GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions

GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions

Key Issues

 Design  Construction  Funding 1. Prepare report 2. CONFERENCE AGENDA: Report

Presentation and Direction 8/21 10/21

3. DECISION: Design Contract

12/21 4. Complete design 3/22 5. DECISION: Award construction contract 5/22 6. Construction 2022

Responsibility: City Engineer

August 1, 2021 Update

Memorandum of Understanding has been accepted by Lawnwood Regional Medical Center. This agreement has been forwarded to our consultant to prepare submittal to FDOT. This appears to be the only outstanding issue remaining for permit approval.