90 80
OHIO STATE EDITION
6
A Supplement to:
422
6 80 24
6
4
71
76
199 30 30 75
68
30 77
71 23 22 68
4
70 70
®
70
22 71
75
77
27
July 16 2016
22 74
50
50 25
Vol. XVIII • No. 15
35
52
“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640
ASI Continues $110M Rebuild of Buckeye Lake Dam
ASI Constructors Inc., a heavy-civil engineering contractor specializing in the construction of dams and dam modification projects, agreed to the aggressive 20-hour construction schedule to complete the stability berm and seepage barrier.
By Irwin Rapoport CEG CORRESPONDENT
The Buckeye Lake Dam, part of the Buckeye Lake State Park, is undergoing a $110 million rebuild that was awarded to ASI Constructors Inc., with design-related services being provided by Gannett Fleming Inc. The project is ahead of schedule and a team effort is helping to ensure that benchmarks are being met efficiently. The dam, owned by the Ohio Department of Natural Resources (ODNR), is located near the edge of Millersport and the Village of Buckeye Lake and approximately 30 mi.
east of Columbus. The lake surface area at the top of the dam is 3,030 acres, and the principal spillway level is 2,800 acres at the normal summer pool elevation of 891.5 ft. above mean sea level. The lake’s storage capacity is more than 4.5 billion gallons of water at principal spillway level. Work on the project began in September 2015 and will be completed in 2019. The project is funded by capital improvement funds appropriated by the Ohio General Assembly. The dam’s maximum embankment height is approximately 15 ft., its principal spillway type is a concrete sluiceway with an AMIL gate and its emergency Spillway (at Sellers
Point) is a U-shaped concrete gravity, ungated weir structure with a crest elevation of 892.1 ft. above mean sea level; and in terms of drains, it has a 60-in. (152 cm) diameter pipe at principal spillway, and 60-in. diameter pipe at secondary spillway. The lake attracts many boating and fishing enthusiasts. The dam needed to be replaced after it was determined to pose a likely hazard in the spring of 2015. Buckeye Lake Dam is designated as a Class I high-hazard potential dam, according to the website for the project. A high-hazard potential dam classification signifies the general adverse consequences to lives and property that would occur in the event of a
catastrophic dam failure and does not describe the dam’s condition. This was among the interim risk reduction measures recommended by the U.S. Army Corps of Engineers in its March 2015 report. Upon completion in May 2016 of two structural risk reduction measures — an embankment stability berm and a soil mix seepage cutoff wall. The ONDR is taking nothing for granted. Comprehensive improvements to the dam are needed for it to meet dam safety standards. While the first phase of these improvements was completed in May, the second phase is yet to be determined and finalized. see DAM page 2
Page 2 • July 16, 2016 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
ASI Crews Discover Extensive Defects in Embankment DAM from page 1
The dam’s deficiencies and relevant dam safety standards were documented in Ohio Dam Safety Program inspection reports (2010, 2005) and in a March, 2015 report issued to ODNR by the U.S. Army Corps of Engineers, according to the website. Phase One was completed almost one year ahead of schedule, which allowed the ONDR to increase water levels by 2 ft. (.6 m) above the winter pool level. The work included the construction of an embankment stability berm (ESB) — that used nearly 382,000 cu. yds. (292,059 cu m) of local bank material — and a cutoff wall to serve as a new seepage barrier. The cutoff wall was constructed using soil-mixing equipment — two Raito rigs and a Dewind One-Pass trencher — which were assembled at Liebs Island and North Shore. The machines were used two shifts per day, operating between six and seven days per week. Crews employed mixing paddles (augers) driven into the ground to a depth of approximately 40 ft. (12 m) and mixed grout with the surrounding in-place soil material. The Dewind machine used a 50-ft. (15 m) cutting boom to cut the trench while also Almost every size of excavator was used from the large Cat 336, an amphibious excavator used in dock removal.
The Buckeye Lake Dam, part of the Buckeye Lake State Park, is undergoing a $110 million rebuild that was awarded to ASI constructors Inc., with design-related services being provided by Gannett Fleming Inc.
vertically mixing the injected grout. Also employed was a 2015 Diedrich D-50 Turbo truck mount drill rig to perform vertical verification core borings of the cutoff wall. For tooling, ASI used a Boart Longyear PQ3 wireline core barrel. According to the website extensive defects in the old dam embankment were discovered during the project that had been previously hidden by various kinds of private structures and vegetation. These defects include large voids found in the dam embankment that are suspected to be caused
by erosion, tree decay and utility penetrations. These defects are being addressed through various interim risk reduction measures. This work secured an important milestone as it allows for a higher interim water level to be maintained, support recreational activities and help local businesses. The plans for Phase Two of the project are being prepared. The design for the new dam is being prepared by Gannett Fleming. The ONDR recently awarded a contract to Grass Groomers Inc. to put a fourth dredge (the
only private dredge) into Buckeye Lake this summer. “The design challenge was preparing plans and specs for a 4.1-mile-long embankment stability berm and cutoff wall within a five month timeframe back in late 2015,” said an ONDR representative. “The design needed to address over 350 boat docks, a sewer main, yacht club utilities and pedestrian access and maintaining the operation of two spillways within the footprint of the Phase I work.” The site is in close proximity to more than 350 homes built into the downstream side of the dam which is a highly unusual setting for dam rehabilitation work. “The dam exceeded its lifespan. It is over 175 years old and had not undergone a comprehensive rehabilitation since constructed. The lifespan of the new dam is at least 50 to 100 years.” Robert A. Kline Jr., PE, Gannett Fleming’s vice president dams and hydraulics section, appreciates the team spirit. “Phase I was completed in May 2016 and we are starting Phase II,” he said. “As with any construction project, there are quality requirements imposed on the stability berm material and the performance of the cutoff wall. This project is breaking new ground in that cutoff walls have been in use in the interior of existing embankment dams. However this project uses soil-mix technol-
ogy to create a standalone gravity dam upstream of the existing embankment dam. It is likely one of a kind in the United States.” ASI Constructors Inc., a heavy-civil engineering contractor specializing in the construction of dams and dam modification projects, agreed to the aggressive 20-hour construction schedule to complete the stability berm and seepage barrier. “Constructing a new dam is a complex process and the features that make the Buckeye Lake Dam unique are also the elements creating a challenging construction environment for the new dam,” said Pete Buchholz, PE ASI project manager of the Buckeye Lake Dam Improvements Project. “As the construction manager ASI was responsible for overall site safety during construction. In order to ensure site personnel, as well as public safety, ASI employed dedicated construction safety professionals, conducted continues site safety inspections, held weekly site wide safety meetings and completed daily job hazard analysis prior to starting work to identify, eliminate and or control potential hazards. Through this robust safety program/culture, ASI is pleased to report that throughout Phase I of construction there were no major safety incidents involving site personnel or the public.” The ongoing construction will see ASI see DAM page 4
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • July 16, 2016 • Page 3
Highway Equipment Company of Ohio 1405 Timken Place SW Canton, OH 44706 330-915-8391 Fax: 330-915-8411 www.highway-equipment.com
Attachments can n make your machine moree valuable. Allied offers a wide assortment of attachments to fit all of your makes and models of excavator, loader/backhoe, mini-excavator, skid-steer or compact track loader machines. Allied has become attached to your machines. Allied’s construction and demolition attachments are productive and dependable. State-of-the-art technology.Full product line. Competitive price and performance. Allied offers innovative, problem-solving capabilities. Commitment to product availability. Superior product support. Strong Distributor network. Most of all Allied meets and exceeds customer performance expectations. To put a high performance Allied attachment on your machine, call us at 1-800-321-1046 or visit AlliedCP.com for the name of a Distributor nearest you. We’ve become attached to your machines.
© 2015 Allied Construction Products, LLC
Highway Equipment Company of Ohio
Highway Equipment Company of Ohio
1405 Timken Place SW • Canton, OH 44706 330-915-8391 • Fax: 330-915-8411 www.highway-equipment.com
1405 Timken Place SW • Canton, OH 44706 330-915-8391 • Fax: 330-915-8411 www.highway-equipment.com
Page 4 • July 16, 2016 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
CONSTRUCTION EQUIPMENT SALES • SERVICE • PARTS • RENTALS
042815-JCB
NO DPF ON ANY JCB!
Northeast Ohio
Central Ohio
Southwest Ohio
MH
BURNS 800-752-1220 • www.burnsjcb.com
855-509-1689 • www.hy-tekjcb.com
513-681-2200 • www.mhjcb.com
Gannett Fleming Works to Finish Design of Phase II DAM from page 2
crews perform additional work on the cutoff wall at various locations and lead to the removal of the yellow turbidity curtain. By the start of the winter, the old dam is expected to be cleared of patios, flag poles and other defects. Phase two construction of new dam is currently estimated to begin in spring of 2017 after design is complete. “Phase one included the construction of a 4.1 mile long embankment stability berm that was 30 feet wide,” said Buchholz. “The berm acted as a construction platform for the soil mixing equipment and was constructed around the clock during the coldest weather of the year. Safety of the public, our employees and subcontractors was always our top priority. The soil mixing received much attention but we also had to remove more than 300 docks and other structures that were in front of the old dam and in the way of the berm construction. After removal, these docks were stored on-site for 60
“The design challenge was preparing plans and specs for a 4.1-mile-long embankment stability berm and cutoff wall within a five-month timeframe back in late 2015,” said an ONDR representative.
days in case the owners wanted them back. “Despite the long hours and tough working conditions, the team really came together and completed the project ahead of schedule,” he said. “I’m really proud of the work we did here and am looking forward to finishing
the project, which will likely be done in single shifts with regular working hours.” Testing and verification is essential since the structure is approximately 42 ft. (12.8 m) underground and cannot be inspected directly. “Since the cut-off wall is underground and cannot be directly
inspected,” said Kline, “samples of the cut-off wall are taken using Diedrdich D-50 truck mount for vertical verification core borings. The core barrel used was a pQ3 wireline system. Tests are then conducted based on specifications in the design.” A variety a different vehicles
and equipment were used in the construction of the berm and the cut-off wall. Almost every size of excavator was used from the large Cat 336 an amphibious excavator used in dock removal. Several types of dozers and graders also were used. Other equipment includes: Cat D4, D5 and D6 dozers; Cat 160M and 14H graders; Volvo L120 and Cat 982Ms and 966M loaders; Cat 740 end dump trucks, Cat 740 ejector trucks, Cat 773E haul trucks, a Komatsu HM400, and a Volvo A35 truck; and water craft — John boats, pontoon boats, tug boats and Flexi Float barges. The design team at Gannett Fleming will be working to finishing design of Phase II to begin construction in the spring of 2017. Means and methods for Phase II construction have not been determined. (This story also can be found on Construction Equipment Guide’s website at www.constructionequipmentguide.com.) CEG
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • July 16, 2016 • Page 5
Page 6 • July 16, 2016 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
Wood • Hamilton • Stark • Henry • Greene • Knox • Franklin • Clermont • Crawford • Union • Cuyahoga • Brown • Licking • Medina •Ohio.. Williams • Harrison • Adams • Mercer • Butler • Clark • Ashtabula • Sandusky • Portage • Athens • Logan • Lake • Erie • Wyandot • Warren • Fairfield • Miami • Paulding • Darke • Muskingum • Ottawa • Holmes • Jefferson • Trumbull • Summit • Washington • Van Vert • Licking • Wood • Hamilton • Stark • Henry • Greene • Knox • Franklin • Clermont • Crawford • Union • Cuyahoga • Brown • Licking • Medina • Williams • Harrison • Adams • Mercer • Butler • Clark • Ashtabula • Sandusky • Portage • Athens • Logan • Lake
‘Buckeye State’ Highway Lettings
The Ohio State Department of Transportation received bids for transportation-related improvement projects. The following is a list of some of the projects let. Project No: 160225 Type: Four lane resurfacing. Location: CLE-IR 275-8.90. State Estimate: $2,265,000 Contractors and Bid Amounts:
• Barrett Paving Materials Inc., Middletown, Ohio — $1,896,626 • John R Jurgensen Company, Cincinnati, Ohio — $2,225,389 Completion Date: Oct. 31, 2016 Project No: 160273 Type: Four lane resurfacing. Location: CUY-SR 8-04.93 (Part 1 and Part 2).
State Estimate: $1,472,000 Contractors and Bid Amounts: • Catts Construction Inc., Warrensville Hts, Ohio — $1,271,540 • Karvo Companies Inc., Stow, Ohio — $1,352,213 • Parella-Pannunzio Inc., Youngstown, Ohio — $1,610,526 • Perk Company Inc., Cleveland, Ohio — $2,044,398 • C A Agresta Construction Company, Cleveland, Ohio — $2,104,361 Completion Date: Oct. 31, 2016 Project No: 160275 Type: Guardrail rebuilding. Location: D05-Guardrail-FY2016. State Estimate: $1,180,000 Contractors and Bid Amounts: • Lake Erie Construction Company, Norwalk, Ohio — $1,029,875 • PDK Construction Inc., Pomeroy, Ohio — $1,134,186 • M P Dory Company, Columbus, Ohio — $1,371,915 Completion Date: Oct. 15, 2016 Project No: 160281 Type: Two lane resurfacing. Location: GRE-US 68/SR 235-11.39/0.00. State Estimate: $2,400,000 Contractors and Bid Amounts: • Barrett Paving Materials Inc., Middletown, Ohio — $2,597,025 • John R Jurgensen Company, Cincinnati, Ohio — $2,626,740 Completion Date: Oct. 31, 2016 Project No: 160282 Type: Bridge repair. Location: GUE-IR 77-07.08. State Estimate: $1,227,000 Contractors and Bid Amounts: • Shelly & Sands Inc., Columbus, Ohio — $1,149,016 • Complete General Construction Company, Columbus, Ohio — $1,220,588 • Ruhlin Company, Sharon Center, Ohio — $1,221,887 • Dot Construction Corporation, Canfield, Ohio — $1,287,535 • Rietschlin Construction Inc., Crestline, Ohio — $1,343,518 • Becdir Construction Company, Berlin Center, Ohio — $1,388,377 Completion Date: Oct. 31, 2016
HUDSON 6681 Chittenden Road Hudson, OH 44236 P-330-655-5900 F-330-655-5969
COLUMBUS 3155 E 17th Avenue Columbus, OH 43219 P-614-475-2880 F-614-475-0069
CINCINNATI 8131 Regal Lane West Chester, OH 45069 P-513-777-5556 F-513-777-4494
Project No: 160285 Type: Culvert replacement. Location: HOC-SR 180-Var. State Estimate: $1,264,000 Contractors and Bid Amounts: • Shelly & Sands Inc., Columbus, Ohio — $1,469,999 • Foill Inc., Waverly, Ohio — $1,217,196 • Buds Inc., Nashport, Ohio — $1,969,576 Completion Date: Nov. 1, 2016
Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • July 16, 2016 • Page 7
3 ! , % 3 s 2 % . 4 ! , 3 s 0 ! 2 4 3 s 3 % 2 6 ) # %
DRILL ILL RIGS FOR RENT 1.800.PILE.USA -or- www.ecanet.com PITTSBURGH PO Box 306 Coraopolis, PA 15108 P 412.264.4480 F 412.264.1158
PHILADELPHIA PO Box 387 Aldan, PA 19018 P 610.626.2200 F 610.626.2245
WASHINGTON, D.C. 6300 Foxley Road Upper Marlboro, MD 20772 P 301.599.1300 F 301.599.1597
TORONTO 166 Bentworth Ave Toronto, Ontario M6A 1P7 P 416.787.4259 F 416.787.4362
EQUIPMENT CORPORATION OF AMERICA B U I L D I N G F O U N DATI O N S S I N C E 1 91 8
AUTHORIZED DEALER:
PITTSBURGH
PHILADELPHIA
WASHINGTON
D.C.
ntoo Sa Savings avvings in Shift Shiff t IInto
TORONTO
KUBOTA KUBO TA A SALES EVENT
47117 St. Rt. 18 Wellington, OH 44090
440-647-2015 www.krystowskitractor.com *$0 down, 0% A.P.R. financing for up to 60 months on purchases of new Kubota SSV Series Equipment is available to qualified purchasers from participating dealers’ in-stock inventory through 9/30/2016. Example: A 60-month monthly installment repayment term at 0% A.P.R. requires 60 payments of $16.67 per $1,000 financed. 0% A.P.R. interest is available to customers if no dealer documentation preparation fee is charged. Dealer charge for document preparation fee shall be in accordance with state laws. Inclusion of ineligible equipment may result in a higher blended A.P.R. 0% A.P.R. and low-rate financing may not be available with customer instant rebate offers. Financing is available through Kubota Credit Corporation, U.S.A., 3401 Del Amo Blvd., Torrance, CA 90503; subject to credit approval. Some exceptions apply. Offer expires 9/30/2016. See us for details on these and other low-rate options or go to www.kubota.com for more information. Optional equipment may be shown.
kubota.com
© Kubota Tractor Corporation, 2016
Page 8 • July 16, 2016 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide
EXPERIENCE THE
iMC Revolution Columbus Equipment Company recently introduced Komatsu’s groundbreaking intelligent Machine Control (iMC) technology technology.. Ever since, iMC has been transforming the way Ohio contrac contrac-tors move earth. Komatsu’s market share has ballooned as the technology proves itself where it counts ... in the field.
Columbus Equipment Company has provided Ohio customers with unparalleled product support since 1952, and continues to do so. A specialized iMC support team will partner with you closely as you introduce unprecedented capability to your fleet … and Experience the iMC Revolution.
iMC integrates GPS positioning antennae and sensors to c ontrol the machine—not just the blade—thereby maximizing control material load and push. W ith no external daily setup, cost is With greatly reduced. Robust automatics and intelligence also get the contractor on-grade faster—with fewer passes—increasing productivity and efficiency by as much as 25%.
ct Machine Contr Control rol ol Manager Contact Mike Fenster at (614) 802-7099 on the fleet of Komatsu iMC machines including D39i, D61i, D65i, D85i and D155AXi crawler dozers and PC210i, PC360i and PC490i excavators, and to schedule a demo.
Columbus Toledo Cincinnati Richfield Cadiz (614) 443-6541 (419) 872-7101 (513) 771-3922 (330) 659-6681 (740) 942-8871 Painesville Piketon Dayton Massillon Zaneville (937) 879-3154 (330) 833-2420 (740) 455-4036 (440) 352-0452 (740) 289-3757
Ohio’s Dependable Dealer
www.columbusequipment.com