Teamwork Helps Meet Substation & Transmission Line Schedule POWER & ENERGY MARKET n
By Cam Rand
I
n the spring of 2020, Cianbro concluded the installation of County Road Substation in Oakland, Maine, along with seven miles of new direct embedded steel monopole 115 kV transmission line which tied into the new substation. Cianbro’s Power & Energy team began this project in late summer of 2019 when we broke ground at the substation pad with our subcontract partner, Ranger Contracting Inc. With the delayed award of the project, our team acknowledged the urgency to get below-grade construction of the 115/34.5/12.47kV substation complete before winter set in. As work progressed in the yard, below grade with oversight from Project Assistant Superintendent Jeremy Moody and Design Specialist Ryan Lockhart, the team in the control house, led by Patti Brann, was executing a well-orchestrated plan to complete the fit-out of the control house. As foundations were placed and grades established, Jordan Lyford and his team continued diligently in the field with yard conduit and ground grid installations. The T-line scope of work started with the installation of seventy-four 48-inch and 60-inch culverts for the direct embedded poles. By early fall, the first steel pole for the new line, Section 241, was spotted and installed by Scott Bumps, DJ Robinson, and team. All resources and team members’ focus was then directed toward completing the Interstate 95 crossing. With this being outage-driven work, all of our Northern New England Transmission & Distribution resources came together and showed superior team work in executing this large scope of work within a tight schedule. By the turn of the year the team, led by Ryan Perkins and Matt Sullivan, were ready to install the new 126,000 feet of 1192 aluminum conductor steel reinforced, and 40,000 feet of optical ground wire.
34
CIANBRO CHATTER