GOAL 5: Wayfinding Signage

GOAL 5: Wayfinding Signage: Upgraded Design and Funding

Key Issues

 Design  Themes  Colors  Locations  Digital “Wayfinding” 1. Prepare plan and finalize design options 5/22 2. Finalize report 6/22 3. FPRA DECISION: Presentation, Direction and Funding 7/22 4. Mobilize project 8/22 5. Complete installation 12/22

Responsibility: City Manager

June 2022 Update

All district logos have been created and finalized. This information has been relayed to the consultant who will revise the design and present a final proposal. The wayfinding signage proposal will be included in the FPRA Project-Based Budget on July 12, 2022.