Cianbro Chatter 2021

Page 30

Delivering Infrastructure Projects Efficiently with CM/GC INFRASTRUCTURE MARKET n

By Scott Jason

D

elivering infrastructure projects efficiently, within budget and on time is critical to our customers, particularly our public agency owners. One way public agencies ensure they are delivering projects efficiently is by choosing a delivery method that allocates risk and control to the entity best able to manage it during design and construction. Historically, the two most common methods of project delivery are “Design-Bid-Build” and “Design-Build.” These delivery methods tend to be a one-size-fits all approach and the owner must accept tradeoffs when choosing between the two. Over the last decade, the Federal Highway Administration

has promoted an alternate delivery method called Construction Manager/General Contractor (CM/GC) to overcome limitations of Design-Bid-Build and Design-Build. This method of project delivery allows the client/agency to retain control of the design through a contract with the engineer of their choosing while at the same time having the advantage of utilizing the collective experience and knowledge of the best suited contractor to provide constructability, risk and subsequent cost analysis input during the design process. This process is the best example of working together as a team for a common goal leveraging the strengths of all parties involved. Cianbro has been at the forefront of adopting this new approach from the contractor side and to date, has either completed or is in the process of executing CM/GC projects in Connecticut, Maine, Maryland, and Vermont. The following provides a more detailed look into those projects.

The Walk Bridge & CP243 Dock Yard Project Connecticut Department of Transportation Cianbro is currently working with Connecticut Department of Transportation (CTDOT) on two projects that are part of the overall Walk Bridge Program in Norwalk, Connecticut. What originally started as one project to replace the existing swing bridge evolved into two projects out of necessity. It was determined during the procurement and CM process that additional rail work was needed to avoid any significant impact to the rail service. The CTDOT was able to utilize the extensive experience of the Cianbro joint venture team to accelerate the start of the work, which may have otherwise been delayed, possibly for years. By using the CM/GC team approach, the precursor project referred to as the CP243 Dockyard Project, was designed, refined, and started while the engineering for the Walk Bridge was taking place. The Cianbro team had project execution personnel and estimating teams working on both fronts to advance the projects. Cianbro’s collaboration with the owner and designer has enabled design elements of the Walk Bridge to be

30

CIANBRO CHATTER

simultaneously incorporated into the CP243 Dockyard Project. A prime example of this is the early installation of the replacement submarine cable needed for the new bridge and the advanced utilities packages at two separate locations that must be completed as part of the overall program. These activities are planned to finish in advance of the bridge work allowing for less schedule pressure and risk to the owner and less congestion and overall cost during the major bridge work. Further, by performing the utility work early, the team can


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

25 Year Recognitions for 2019

5min
pages 54-56

Cianbro, Starcon, A/Z Years of Service Anniversaries

35min
pages 46-53

In Memory of Mac Cianchette

5min
pages 44-45

1 Million Hours Without Injury at Marathon Canton

2min
page 41

Cianbro Equipment & Starcon Logistics Integration

3min
pages 42-43

AEP Award Highlights Cianbro’s Commitment to Safety

2min
page 37

Starcon Continues Successful Partnership with Dow

1min
page 40

Starcon Awards Highlight Success

3min
pages 38-39

Cianbro’s First 138kV BOLD Transmission Line

1min
page 36

Meeting Substation & Transmission Line Schedule

3min
pages 34-35

Delivering Infrastructure Projects Efficiently

4min
pages 30-31

Brighton Dam Rehabilitation Project Recognized

1min
page 32

Transmission & Distribution Team Supports Clients

1min
page 33

FEATURE

3min
pages 28-29

Meeting the Challenge for Portsmouth Naval Shipyard

4min
pages 26-27

Market Supports Growth in Southern New England

2min
pages 24-25

Building Long Term Relationships to Meet Needs

1min
page 23

Long Term Growth in the Southeast

1min
page 22

A Creative Solution for a Concrete Problem

1min
page 18

Building Projects Earn Honors

1min
page 19

Cianbro’s Quality Control Certifications

2min
pages 20-21

Puritan & Cianbro Partnership Continues

2min
page 17

FABRICATION & COATING

2min
page 16

Cianbro Helps Reshape Portland’s Waterfront

3min
pages 14-15

Delivering on Modern Healthcare Demands

1min
page 13

Safety Excellence in Trying Times

3min
pages 8-9

MODULAR

1min
page 3

Renovations & Labs Improve Patient Safety

1min
page 10

Cement Receiving & Distribution Terminal Expansion

1min
page 11

Mid-Atlantic Building Group

2min
page 12

Vacant Facility Now Pivotal in COVID Battle

3min
pages 4-5

Welcoming Starcon & A/Z Corporation to the ESOP

1min
page 7

Students Explore Career Opportunities with Cianbro

1min
page 6
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Cianbro Chatter 2021 by Cianbro Corporation - Issuu