Cianbro Chatter 2021

Page 26

Meeting the Challenge for Portsmouth Naval Shipyard INFRASTRUCTURE MARKET n

By Scott Jason

P

ortsmouth Naval Shipyard (PNSY), located in Kittery, Maine, is the U.S. Navy’s oldest continuously operating naval shipyard. Established during the administration of John Adams, the shipyard has a storied history; building and servicing ships, housing prisoners of war and even serving as the backdrop for an International Peace Treaty. For the last 100 years, PNSY has specialized in building and servicing submarines. Due to the Navy’s operational requirements and the limited amount of shipyards with the capability to perform PNSY’s mission, contractors on the base must meet aggressive timelines, manage complex coordination challenges, and make schedule adjustments on short notice. Cianbro has been meeting these challenges at the shipyard with high-profile projects of increasing complexity. Awarded in January 2017, the Caisson Replacement & Seat Repair was a mission-critical project to replace an existing dry dock door (caisson) and rehabilitate the dry dock seat. One of the challenges of the project was how to rehabilitate the dry dock entrance structure without taking the dock out of service. The solution would be what is called a limpet cofferdam. Limpet cofferdams are small cofferdams typically used in ship repair to effect in-water hull repairs. This innovative approach provided a dry workspace large enough to allow team members to complete concrete repairs below the surface without taking the dry dock out of service. In addition to the seat repairs, Cianbro managed the construction of the new caisson at an offsite facility by our partner Steel America, as well as replacement of a sluice gate and conduit grate at the dock entrance, concrete repairs to the interior of the dock walls and the installation of a new dock stairway system. The project was successfully delivered on time in the spring of 2020. Awarded in November 2016, Cianbro modernized over 1,200 feet of pile-supported open wharf structures in front of an active dry dock. The team installed a king pile-supported precast concrete shutter panel wall and sheet pile bulkhead. 26

CIANBRO CHATTER

The challenges were schedule and logistics. The Navy had a “must meet” aggressive timeline to accommodate a fixed submarine berthing schedule, with limited shore side space to accommodate equipment, personnel, and material. Cianbro mobilized a significant portion of marine equipment including specialized jack up barges, deck barges and sectional crane barges with specialized cranes to reduce the shore side footprint. Through a partnering relationship, appreciation for the clients and needs and the commitment of the greater team toward the accomplishment of the mission, Cianbro substantially completed the project on time in March 2020. In mid-2017, Cianbro was selected as the successful bidder for a submarine support complex. Shortly after receiving notice of award, the mission of the project was changed to meet the mission needs of the shipyard facility. For the next several months, the Cianbro team worked alongside with the PNSY Naval Facilities Engineering Command (NAVFAC) and engineering teams to get the new design and construction of the project under way in an unprecedented short window of time. The work was broken into packages and put into execution with amazing speed and efficiency. This project included the construction of multiple complex industrial buildings that required strict compliance and was surrounded by numerous other planned and ongoing projects. Portions of the work were subcontracted to specialty subcontractors with the experience in execution of this type of work for the Navy in the past. Structural steel, metal siding panels, electrical and controls, unique HVAC systems, etc. are just some of the critical pieces of work needed to deliver this project. Work continues on the complex as Cianbro works closely with NAVFAC, it’s engineers and shipyard customers to bring this unique project to successful completion. Awarded in December 2019, the P-310 Superflood Project is the first phase of the largest and most technically complex infrastructure project the Navy has undertaken in years. The project involves constructing the foundational basin of what will become two new multi-mission dry docks needed to service the Navy’s future fleet of submarines. The work entails construction of large concrete filled cellular cofferdams to extend the existing structures, fabrication, delivery and installation of a more than 5,000-ton precast concrete entrance


Turn static files into dynamic content formats.

Create a flipbook

Articles inside

25 Year Recognitions for 2019

5min
pages 54-56

Cianbro, Starcon, A/Z Years of Service Anniversaries

35min
pages 46-53

In Memory of Mac Cianchette

5min
pages 44-45

1 Million Hours Without Injury at Marathon Canton

2min
page 41

Cianbro Equipment & Starcon Logistics Integration

3min
pages 42-43

AEP Award Highlights Cianbro’s Commitment to Safety

2min
page 37

Starcon Continues Successful Partnership with Dow

1min
page 40

Starcon Awards Highlight Success

3min
pages 38-39

Cianbro’s First 138kV BOLD Transmission Line

1min
page 36

Meeting Substation & Transmission Line Schedule

3min
pages 34-35

Delivering Infrastructure Projects Efficiently

4min
pages 30-31

Brighton Dam Rehabilitation Project Recognized

1min
page 32

Transmission & Distribution Team Supports Clients

1min
page 33

FEATURE

3min
pages 28-29

Meeting the Challenge for Portsmouth Naval Shipyard

4min
pages 26-27

Market Supports Growth in Southern New England

2min
pages 24-25

Building Long Term Relationships to Meet Needs

1min
page 23

Long Term Growth in the Southeast

1min
page 22

A Creative Solution for a Concrete Problem

1min
page 18

Building Projects Earn Honors

1min
page 19

Cianbro’s Quality Control Certifications

2min
pages 20-21

Puritan & Cianbro Partnership Continues

2min
page 17

FABRICATION & COATING

2min
page 16

Cianbro Helps Reshape Portland’s Waterfront

3min
pages 14-15

Delivering on Modern Healthcare Demands

1min
page 13

Safety Excellence in Trying Times

3min
pages 8-9

MODULAR

1min
page 3

Renovations & Labs Improve Patient Safety

1min
page 10

Cement Receiving & Distribution Terminal Expansion

1min
page 11

Mid-Atlantic Building Group

2min
page 12

Vacant Facility Now Pivotal in COVID Battle

3min
pages 4-5

Welcoming Starcon & A/Z Corporation to the ESOP

1min
page 7

Students Explore Career Opportunities with Cianbro

1min
page 6
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Cianbro Chatter 2021 by Cianbro Corporation - Issuu