Georgia 26 December 21, 2016

Page 1

441

59

75

GEORGIA STATE EDITION

Cornella 19

A Supplement to:

Rome 85 27

Athens 441

Atlanta

20

Madison Augusta

85

20

Griffin 1

129

Milledgeville

75

La Grange

Macon

301

185 19

®

16

Dublin

Swainsboro Oak Park

Columbus

Statesboro

341 441 16

Lyons Americus

December 21 2016

Dorchester

341

Cuthbert

75

Albany

84

Douglas Tifton

82

95

82

Blakely

Pearson

“The Nation’s Best Read Construction Newspaper… Founded in 1957.”

301

1

82

Vol. XVIII • No. 26

Savannah

McRae Cordele

27

27 84

Moultrie

19 319

84

Bainbridge

Valdosta Thomasville

Waycross Brunswick 82

1 441

Your Georgia Connection: Rich Olivier, Atlanta, GA • 1-800-409-1479

$400M Dalton Expansion to Extend Transco Pipeline By Cindy Riley

In Georgia, construction is underway on the massive dalton Expansion project, which calls for a new pipeline laterally connecting the transco natural gas pipeline to an existing electric generating facility operated by oglethorpe power Corp. the $400 million investment involves a local distribution company run by Atlanta Gas Light Company and the municipality of Cartersville, Ga. the pipeline will be complete in 2017. “We have tremendous internal expertise to execute major pipeline projects like our dalton expansion,” said Chris stockton, a spokesman of Williams, the tulsa, okla.-based energy company operating the transco pipeline. “A big part of this is working very closely with our customers to determine what their needs are, and timing requirements, so that we can develop a realistic, executable project schedule.” the dalton Expansion project will consist of 115 mi. (185 km) of new steel pipe ranging from 16 to 30 in. (40 to 76 cm) in diameter, extending from the existing transco pipeline in Coweta County, Ga., and providing service to new delivery points in paulding and Murray Counties. the project was designed to transport approximately 448,000 dekatherms of natural gas per day. Williams’ personnel are responsible for a number of development functions, including project management, engineering, drafting, business development, land acquisition, environment permitting, regulatory affairs and survey. “Construction on the new 21,000-horsepower compressor station in Carroll County broke ground in August 2016,” said stockton. “the initial site prep work is nearly complete. Compressor foundations have been poured and pipe fabrication is underway. Construction on the 115-mile pipeline lateral is also underway, kicking off with preparations initiated on the two pipeline contractor yards.” the compressor facility design called for two approximately 11,000-horsepower gas turbine-driven compression units, four natural gas after-coolers, one emergency generator, two electric air compressors and an air storage tank. A pre-engineered metal building will serve as a warehouse/workshop with roll-up doors for storing spare parts and equipment. two above ground storage tanks for waste oil and oily water are included in the plans, along with a security fence enclosing all equipment. the gas turbines and the attached compressors will be installed within a metal building to both limit noise from the gas turbines and the compressors and to provide protection from the elements. Most above ground piping also will be insulated to minimize noise. As for the overall project, stockton said any pipeline proj-

CEG CorrEspondEnt

ect of this size presents unique challenges. “Managing potential environmental and landowner issues, while balancing the requirements of the various state and federal permitting agencies, requires a tremendous amount of planning and coordination,” stockton said. “there are so many moving pieces with a project of this size. All of the various Williams functional areas, along with third party consultants, have to be well-synchronized to execute the project deliverables and maintain the customer schedule.” the pipeline was designed to transport enough natural gas to meet the daily needs of about two million homes, based on a calculation by the American Gas Association. stockton said getting public feedback was key. “We are regulated by the Federal Energy regulatory

Commission (FErC). prior to submitting our formal application to obtain a Certificate of public Convenience and necessity, FErC encourages applicants to engage in what they call the ‘pre-filing’ process. this consists of extensive outreach to key project stakeholders such as landowners, public officials, environmental groups and state and local agencies, to identify any potential issues with the project design prior to submitting a formal application with FErC. “We participated in the pre-filing process for dalton, hosting numerous public meetings to solicit feedback on the route. We adopted some of this feedback, making modifications to the route to avoid potential issues which would become larger issues during the application’s regulatory review process.” see PIPELINE page 2

Williams photo

The $400 million investment involves a local distribution company run by Atlanta Gas Light Company and the municipality of Cartersville, Ga. The pipeline will be complete in 2017.


Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.