D: Design Review Flowchart
Owner determines Builder/Designer for homeproject Submit Approved Designer Application for DRC review and qualification


DRC to approve designer



PreliminaryPlans remitted to DRCAdmin Complete DRC Application with all fees remitted >10 days prior to scheduled DRC meeting


DRCAdmin to remit plans to 3rd party Architectsfor complete review
Design Plans and comments from Architect are reviewed with DRC
Plan addedto agenda for DRC Meeting



Committee Review, feedback solicited

Approved or Denied?

Feedback provided within30 days of DRC Meeting Owner/Builder to remit revisionsas stated in the review summary



Revise Plans,
respond to all bolded review items
Upon receipt of deposits, DR Admin will schedule PreConstruction Conference


Construction Begins!
Construction must begin within 18 months of DRC approval Note that final plans may be resubmitted once without penalty, repeat re-submittals will require a $500 fee per review
Revised plans must be remitted >10 days prior to scheduled DRC meeting with responses to all bolded items from review
Designer/Builder is notified of denial within 30 days of DRC meeting listing items that must comply
If plans are not approved, must resubmit within 12 months or re-apply with all fees
Secondary submittal due in 30 days: Sample Board
Submit request for FINAL INSPECTION