GOAL 15: Seaplanes: Facility and Service

Key Issues

 Design  Funding  Construction 1. Obtain permits 2. DECISION: Funding and Design 3. Complete construction 4. Ribbon-cutting and 1st Flight

Responsibility: City Engineer

5/22 5/22 TBD TBD

April 2022 Update

• Final approval for seaplane base from FDOT is currently in the 45-day public comment period.

Expect final approval by end of May 2022. • A request has been made to the consultant to provide a proposal for the engineering design and permitting of the seaplane base. Proposal anticipated by May 30, 2022.