GOAL 13: Port Development
GOAL 13: Port Development: Re-Zoning Direction
Key Issues
Land Use Project Direction Timing 1. Continue discussion with property owner(s) 3/22 2. Review draft proposal 3/22 3. Finalize proposal and land use changes 4/22 4. Planning Board Review 9/22 5. DECISION: 1st Reading 10/22 6. Submit to State 11/22 7. DECISION: 2nd Reading – Final Approval 12/22
Responsibility: Planning Director
April 2022 Update
The finalized proposal and land use changes have been completed. The Planning Department is on schedule for the targeted September 2022 Planning Board Review.