GOAL 15: Seaplanes: Facility and Service
Key Issues
Design Funding Construction 1. Obtain permits 2. DECISION: Funding and Design 3. Complete construction 4. Ribbon-cutting and 1st Flight
Responsibility: City Engineer
5/22 5/22 TBD TBD
April 2022 Update
• Final approval for seaplane base from FDOT is currently in the 45-day public comment period.
Expect final approval by end of May 2022. • A request has been made to the consultant to provide a proposal for the engineering design and permitting of the seaplane base. Proposal anticipated by May 30, 2022.