GENERAL NOTES 1. 2.
location of work Apt. 12D & 12E
4" 4'20 12
0'-
2008 Smoke/ Carbon Monoxide Detector Notes
Drawing List
0"
A-100.00
Cover Sheet, Plot Plan, Key Plan, Notes
DM-101.00
Demolition Plan
A-102.00
Construction Plan
A-103.00
Reflected Ceiling Plan
1. 2. 3. 4.
A-104.00
Exterior Elevation @ Kitchen Window
E-100.00
Electrical Plan
5.
M-100.00
Mechanical Floor Plan
6.
P-100.00
Demolition Floor Plan
P-101.00
Plumbing Floor Plan
7. 8. 9.
P-200.00
Plumbing Details, Notes and Riser Diagrams
10.
P-201.00
Plumbing Specifications
11. 12. 13. 14.
Smoke/ Carbon Monoxide detectors or devices shall be installed in ordinance with the Housing Maintenance Code. Multiple Dwelling Law, the New York Building Code, the New York City Electrical Code and NFPA 72. Smoke Detectors and Carbon Monoxide Detectors may be combined providing the devices comply with the provisions of title 28 of the administrative code of the city of New York and any applicable rules promulgated thereunder. Each Smoke/ Carbon Monoxide Detector shall be installed in accordance with Reference Standard UL 2034 and UL 2075 of the New York City Building Code. Each Smoke/ Carbon Monoxide Detector shall be installed outside of each sleeping room in the immediate vicinity of within 15'-0" of the entrance to a sleeping room; inside each sleeping room; and on each story within a dwelling unit, including below grade stories and penthouses per 908.7.1.1.1. Each Smoke/ Carbon Monoxide Detector shall be of a type that allows for readily testing of such a device. Duplex units shall have a device located on each level if only one means of egress is provided from each level. Ceiling mounted devices shall be a minimum distance of 4" from any wall. Wall mounted devices shall be a minimum of 4" to a maximum of 12" from the ceiling. Each dwelling unit shall be equipped with an approved type smoke/ carbon monoxide detector device receiving primary power from the building wiring with no switches in the circuit other than the over current device protecting the branch circuit as per New York City Building Code Sec. 907.2.10.2 through 907.2.10.4. Existing buildings that are not equipped with hardwired connections shall be supplied with battery operated devices. Such Smoke/ Carbon Monoxide Detector must be either the ionization chamber type or the photoelectric detector type as per New York City Building Code Sec. 907 and 908. A "Certificate of Satisfactory installation for Smoke/ Carbon Monoxide Detector" must be filed with the division of code enforcement H.P.D., 10 days after installation. Written information of testing and maintenance of the devices shall be provided to the dwelling unit owner. In multiple dwellings (R-2), smoke alarms shall be able to support visible alarm per ANSI A117.1.
Tenant Protection Plan 28-104.8.4 Tenant protection plan. Construction documents for alterations of buildings in which any dwelling unit will be occupied during construction shall include a tenant protection plan. Such plan shall contain a statement that the building contains dwelling units that will be occupied during construction and shall indicate in sufficient detail the specific units that are or may be occupied during construction, the means and methods to be employed to safeguard the safety and health of the occupants, including, where applicable, details such as temporary fire-rated assemblies, opening protective, or dust containment procedures. The elements of the tenant protection plan may vary depending on the nature and scope of the work but at a minimum shall make detailed and specific provisions for: 1.
2. 3.
4.
5. 6.
Egress. At all times in the course of construction provision shall be made for adequate egress as required by this code and the tenant protection plan shall identify the egress that will be provided. Required egress shall not be obstructed at any time except where approved by the commissioner. Fire Safety. All necessary laws and controls, including those with respect to occupied dwellings, as well as additional safety measures necessitated by the construction shall be strictly observed. Health requirements. Specification of methods to be used for control of dust, disposal of construction debris, pest control and maintenance of sanitary facilities, and limitation of noise to acceptable levels shall be included. 3.1 There shall be included a statement of compliance with applicable provisions of law relating to lead and asbestos. Compliance with housing standards. The requirements of the New York City housing maintenance code, and, where applicable, of the New York City housing maintenance code, and where applicable, the New York State multiple dwelling law shall be strictly observed. Structural safety. No structural work shall be done that may endanger the occupants. Noise restrictions. Where hours of the day or the days of the week in which construction work may be undertaken are limited to the New York City noise control code, such limitactions shall be stated.
Scope of Work: All work shall fully conform to the requirements of New York City Building Code, Fire Department Rules and Regulations, utility company requirements, and the best trade practices. 3. Before commencing work, the contractor shall file all required insurance certificates with the Department of Buildings, obtain all required permits, and pay all fees required by the governing New York City agencies. 4. Minor details not usually shown or specified, but required for proper construction of any part of the work shall be included as if they were indicated in the drawings. 5. The contractor shall coordinate all work procedures with the stipulations of local authorities, building management or board of directors. 6. The contractor shall be responsible for the protection of all conditions and materials within the proposed construction area. The contractor shall design and install adequate shoring and bracing for all structural or removal tasks. The contractor shall have sole responsibility for any damage or injuries caused by or during the execution of the work. 7. The contractor shall lay out his own work, and shall provide all dimensions required for other trades: plumbing, electrical, etc. 8. Plumbing work shall be performed by persons licensed in their trades, who shall arrange for and obtain through the Department of Buildings all required permits, inspections and required sign-offs. 9. Electrical work shall be performed by persons licensed in their trades, who shall arrange for and obtain through the Bureau of Electrical Control all required permits, inspections and required sign-offs. 10. The contractor shall do all cutting, patching, repairing as required to perform all of the work indicated on the drawings, and all other work that maybe required to complete the job. 11. All piping and wiring shall be removed to a point of concealment and shall be properly capped or plugged.
Tenant Safety Notes: Residential Renovation No change of use, occupancy, or zoning this application N
1
block: 1147 lot: 7501 Zone: C2-7A, R8B Map: 8C
ENERGY STATEMENT: To the best of my knowledge, belief, and professional judgement, this application is exempt from compliance with the 2011 NYCECC, USN# 06101.009566
plot plan n.t.s.
204'-4"
1.
General: All work to be completed in accordance with the New York City Building Code, Article 33, and regulation of all other agencies having jurisdiction.
2.
Means of Egress: All existing means of egress for tenants of the building to be maintained clear and free of all o obstructions, such as building materials, tools, etc.
3. a.
Fire Safety: All building materials which are stored at the site or any area of the building are to be stored in a locked area. Access to the area to be controlled by the owner, or the General Contractor. All materials to be stored in an orderly fashion. All flammable materials to be kept tightly sealed in their respective manufacturers’ containers. Such materials are to be kept away from heat. All flammable materials to be used and stored in an adequately ventilated space. All electrical power to be shut off where there are exposed conduits. All electrical power in the construction area to be shut off after working hours. Contractor, at all times, to ensure there is no natural gas leakage in the buildings, or any flammable gas to be used during construction.
b. c. d. e. f. g.
Amsterdam Avenue
4. a. b.
open to (2nd Flr.) below
open to (cellar) below
adjacent building
open to (1st Flr.) below
5. a. b.
Noise after Hours: Construction operations will be confined to normal working hours: 8am to 6pm, Monday to Friday, except legal holidays. Contractor must obtain written permission from all affected parties to work other than regular hours.
6.
Construction Operations will not involve interruption of heating, water, or electrical services to other tenants.
7.
Construction work will be confined to the apartment interior, and will not create dust, dirt, or other such i inconveniences to the other apartments units within the building.
8.
There will be no one occupying the premises to be renovated during the course of the construction work.
List of Inspections Special Inspections:
open to (cellar) below
area of work Apt. 12E. & 12D
W 76th Street
open to (2nd Flr.) below
120'-0"
open to (1st Flr.) below
1. Mechanical Systems 2. Firestop, Draftstop, and Fireblock Systems
E.S.
Progress Inspections:
open to (7th Flr.) below
59'-0"
W 75th Street
c.
Dust Control: Debris, dirt, and dust to be kept to a minimum and confined to the immediate construction area. Contractor to isolate construction area from occupied building area by means of temporary partitions or heavy w eight drop cloths. Debris, dirt, and dust to be cleaned up and cleared from the building site periodically to avoid excessive accumulation
E.E. E.S.
open to (1st Flr.) below
1. Preliminary 2. Fire-Resistance Rated Construction 3. Final Inspection
Endres Lyons Residence 161 West 75 St. , 12th Floor Apt. 12 D & E New York NY 10023
Page Goolrick Architect P.C. open to (cellar) below
open to (1st Flr.) below
20 W 22nd Street NY NY 10010 phone 212.219.3666
email pg@goolrick.com
www.goolrick.com
indicates apartment, area of work indicates demised space
2
key plan n.t.s.
E.S.
- existing egress stairs
E.E.
- existing elevator
title:
Cover Sheet, Plot Plan, Key Plan, Notes BOARD REVIEW SET
scale: varies date:
31 January 2014
A -100.00 Page 1 of 6