PROJECT HIGHLIGHTS
City of Venice Resurfacing Contract The City of Venice hasn’t had a paving project of this size in a few years and this project had some major roads that were in need of repair. The commercial area located near our Main office in North Venice, which encompassed Triple Diamond Blvd, Technology Dr and Precision Dr are three of the main feeders to major Venice Commercial Businesses. These roads were reconstructed around business schedules to accommodate their deliveries and employees. We also resurfaced the Pinebrook neighborhood and placed brand new sidewalk down the main stretch of Pinebrook Way. We also resurfaced the commercial area near downtown Venice: Warfield Ave, Grove St and Spur St. We replaced the concrete apron to the fire station and accommodated their trucks during this process. Later in the project, we resurfaced and fixed issues on San Marco, Riviera and Bayshore Dr. This extra work included replacing storm drain at the main intersection downtown at Harbor Dr and Venice Project Write-up by: Nathan Hassler, Project Manager
Ave, as well as replacing the brick pavers that had settled with the new stamped asphalt. Project Superintendent duties were split between Wally Cabral and Cameron Milliken. Both did an incredible job completing this project for the City of Venice. PROJECT BID: 2.7 Million TONNAGE: 27,000
SR 776 Scope of Work: A well laid out plan from the beginning made this project run very smooth. SR 776 consisted of mill and overlay, signal and lighting updates, concrete sidewalk, curb & gutter, ADA improvements, guardrail, sod and striping. We were very ambitious to tackle this job and complete it in a short time. The vision we had was well communicated and accepted from all those involved; from superintendent, foreman, crews, subcontractors, to management. The communication did not stop there. We had buy-in from the DOT with such an aggressive schedule knowing any issues would need to be handled at the lowest level if possible. It was great to have a team from owner and contractor that made this such a success. We had a dream, a vision and a team. Teamwork DID make this dream work! Fantastic job to everyone involved! It was an honor to see something so well planned come together with such ease and determination. 12
CONTRACT AMOUNT: $2,068,027.15 TONNAGE: 4,000 tons 12.5 C
Project Write-up by: Chad Schmidtke, Project Manager AJAX ANNUAL MAGAZINE • 2020
1,850 tons FC-5