FORT PIERCE Strategic Plan 2021 Goals GOAL 3: Seaplane/Shuffleboard Area: Directions and Actions Key Issues Design Construction Funding
1. Prepare report 2. CONFERENCE AGENDA: Report Presentation and Direction 3. DECISION: Design Contract 4. Complete design 5. DECISION: Award construction contract 6. Construction
8/21 10/21 12/21 3/22 5/22 2022
Responsibility: City Engineer
August 1, 2021 Update Memorandum of Understanding has been accepted by Lawnwood Regional Medical Center. This agreement has been forwarded to our consultant to prepare submittal to FDOT. This appears to be the only outstanding issue remaining for permit approval.