AIT Waste Water Treatment Facility: Activity Attributes

ID: 1043 Activity: Sequencing of Project Activities Description of Work: Responsible party: TNLS This activity requires the Identification and documentation of relationships among the project activities, by means of a network diagram.

Activity Predecessors:

Lead or Lag:

Activity Successors:

Lead or Lag:

Preparation of a Milestone List

No lead or lag

Estimate Activity Resource Requirements

No lead or lag

Activity Cost â‚Ź 390.00

Activity effort: 8.7 Hours

Activity Resource Requirements Input from project parties

ID: 1044 Activity: Estimate Activity Resource Requirements Description of Work: Responsible party: TNLS This activity involves estimating the type and quantities of material, people, equipment and supplies required to perform each activity, and formulating a resource breakdown structure.

Activity Predecessors:

Lead or Lag:

Activity Successors:

Lead or Lag:

Sequencing of Project Activities

No lead or lag

Estimate Activity Effort

No lead or lag

Activity Cost â‚Ź 405.00

Activity effort: 9.0 Hours

Activity Resource Requirements Contact with experts, resource calendars etc.