FORT PIERCE Strategic Plan 2021 Goals GOAL 8: Porpoise Park Design: Funding and Direction Key Issues Parking Lot Connection to Beach Crossing Natural Dunes
1. CONFERENCE AGENDA: Design and Proposed Budget 2. Bid Project 3. DECISION: Award construction contract 4. Open
2/21 8/21 10/21 1/22
Responsibility: City Engineer
August 1, 2021 Update FDOT has approved second driveway connection. Plans and specifications have been completed and bids are currently being solicited for construction.