FORT PIERCE Strategic Plan 2022 Goals GOAL 6: 13th Street Upgrade: Direction and Funding (North and South) Key Issues Project Costs: $10 million Funding Source Grant Opportunities Federal Infrastructure North - Design
1. Identify initial funding options – South 2. Incorporate in CIP Update 3. Updated Plan Completed
6/22 7/22 12/22
Responsibility: City Engineer
June 2022 Update
Continuing to search for alternative funding sources.
23