AIT Waste Water Treatment Facility: Activity Attributes
ID: 1043 Activity: Sequencing of Project Activities Description of Work: Responsible party: TNLS This activity requires the Identification and documentation of relationships among the project activities, by means of a network diagram.
Activity Predecessors:
Lead or Lag:
Activity Successors:
Lead or Lag:
Preparation of a Milestone List
No lead or lag
Estimate Activity Resource Requirements
No lead or lag
Activity Cost â‚Ź 390.00
Activity effort: 8.7 Hours
Activity Resource Requirements Input from project parties
ID: 1044 Activity: Estimate Activity Resource Requirements Description of Work: Responsible party: TNLS This activity involves estimating the type and quantities of material, people, equipment and supplies required to perform each activity, and formulating a resource breakdown structure.
Activity Predecessors:
Lead or Lag:
Activity Successors:
Lead or Lag:
Sequencing of Project Activities
No lead or lag
Estimate Activity Effort
No lead or lag
Activity Cost â‚Ź 405.00
Activity effort: 9.0 Hours
Activity Resource Requirements Contact with experts, resource calendars etc.
23