GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions
GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions
Key Issues
Design Construction Funding 1. Prepare report 2. CONFERENCE AGENDA: Report
Presentation and Direction 8/21 10/21
3. DECISION: Design Contract
12/21 4. Complete design 3/22 5. DECISION: Award construction contract 5/22 6. Construction 2022
Responsibility: City Engineer
August 1, 2021 Update
Memorandum of Understanding has been accepted by Lawnwood Regional Medical Center. This agreement has been forwarded to our consultant to prepare submittal to FDOT. This appears to be the only outstanding issue remaining for permit approval.