Prestige Internal Finishing

Prestige understands the importanceof havingconfidence inthe homewhen it comes to handing a newly sited home over to the Homeowner.

The Internal Finishing Team (IFT) will support the Park Owners to ensure every aspect of the new unit is ready for the Homeowner to move straight into. The team will check the externals, complete all internal finishing, review, action snags and bring any shortages to complete the home, ready for the final customer-ready clean and propping by the Park.

As a manufacturer we believe that working in partnership with Parks is the best way that we can provide support. Continuity is vital and is the basis of a strong and solid relationship with both Park Managers and, where appropriate, the Homeowners.

The Park’s preferred Hauliers will be used to transport the home and carry out the external siting (up level and watertight), as per the PSL. Prestige will then make arrangements with the Park for their dedicated Engineers to attend and carry out theInternal Finishingoncethehome has been connected to the main services.

Ordinarily the IFT will attend site between 7-10 days following despatch, to allow time for siting, externals and commissioning of the home. We appreciate that due to timings for the bases, homes can be held in storage for a time before siting commences. This can be planned with your Account Manager, rather than an automatic plan to attend after despatch. Alternatively, if a home is likely to be commissioned earlier than 7 days, we can plan this in advance with the team.

The Internal Finishing process itself can takebetween 1-3 days, dependent on the complexity of the home, and willinclude a197-pointcheck designed to ensurethehome is handedover tothestandard weexpect.

We request that all Internal Finishing is carried out once the home has been connected to the main services, to ensure that our Engineers can complete the finishing to the highest standard. The commissioning is necessary for effective lighting, heating, drying times during the wet works and for effective snagging and plumbing and electrical testingthroughout which is beneficial to both parties.

Key Areas Covered During Internal Finishing

 Checkthehomeis level and theexternalsitinghas been carriedout toPrestige’s satisfaction.

 Inspect the exterior ofthehome forany damage which may haveoccurred during transportation, such as to guttering, fascia's and soffits.

 Adjust exterior windows & door if necessary to ensure they are level and check that allthe lockingmechanisms operate correctly.

 Checkexteriorwindows&doorsaresealed.

 Fitinternaljoiningstrips.

 Checkallplumbingconnections.

 Inspectinternaldoorsfordamageandensurethattheyareworkingcorrectly.

 Inspectand test kitchenappliances.

 Inspectkitchenequipmentincludingsinks,worktopsanddoorfronts.

 Inspectelectricalitemseg:switches,socketsandlightfittings.

 Inspectcurtains andblinds,andcheckthatthey areoperatingcorrectly.

 Assemble allfurniture supplied by Prestige and set up in accordance withthe floor plan ofthe home.

 Inspect, installandcommission fireplaceifdesignedtosit acrossthejoin(twin homesonly).

 InspectBathrooms/en-suitesincluding toilets,basinsandshowers. Adjusttapsifnecessary.

 Inspectbedroomfurnitureincludingbeds/mattresses.

 Completeflooring,i.e.carpets,vinyl,laminateandtiling.

 Removalallpackaginganddebrisfromtheunit.

 Completeathoroughbuilderscleanthroughoutthehome.

 Completethe handoverand formally signoffthe home with thePark Representative.

Internal Finishing – Engineers checklist and sign off form

Team Park Name

SerialNo

Model

Size

IF Date

Customer Name

TimeAllowed Inc. Travel

TimeTaken

Transported By

Shortages Y ☐/ N ☐ Up Level&Watertight Y ☐ / N ☐

Please note: If shortages are reported, please detail on the attached handover and final report page

Special Home requirements

Laminateflooringtobefinishedonsite ☐

Tilingto befinished onsite ☐

Concealed joins ☐

Carpettobefinishedonsite ☐

Vinylto befinished onsite ☐

Booking in Checklist YESNO

Willhomebe connected tothemain services uponarrival ofengineers

Willa representativefromthe park be presentforwalkthrough/signoff

If representative is available, please specify name of person

All packaging & waste to be disposed of in (area)

1) Exterior/ windows and doors Complete Incomplete

Check levelof home & that jacks are tight

Checkexteriorfinish forany damageto walls & driprail ifapplicable

Roof–Visually checkridge& flashings havebeen installedcorrectly

Fascia,soffits& bargeboard joins –visuallycheckifinstalledcorrectly

Check forsigns ofgutter leaks ordamage & that downpipes are secure

Check allwindows & doorsaresealed as required

Check alltricklevents& drainageplugs

Check&adjust allexteriorwindows& doors(opening/locking)

Checkalllockingmechanismsareassembled&operatecorrectly

Checkifunderfloorpads areinstalled

Check hook& eyesarefitted whereapplicable

2) Boiler and radiators

Check allradiators/towelrails arestill securely on brackets

Checkboilerinstructionmanualhas beensuppliedin home

3) Plumbing

Check alltaps& wasteconnectionstosinks&basins

Checkallwastepipeconnectionsofwhitegoods

4) Entrance/ hallway

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

4) Entrance/ hallway (cont)

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkcurtains/blindsareoperatingcorrectly& inspectfordamage

Check curtain poles/trackfordamage

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectricalsocket face plates arelevel& installed securely

5) Lounge

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly& inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkcurtains/blindsareoperatingcorrectly& inspectfordamage

Check curtain poles/trackfordamage

Check fireplace fordamage& installifapplicable

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectricalsocket face plates arelevel& installed securely

6) Diner

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectify whereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkcurtains/blindsareoperatingcorrectly& inspectfor damage

Check curtain poles/trackfordamage

Unpackany furniture& assembleifapplicable –checkfordamage

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectrical socket face plates arelevel& installed securely

Complete Incomplete

7) Kitchen Complete Incomplete

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectify whereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkallappliancesarecorrecttospecification&areinstalledcorrectly

Checkallappliancesfordamage

Performa testcycleonwashingmachinetocheckplumbing

Performa test cycleon dishwasherto checkplumbing

Checksink forscratches/damage

Checksplash back/upstandshavebeeninstalledcorrectly/sealed

Check that alldoors arelevel & adjustifrequired

Check drawersarerunning correctly& adjustifrequired

Checkworktops&mitrejoints

7) Kitchen Complete Incomplete

Checkinstallation& fordamageoncornice,light pelmets& plinths

Checktiling –installation&grouting

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingordamaged light fittings

Check that allelectricalsocket face plates arelevel& installed securely

8) Bedroom 1 / Dressing room (if applicable)

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkmattressesfordamage

Check fordamage towardrobes

Checkdooralignmenttowardrobes& adjustwherenecessary

Check drawersarerunning correctly& adjust ifrequired

Installanymirrors asperspec/plan& check fordamages

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectricalsocket faceplates arelevel& installed securely

9) Bedroom 2 / Dressing room (if applicable)

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/ scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkmattressesfordamage

Check fordamage towardrobes

Checkdooralignmenttowardrobes& adjustwherenecessary

Check drawersarerunning correctly& adjustifrequired

Installanymirrors asperspec/plan& check fordamages

Installwall/ceilinglightfittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectricalsocket face plates arelevel& installed securely

10) Bedroom 3/ 4 (if applicable) Complete Incomplete

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checkmattressesfordamage

Check fordamage towardrobes

Checkdooralignmenttowardrobes& adjustwherenecessary

Installanymirrors asperspec/plan& check fordamages

Installwall/ceilinglight fittingswhereapplicable

Checkforanymissingor damaged lightfittings

Check that allelectricalsocket face plates arelevel& installed securely

11) Study (if applicable) Complete Incomplete

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Unpack anyloosefurniture&assembleifapplicable –check fordamage

Checkforanymissingordamaged light fittings

12) Bathroom Complete Incomplete

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checktiling – fitting& grouting

Checkinstallationoftoilet cistern, checkseal&checkseatis tight

Check basin/bathtapsaretight & not damaged

Checkpedestalsarefittedstraight

Check basins& vanityfordamages

Checkifextractoroperatescorrectly

Checkextractor fan covershavebeenfittedcorrectly& level

Checkextractor has been fittedcorrecttothespec/plan

Checktoiletrollholder/towel railsarefittedifapplicable

Adjustshowercubicledoorsifrequired

Adjust showerscreen tobathifrequired

Check allsealant totheshower trays/cubicles

Checkmirrors fordamages& installifapplicable

13) En-suite Complete Incomplete

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Checktiling – fitting&grouting

Checkinstallationoftoilet cistern, checkseal&checkseatis tight

Check basin/bathtapsaretight & not damaged

Checkpedestalsarefittedstraight

Check basins& vanityfordamages

Checkifextractoroperatescorrectly

Checkextractor fan covershavebeenfittedcorrectly& level

Checkextractor hasbeen fittedcorrecttothespec/plan

Checktoiletrollholder/towel railsarefittedifapplicable

Adjustshowercubicledoorsifrequired

Adjust showerscreen tobathifrequired

Check allsealant totheshower trays/cubicles

Checkmirrors fordamages& installifapplicable

14) Cloakroom cupboard (if applicable)

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Check coat hooks havebeensupplied& installed

15) Airing cupboard

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhere needed

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly &inspectfordamage

Checkskirtingfordamage/scuffs& rectify where needed

Checkfloorcovering

Check shelvinghas been installed & is level

Checkifelectricalheaterisinstalled &operatingcorrectly

16) Boiler cupboard

Checkwallsareinstalledcorrectly, inspectfordamage& rectify ifneeded

Checkceiling fordamage/scuffs & rectifywhereneeded

Checkcovingfordamage/scuffs & rectifywhereneeded

Checkarchitravesfordamage/scuffs&rectifywhereneeded

Checkinterior doorsareoperatingcorrectly& inspectfordamage

Checkskirtingfordamage/scuffs& rectify whereneeded

Checkfloorcovering

Incomplete

Incomplete

17) Final checks Complete Incomplete

Removeallpackaging& disposeofproperly at thedesignatedpoint

Hooverhomethroughout

Cleanallsurfacesthroughouthome

Finalsweep throughfor wall scuffs/chips topaintwork

Checkdoorstopsarefittedwhereapplicable

Ensurefurniture is setoutcorrectly asper floorplan

Find park representative (details on first page of this report) to begin hand over

Internal Finishing – Handover and final report

Please list below any comments from handover with park operator List any damages or shortages on this home

I confirm that the Internal Finishing works have been satisfactorily completed except for the items marked as not complete and the comments listed above.

Park Operator Name:

Park Operator Signature Date

Engineer Signature Date

Please return this form to head office once completed – thank you

Intentionally Blank

Turn static files into dynamic content formats.

Create a flipbook
Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.
Internal Finishing & Customer Care by PrestigePLH - Issuu