Timeline Date
Action
Result
Nov. 18, 2015
Board of Directors gives final approval of construction plans and budget
Project moves ahead
Dec. 2, 2015
Official announcement to parent community at Building Our Future event
Project and capital campaign becomes public to parents
Dec. 15, 2015
Alumni event
Announcement to alumni community
Jan. 22, 2016
York Parents Association morning parent meeting
Board Chair and Head of School present project details and The 1320 Challenge
Jan. 26, 2016
Official announcement to students following exams
Project is now public knowledge within the entire school community
Mar. 2016
Phase I
Construction begins
Parking lot off of Farnham Ave. closes
All pick up and drop off traffic rerouted through laneway just south of 1320 Yonge Street
Construction begins on temporary classroom space
Area under gym is fenced off and no longer accessible to students and vehicles. Turf remains open.
Junior and Middle/Senior School York Shop locations close
All uniform sales move online following the March Break
May 13, 2016
Annual Night on the Town
Annual parent event will include Fast Forward groundbreaking ceremony
June 2016
Phase II begins on second and third floors and on front facade
All staff relocated to 1639 Yonge Street or alternate location
Sept. 2016
Phase I opens
Classes and student activities commence on third and fourth floors. First and second floors remain closed.