BRAUN Maschinenfabrik received the order to deliver a movable bridge wire saw, to dismantle 6 steam generators / heat exchangers in the Russian nuclear power plant Nowoworonesch, to VIP-Systems. The

end customer, ROSATOM, is the world's largest nuclear company. The planning of the movable bridge wire saw with integrated gantry crane began already 2017. The order intake was in May 2018. It was built from August to November. The first assembly and commissioning took place at the end of November in Vรถcklabruck and took just under two weeks.