GOAL 2: Island Reclamation Plant Relocation
GOAL 2: Island Reclamation Plant Relocation: Design
Key Issues
Target Date: 12/25 Grants and Outside Funding Sources Debt Restructure Rate Structure Use of Property Plant Design 1. Complete 30% design
Complete 2. Prepare report with recommendations 5/22 3. DECISION: Debt Restructure and Rate
Approval 5/22 4. Complete 50% design 6/22 5. Complete 90-100% design 12/22 6. Begin construction 2023
Responsibility: FPUA
April 2022 Update
The FPUA Board approved rate adjustments on May 3, 2022. The City Commission will vote on rate adjustments on May 16, 2022. If approved, FPUA staff will proceed with a 60% design task order with expected completion in the 4th quarter of 2022. Also, if approved on May 16th, FPUA staff will approve early work packages to begin procurement of the material with long lead times. Construction expected to begin in January 2023.