1 minute read

GOAL 4: Greenway Trail

GOAL 4: Greenway Trail: Development

Key Issues

 Link to Sun Trail  Goals  Options  Funding  Route through Downtown  FEC Land Acquisition (Small Parcel 1. Complete Highwaymen Trail Gap

Design 2. Solidify Historic Downtown route 3. CONFERENCE AGENDA: Presentation and

Direction 6/22

8/22 9/22

4. DECISION: Historic Downtown Route 11/22 Responsibility: City Engineer

June 2022 Update Highwaymen Trail Segment

• Design plans (80%). • Still waiting for reply to request sent to FEC Railroad to purchase/lease corner parcel for trail connectivity.

Historic Downtown Segment

• Consultant has submitted 30% plans for review. • Alternative routes being explored (ongoing). • Proposed route shared with consultant working on Downtown Master Plan.

This article is from: