Skip to main content

Ohio 3, February 5, 2022

Page 1

State Supplement sponsored by:

90 80 6 422

6 80 24

OHIO STATE EDITION

6

4

71

76

199

A Supplement to:

30 30 75

68

30 77

71 23 22 68

4

70 70

70

22 71

75

77

27 22 74

50

50 25

35

SHIP WITHIN 48 HOURS

52

®

SAME DAY PARTS AVAILABILITY 24 HOUR TECHNICAL SUPPORT BACKED BY A 75 YEAR BUSINESS

February 5 2022

Thousands in Service!

Vol. XVI • No. 3

“The Nation’s Best Read Construction Newspaper… Founded in 1957.” Your Ohio Connection: Ed Bryden, Strongsville, OH • 1-800-810-7640

Affordable Price. Premium Service.

CALL 800-367-4937 *On approved credit • Financing Available

Morgan Overbey photo

The Ohio Department of Transportation (ODOT) is overseeing the $88 million effort, which includes major bridge work and the resurfacing of I-70 between U.S. 40 and State Route 93 in Muskingum County.

By Cindy Riley CEG CORRESPONDENT

Progress continues on a six-year project that will reconstruct I-70 through the city of Zanesville, Ohio. The Ohio Department of Transportation (ODOT) is overseeing the $88 million effort, which includes major bridge work and the resurfacing of I-70 between U.S. 40 and State Route 93 in Muskingum County. “Failures of subgrade throughout the project limits and deteriorating pavement and bridge conditions have caused maintenance throughout this section to become excessive,” said Audrey Seals, ODOT area engineer, who explained that

construction will be stretched out over time. “The phasing of the project is difficult, as it is necessary to maintain two lanes of traffic in both directions, while also allowing as many ramps to be open as possible throughout Zanesville. Lane closures are only permitted during certain times, mostly at night, due to the volume of traffic that travels this section of I-70. There are 16 bridges that will be rehabilitated on this project, and some of them have limited access, so not all of them are able to be constructed at the same time.” Pre-Phase 1 work included constructing temporary concrete pavement widening, temporary lighting and installing portable concrete barrier to move traffic to the outside lanes

for the Phase 1 configuration. It also required adding advance radar detectors on various signals throughout Zanesville to improve the traffic flow through town during construction. Two temporary signals also were added at the SR-93 on and off ramps to facilitate the detours to be used throughout the project. “Phase 1 includes removing the existing median barrier and constructing new concrete barrier with the addition of new lighting on the concrete barrier,” said Seals. “It also includes reconstructing the inside lanes and various ramps, which consist of full depth reconstruction of the pavement with cement stabilization of the subgrade, as well as various see ODOT page 4


Page 2 • February 5, 2022 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

OAIMA Recognizes Contributors at Annual Meeting, Show The Ohio Aggregates & Industrial Minerals Association (OAIMA) held its 2021 annual meeting and trade show in Columbus in November. During the event, which included educational sessions, an exhibitor reception and trade show, many individuals were recognized for their endeavors on behalf of OAIMA, including: Bob Stewart Bob Stewart of Columbus Equipment Co. was recognized for his service to OAIMA. Stewart served on the OAIMA board of directors from 2019 through 2021. “Bob Stewart has long been a supporter and contributor to OAIMA and its mission,” said Patrick Jacomet, OAIMA executive director. “He is always willing to share his vast knowledge of the industry in Bob Stewart support of causes important to our members. His leadership on the board and but are thankful for his service,” said willingness to volunteer his time are invalu- Jacomet. “His experience in the industry and able to us. He is a wonderful representative participation on the board have brought a of the industry and in particular Columbus new and fresh perspective to OAIMA. We are grateful to John and all of the great folks Equipment Co.” at Fairborn Cement for their continued support.” Gary Honchell Gary Honchell of Process Machinery Inc. Dan Mapes (PMI) was presented with the Hall of Fame Dan Mapes of the National Lime and Award in recognition for his service to Stone Co. was presented with the Hall of OAIMA. “Gary has long been a supporter and Fame Award in recognition for his service to advocate of the OAIMA and its mission,” OAIMA. “Dan Mapes has long been a supporter said Jacomet. “His service to the industry, including his time on the board have con- and contributor to OAIMA and its mission,” tributed greatly to the advancement of our said Jacomet. “He is always willing to share members and the association. Gary also his vast knowledge of the industry in support serves the community as a volunteer fire- of causes important to our members. His fighter. We are proud to present Gary with the OAIMA Hall of Fame award.”

Jennifer Hanley

leadership of our legislative committee has led to many positive changes benefiting not only our members, but the citizens of Ohio.”

Ron Tipton Ron Tipton of Lehigh Hanson was presented the “Ed Hole” award in recognition of

his support for the industry. “Over the course of Ron’s career, he has always been a steadfast supporter of OAIMA and our mission,” said Jacomet. “His longtime service and leadership on the board saw us through difficult times and led to many positive changes and growth. Additionally, Ron’s support by allowing employees of Lehigh Hanson to actively participate in committee and association work has made us stronger.” The “Ed Hole” award is named in honor of industry pioneer, Ed Hole, and is presented to individuals who have provided leadership on the national or state level and have allowed their employees to participate actively in OAIMA. For more information visit oaima.org. 

Dan Mapes

Ron Tipton

Paul Cuthbert Paul Cuthbert of The Shelly Company was recently elected to serve as a director of the board. “We are excited to have Mr. Cuthbert join our board of directors at OAIMA,” said Jacomet. “Paul brings a wealth of experience to the table, particularly on the logistical front. We look forward to working with Paul for many years to come.”

Jennifer Hanley Jennifer Hanley of the Gilson Co. was presented with the “Rocky Award” in recognition of her support for the industry. “Jennifer has long been a leader within our association and has been extremely supportive of our educational efforts,” Jacomet. “She also is active at the national level through her work with ASTM, AASHTO and other specifying agencies. Her recent work on our MACC Tech program will be instrumental in the promotion of our vital industry as a solid career-choice.” John Miller John Miller of Fairborn Cement was presented with the “Retiring Director” award in recognition of his support for the industry and service. “We are sorry to see John leave the board

Gary Honchell


Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 5, 2022 • Page 3

Call fo or our full line of to ough used equipm ment! &%$#"! " " " " " #"

"

" " "& &

Check outt additional used eq quipment at bobcattent.com P RE-OW N E D, JOB R EA DY E Q UIPMENT NOW A V A AILAB LE !

2012 Bobcat S650, 1600 Hrs, A71 Package, CN 125155 ........$34,500

2016 Bobcat S650, 1860 Hrs, A71 Package, CN 125508 ........$36,500

2017 Bobcat S650, 400 Hrs, Open ROPS, Power Bobtach, CN 126684 ........................................................................................$42,000

2018 Bobcat E42, 800 Hrs, HVAC Cab, Thumb, CN 127115 ....$57,500

2017 Bobcat E50, 825 Hrs, A31 Package, CN 125955 ............$58,000

48” Bobcat Snow Blade, Fits All MT Models, 463 & S70, CN 121580.. ........................................................................................................$1,250

2014 Compactor HRV2000, Fits 24-65 Metric Ton Excavators, CN 90535 ........................................................................................$9,150

2013 Doosan 4 in 1 Bucket, 100.5” 2.5 Cubic Yard, FITS JRB Coupler, CN 89289 ......................................................................$15,250

C i n c i nna n ti • Mt . Orab • H illiard • R eyn olds bu rg • Zan esville • L ex e x ing t o n • Lo uiss v ille


Page 4 • February 5, 2022 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

Coordination Is Key On ODOT’s I-70 Reconstruction Project ODOT from page 1

Morgan Overbey photo

rehabilitation of 15 bridges and the removal of one bridge. “Phase 2 entails constructing the eastbound lanes of I-70 and various ramps, which consists of full depth reconstruction of the pavement with cement stabilization of the subgrade, as well as various rehabilitation of 15 bridges and the removal of one bridge.” Phase 3 involves constructing the westbound lanes of I-70 and various ramps, while Phase 4 calls for milling out the sacrificial asphalt placed in phases 1-3, as well as existing pavement beyond the full depth reclamation limits on each end of the project between U.S.-40 and SR 93. A large majority of the project is 100 percent state funded; however, there is federal funding included for culvert preservation, safety funding and bridge rehabilitation for one structure. Current average daily traffic is 40,620. The project will serve residents of Zanesville, in- and out-of-state travelers and commercial freight traffic. “Because I-70 is a critical truck route, it’s imperative to keep this portion of Zanesville traversable to commercial traffic,” said Seals. “Throughout the project, we will have narrow lanes with one-foot shoulders, various lane closures, which might cause slight delays, and a speed limit reduction to 45 mph while workers are present. Seals noted that communicating any traffic pattern Pre-Phase 1 work included constructing temporary concrete pavement widening, temporary lighting and installing a portable concrete barrier to move traffic to changes to the traveling public in a timely manner is the outside lanes for the Phase 1 configuration. key, as is listening to the concerns of motorists while making every effort to address their concerns. “The overall rideability of this section of I-70 will be greatly improved, with less need for maintenance delays. This project will also improve the lighting, which will increase visibility. The acceleration lane on some ramps will be lengthened to allow for more merge time onto I-70.” Shelly and Sands serves as the general contractor for the project. “Shelly and Sands is a local contractor that’s familiar with the city of Zanesville and understands the importance of this project and the amount of Morgan Overbey photo traffic that uses this section of I-70,” said Seals. According to ODOT, the main concern for crews has “They have also constructed a large number of Morgan Overbey photo mega-construction projects on the Ohio interstate Resurfacing I-70 between U.S. 40 and State Route 93 in involved the lack of right-of-way, resulting in narrow lanes and shoulders, creating a tight work zone, limitsystems around the state.” Muskingum County requires a great deal of coordination. ing access for the contractor. According to ODOT project manager Michelle Sidwell, the main concern for crews has involved and design team has spent several years working on the proj- will be time-consuming. the lack of right-of-way, resulting in narrow lanes and shoul- ect. District 5, along with our consultants, worked hard to “All 16 bridges will have various rehabilitation applicaders, creating a tight work zone for the public to travel and survey, plan, get through the environmental process, design, tions performed on them, including full and partial substruclimiting access to the work zone for the contractor. move utilities and coordinate right-of-way needs. This has ture replacement, full and partial superstructure replacement, “Another challenge has been determining the sequential been a substantial effort, which also required a good amount deck patching and the removal of one bridge,” said Sidwell. construction of the ramps along with construction of the of help and collaboration with the city of Zanesville.” “Some bridges will have aesthetic formliner and staining on main line, with elevation changes of the new pavement in Resurfacing I-70 between U.S. 40 and State Route 93 in the parapets and MSE walls and vandal fence with lettering each phase to ensure traffic has access in and out of Muskingum County requires, not surprisingly, a great deal of to enhance the overall end product. Zanesville. Adequately maintaining the work zone and coordination. “The bridges were constructed when the interstate was maintenance of traffic throughout the project, due to the poor “Once the cement stabilization of the subgrade is com- originally built and have had various rehabilitation projects condition of the existing pavement and the limited space in plete, six inches of 304 aggregate base and 8.5 inches of 302 completed throughout the years but have deteriorated to a the work zone, is another challenge.” asphalt base is placed, followed by 1.75 inches of asphalt point where a major rehabilitation effort was needed. The Work began in July 2021, with a current completion date intermediate course with a 1.5-inch asphalt surface course. time and cost of maintenance on these bridges was becoming of October 2027. Once the full depth reclamation section is complete, we will excessive. Furthermore, design standards also have changed “The project is currently in Phase 1 and is working to mill out the sacrificial asphalt and existing asphalt beyond since these bridges were originally constructed, and the volremove the existing median barrier and demolition on vari- the full depth reclamation section, then place intermediate ume of traffic has increased, creating the need to perform ous bridges, which includes superstructure and substructure and surface asphalt on the entire project from U.S.-40 to SR- various improvements on the bridges.” removal,” said Sidwell, who added that reconstructing I-70 93.” One bridge will be completely removed, embankment through the city of Zanesville is no small undertaking. Work on the 16 bridges along the downtown corridor, placed and new roadway constructed, as it is no longer “In order to get to the point of construction, our planning including those over the Licking and Muskingum Rivers, see ODOT page 6


Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 5, 2022 • Page 5

SO MU UCH IN NVENT TORY, SO O LITTL LE TIM ME RENT ME!

How about me?

TRY ME OU UT!

Check out my rollers!

PICK ME!

TA T AKE ME FOR A SPIN!

S Southeastern carrries quality rentals like small s hand tools, aerial liifts, and heavy duty construction equipm ment at rates you’ll love.

CALL 800-798-LIFT OR VISIT US ONLIN NE AT SOUTHEASTERNRENTAL.COM A This his ad does not constitute an offe err. Products subject to availability and varies by loccation. cation Southeastern reserves the right to substitu ute any of the equipment rented for like like equipmen nt at any time. time Customer may be responsible for additional a charges including, including but not limited to, damages, cleaning fe ees, over hours, fuel and delivery/pickup. Credit approval and insurance required for all rentals. Sou utheastern reserves the right to refuse rentals for any a reason.


Page 6 • February 5, 2022 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

Earthwork Requires Regrading Shoulders, Excavation ODOT from page 4

needed. One bridge rehabilitation includes patching of the deck only. “Rehabilitation of five bridges includes partial removal and replacement of the substructure with full removal of the abutment and partial rehabilitation of the piers, and full removal and replacement of the substructure including the beams, deck and parapets,” said Sidwell. “Rehabilitation of nine bridges includes partial removal and reconstruction of the superstructure, including removal and replacement of the deck and parapets.” Excavation work entails regrading the shoulders on the

ramps and mainline to meet minimum slope requirements, and to provide better drainage throughout this section of I70. There is a total of 58,310 cu. yds. of excavation, 46,305 cu. yds. of embankment and 33,500 cu. yds. of concrete. Along with bridge removal and rehab, key tasks remaining on the project include the removal of the existing pavement; cement stabilization of the subgrade; placement of the 304 aggregate base and asphalt for all of mainline on phases 1, 2 and 3, as well as the on and off ramps for State Street eastbound and westbound; the three ramps included in the Maple Avenue eastbound flyover on-ramp; the off ramp for Maple Avenue westbound, the on-ramp from 6th Street; and

L EEB O Y 8 5 2 0 A S PH A LT PA V E R

Morgan Overbey photo

Shelly and Sands serves as the general contractor for the project.

COMMIT TTED TO QUALITY. COMMITTED TO YOU.

We a r e Le e B o y. T h e n a m e b e h i n d t h e w o r l d ’s m o s t d e p e n d a b l e a n d p r o d u c t i v e c o m m e r c i a l a s p h a l t p a v i n g e q u i p m e n t : p a v e r s , g r a d e r s , d i s t r i b u t o r s , m a i n t a i n e r s a n d m o r e . T h e Le e B o y f a m i l y o f p r o d u c t s a r e a m o n g t h e m o s t t r u s t e d a n d r e q u e s t e d a r o u n d t h e w o r l d . B e c a u s e w e u n d e r s t a n d w h a t d r i v e s y o u a n d w e d e l i v e r. E a c h d a y, l i ke y o u , w e p u t i t a l l o n t h e l i n e . I t ’s h o w w e ’ r e b u i l t . W e ’ r e L e e B o y. y As dependable as your day is long.

LeeBoy, Rossco and LBPerformance brand b equipment available at this reputable Dealer’s locations: o

N OW LING SEL

HUDSON

C COLUMBUS

WEST CHESTER

668 1 C h i t t e n d e n Ro ad Huds o n , O H 4 4 236 P ho n e : 3 3 0- 6 6 5 - 5 9 00 F ax: 3 3 0- 6 5 5 - 5 96 9

31 5 5 E. 1 7th Avenue Co lum mbus , OH 43219 P h o n e: 6 14 -4 75-2880 Fax : 6 14 -4 75-0069

8131 Rega l La ne West Chest er, O H 45069 Phone: 513-777-5556 Fa x: 513-777-4494

the 5th and 7th Street off-ramps. Demolition has begun on four bridges but has yet to begin on the remaining 11. The rehabilitation on the Zanesville State Street Signature bridge — which will occur in the summer of 2022 while school is not in session — will be the first major milestone for crews. In addition, reconstruction of each ramp and reopening them to traffic at the State Street interchange will be a turning point in construction. “Other major milestones will be the completion of each phase of construction,” said Sidwell. “However, the most significant to the residents of Zanesville and the surrounding area is the completion of Phase 3, which will allow all ramps to be reopened to traffic, including the 6th street westbound on-ramp and Maple Avenue eastbound on-ramp, which have been closed since switching to Phase 1 in the fall of 2021 due to safety concerns.” Heavy equipment on the project includes: • trackhoes: a Komatsu 228 USLC, a Hitachi ZA 15, a John Deere 245C and a Caterpillar 360; • cranes: a Grove RT-765E2, a Grove TMS900E; • skid steers: John Deere; • backhoes: Caterpillar; • cement stabilization equipment: Wirtgen; • concrete paver: Wirtgen SP 64i; and • bucket trucks. Concrete, cement, asphalt, 304 aggregate, steel and rebar are among the main materials required. Sidwell said the chief concerns when carrying out such a lengthy reconstruction project involve the safety of the traveling public, as well as project personnel, the effect on traffic and the effect on roads and area businesses. “Staying on time and budget is important as well, as a project that is to occur over many years has the potential to be impacted financially, and weather and various events can affect time. Added Sidwell, “It’s very rewarding to see a job be built that directly affects your daily commute. I also know how important this project is to the community, and how vital this section of I-70 is to Zanesville.”  CEG


Construction Equipment Guide • Ohio State Supplement • www.constructionequipmentguide.com • February 5, 2022 • Page 7

Intel to Build Computer Chip Factories Amid Global Shortage By John Seewer and Andrew Welsh-Huggins ASSOCIATED PRESS

Intel will invest $20 billion in a new computer chip facility in Ohio amid a global shortage of microprocessors used in a wide variety of products, including phones, cars and video games. After years of heavy reliance on Asia for the production of computer chips, vulnerability to shortages of the crucial components was exposed in the United States and Europe as they began to emerge economically from the pandemic. The United States’ share of the worldwide chip manufacturing market has declined from 37 percent in 1990 to 12 percent today, according to the Semiconductor Industry Association. Two chip factories on the 1,000-acre site in Licking County, just east of Columbus, are expected to create 3,000 company jobs and 7,000 construction jobs, and to support tens of thousands of additional jobs for suppliers and partners, the company and local and state officials announced Jan. 21. Construction is expected to begin this year, with production coming online at the end of 2025. Shortages of chips have crimped the ability of United States automakers to produce vehicles. Last year, General Motors was unseated by Toyota as the nation’s top-selling automaker for the first time. The United States and Europe are pushing to aggressively build chip manufacturing capacity and reduce reliance on producers that are now mostly based in Asia. Most big semiconductor companies are dependent on chips produced in Asia, particularly in Taiwan. Taiwan leads the world in chip production, accounting for 22 percent of global manufacturing capacity, followed by South Korea with 21 percent and Japan and mainland China each with 15 percent, according to the semiconductor association. Several chipmakers last year signaled an interest in expanding their American operations if the United States government is able to make it easier to build chip plants. Chipmakers are diversifying their manufacturing sites in response to the shortages. Samsung said in November that it planned to build a $17-billion factory outside Austin, Texas. Micron Technology, based in Boise, Idaho, said it would invest $150 billion globally over the next decade in developing its line of memory chips, with a potential United States manufacturing expansion if tax credits can help make up for the higher costs of American manufacturing. Demand for computer chips continues to grow.

Lawmakers have been urging House and Senate leaders to fully fund a law meant to address the semiconductor shortage. They want Congress to fully fund the $52-billion CHIPS for America Act, allowing for stateside investment in semiconductor factories. Not only has the chip shortage disrupted the United States economy, it is creating a vulnerability in the country’s defense system because eight of every 10 chips are produced in Asia, lawmakers said. Separate federal legislation also under consideration would create a new tax credit for investment in semiconductor manufacturing facilities. Shortages during the pandemic highlighted the need for more manufacturing capacity in the United States and for becoming less reliant on Asia, said Glenn O’Donnell, an analyst at Forrester Research. “Your two biggest producers are Taiwan and South Korea and both are vulnerable spots on the world stage,” he said. U.S. Commerce Secretary Gina Raimondo applauded the announcement. “Intel’s work is essential to our efforts to rebuild America’s chip building capacity and create the kinds of good-paying jobs that support a vibrant American economy,” she said. The Intel project is the largest single private-sector investment in Ohio’s history, on par with an agreement in 1977 that brought Honda to central Ohio, where it now employs more than 14,000 people. The Intel jobs are expected to pay an average of $135,000 a year plus benefits, with the project slated to add $2.8 billion to the state’s annual gross product, Ohio Gov. Mike DeWine said in a statement. “Intel’s new facilities will be transformative for our state, creating thousands of goodpaying jobs in Ohio manufacturing strategically vital semiconductors,” DeWine said. Intel, based in Santa Clara, announced plans last year to spend $20 billion for two new factories in Arizona. It’s also pitching for European subsidies to build a big plant somewhere within the European Union and last month said it would invest $7.1 billion to expand its decades-old manufacturing operation in Malaysia, home to roughly 10 percent of the company’s global workforce. Along with the United States and Malaysia, Intel also has plants in Ireland, Israel, Vietnam and China. Intel is the No. 2 semiconductor manufacturer globally, with $73.1 billion in revenue last year, behind South Korea-based Samsung Electronics with $76 billon, according to market analysis from Gartner Inc. Central Ohio, long known for a largely white-collar workforce in banking and insurance, has added high-tech jobs in recent years, with Amazon, Facebook and Google all building data centers in the region. 

Introducing a truly unique machine with endless possibilities. The JCB Te Teleskid is the first and only skid steer and compact track loader with a telescopic boom, making it the most versati t le machine you’ve ever seen. It can lift higherr,, reach fur ther and dig deeper than any other skid steer on the market and can access areas you wouldn’t haavve thought possible, until now.

jcb.com//tteleskid

Buck and Knobby JCB

Company Wrench JCB

Covering Northwest Ohio 9127 Airport Highway Holland, OH 43528 419-491-2362 www.buckandknobbyjcb.com

Covering Central Ohio 866-262-4181 Toll Free 4805 Scooby Lane Carroll, OH 43112 740-654-5304

Burns JCB Covering Northeast Ohio 8155 Roll & Hold Pkwy. Macedonia, OH 44056 866-459-6713 www.burnsjcb.com

920 Deneen Avenue Monroe, OH 45050 513-649-8105 www.companywrenchjcb.com

5338


Page 8 • February 5, 2022 • www.constructionequipmentguide.com • Ohio State Supplement • Construction Equipment Guide

“

U Using intelligent m machines to grade waterways takes one-h half to one quarter the time … and it’s perfect p every time. Sam Pullins | Pullins Drainage


Turn static files into dynamic content formats.

Create a flipbook
Ohio 3, February 5, 2022 by Construction Equipment Guide - Issuu