FORT PIERCE Strategic Plan 2022 Goals GOAL 2: Island Reclamation Plant Relocation: Design Key Issues Target Date: 12/25 Grants and Outside Funding Sources Debt Restructure Rate Structure Use of Property Plant Design
1. Complete 30% design 2. Prepare report with recommendations 3. DECISION: Debt Restructure and Rate Approval 4. Complete 60% design 5. Complete 90-100% design 6. Begin construction
Complete Complete Complete 6/22 12/22 2023
Responsibility: FPUA June 2022 Update • On June 21 2022, the 2022 bond series final closing was completed and the funds have been acquired. • Staff is preparing a contract for 60% design for board approval. This contract is tentatively scheduled for a meeting in July. • FPUA DOU and City Manager will develop solution for disposition of property for the benefit of both entities.