installation of track Installation of operator's cab Interior work and finishing work Installation of ROPS Assembly of blade
Installation of blade to chassis Final assembly inspection and supply of oil and grease · Pm clinic · Initialization of KOMTRAX · Check of cab pressurization Maintenance Cleaning and touch-up Delivery Arrangement of workplace Wrecker truck Work time Workers Total work time