GOAL 2: Island Reclamation Plant Relocation

GOAL 2: Island Reclamation Plant Relocation: Design

Key Issues

 Target Date: 12/25  Grants and Outside Funding Sources  Debt Restructure  Rate Structure  Use of Property  Plant Design 1. Complete 30% design

Complete 2. Prepare report with recommendations 5/22 3. DECISION: Debt Restructure and Rate

Approval 5/22 4. Complete 50% design 6/22 5. Complete 90-100% design 12/22 6. Begin construction 2023

Responsibility: FPUA

April 2022 Update

The FPUA Board approved rate adjustments on May 3, 2022. The City Commission will vote on rate adjustments on May 16, 2022. If approved, FPUA staff will proceed with a 60% design task order with expected completion in the 4th quarter of 2022. Also, if approved on May 16th, FPUA staff will approve early work packages to begin procurement of the material with long lead times. Construction expected to begin in January 2023.